# Criteria for synchronizing two alternators

Electrical Machine · Chapter 6: Three Phase Synchronous Machines

- Asked in: 2068 Magh, 8 marks
- Video: [HOW TO PARALLEL SYNCRONOUS GENERATOR | ACTUAL SYNCHRONIZATION](https://www.youtube.com/watch?v=pA2hXHpgKEY) — leckyjake
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_4/electrical_machine/synchronizing-two-alternators-criteria
- Whole chapter: https://www.bctengineer.com/md/semester_4/electrical_machine/chapter-6

## Question

Write down the criteria for synchronizing two 3-Ø alternators with the detail explanation.

## Short answer

The incoming alternator must match the bus in voltage magnitude, phase sequence, frequency, and phase angle at the instant of closing. These are checked with lamp methods or a synchroscope; the breaker is closed during dark lamps or when the pointer is at 12 o'clock.

## Answer

Synchronizing (paralleling) means connecting an incoming alternator to a live bus (or another alternator) without disturbing the system. If the conditions are not met, a large circulating current and a mechanical shock result when the switch is closed.

#### Conditions (criteria) for synchronizing
1. **Equal terminal voltage (rms).** The terminal voltage of the incoming machine must equal the bus voltage. Adjust its field current to match. If the voltages differ, a (reactive) circulating current I = ΔE / (Z_s1 + Z_s2) flows, which heats the windings.
2. **Same phase sequence.** The phase sequence (RYB) of the incoming machine must match that of the bus. Otherwise the phase voltages are not in step and a short circuit results. It is checked with a phase-sequence indicator, or with the three-dark-lamp method (all lamps going dark and bright together shows the correct sequence).
3. **Equal frequency.** The frequency of the incoming machine must equal the bus frequency. The prime-mover speed (governor) is adjusted until the frequency difference is very small. With unequal frequencies, the voltages beat and the phase difference between the machines changes continuously.
4. **Phase coincidence.** The voltages must be in phase at the instant of closing the switch (zero phase-angle difference). This is checked with a synchroscope or the lamps.
5. **Same waveform** (sinusoidal), to avoid circulating harmonic currents.

#### Methods of checking
**Three dark lamp method:** three lamps are connected between corresponding terminals of the incoming alternator and the bus. If the sequence is correct and the frequencies are close, the lamps flicker (dark and bright) together at the difference frequency. The breaker is closed in the middle of the dark period, when a voltmeter across a lamp reads zero.

**Two bright, one dark lamp method:** one lamp is connected straight and the other two are cross-connected. With the correct sequence the lamps light up one after another (a rotating light), and the direction of rotation shows whether the incoming machine is fast or slow. The breaker is closed when the straight-connected lamp is dark and the two cross-connected lamps are equally bright.

**Synchroscope:** its pointer rotates at the difference frequency, clockwise if the incoming machine is fast. The breaker is closed when the pointer is at the 12 o'clock (vertical, zero phase angle) position.

#### Procedure
1. Start the prime mover and bring the speed close to rated speed.
2. Adjust the field current until the voltmeter shows a voltage equal to the bus voltage.
3. Adjust the speed to bring the frequency to the bus frequency (slow pointer rotation).
4. Close the breaker at the synchronising instant.
5. Increase the prime-mover input so that the machine takes up load.

```text
  Incoming       Bus
  alternator --[ 3 lamps / synchroscope ]-- bus
              \__ breaker closed when dark / pointer at 12
```

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Which is NOT a required synchronizing condition?
   A. Equal terminal voltage
   B. Same phase sequence
   C. Equal output power
   D. Equal frequency and phase coincidence
   Answer: C. Voltage, sequence, frequency and phase coincidence must match; power sharing is adjusted afterwards. (Key point: Criteria)

2. What happens if the voltages differ at closing?
   A. Reactive circulating current flows
   B. Frequency changes
   C. Phase sequence reverses
   D. No effect
   Answer: A. I = deltaE/(Zs1+Zs2) heats the windings. (Key point: Unequal voltage)

3. When is the breaker closed using a synchroscope?
   A. Pointer at 6 o'clock
   B. Pointer at 12 o'clock (zero phase angle) and moving slowly
   C. Pointer rotating fast
   D. Pointer at 3 o'clock
   Answer: B. The pointer rotates at the difference frequency; vertical means phases coincide. (Key point: Synchroscope)

4. When is the breaker closed in the three-dark-lamp method?
   A. Lamps brightest
   B. Middle of the dark period
   C. Lamps flicker fast
   D. Any time
   Answer: B. Lamps dark means zero voltage across the switch. (Key point: Three dark lamps)

## Related in Electrical Machine

- [Criteria for synchronizing two alternators](https://www.bctengineer.com/question.md?key=semester_4%2Felectrical_machines%3Async-alternators-synchronizing-criteria) — Electrical Machines, chapter 6
- [Synchronizing alternators by dark lamp method](https://www.bctengineer.com/question.md?key=semester_4%2Felectrical_machines%3Async-alternators-dark-lamp) — Electrical Machines, chapter 6

## Related in other subjects

- [Fault current: two 500 kVA alternators](https://www.bctengineer.com/question.md?key=semester_7%2Fpower_plant_equipment%3Afault-two-500kva-alternators) — Power Plant Equipment, chapter 4