# Limestone true thickness: A 600 m N28E, C 400 m S10W

Engineering Geology II · Chapter 6: Measurement, analysis and interpretation of structural geological data

- Asked in: 2073 Bhadra, 5 marks; 2070 Bhadra, 4 marks (asked 2 times)
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_4/engineering_geology_ii/bh-limestone-true-thickness-a600
- Whole chapter: https://www.bctengineer.com/md/semester_4/engineering_geology_ii/chapter-6

## Question

Three boreholes A, B and C were drilled for limestone reserve calculation. Borehole A lies at 600 m distance due N28°E from borehole B. Borehole C lies at 400 m distance due S10°W from borehole B. The top and bottom of the limestone bed were encountered at the following depths of the given boreholes.

| Borehole | Top (m) | Bottom (m) |
|---|---|---|
| A | 200 | 260 |
| B | 220 | 280 |
| C | 240 | 300 |

Calculate the true thickness of the limestone bed.

## Short answer

From the three borehole depths, vertical thickness is 60 m. The top-of-bed plane dips 3.9° towards SSE (dip direction 147°), strike N57.4°E. True thickness = 60 × cos(3.9°) = 59.9 m.

## Answer

**Method:** the top of the limestone is at 200 m, 220 m and 240 m depth in A, B and C. All three boreholes are vertical and the bed is 60 m thick in each (260 - 200 = 280 - 220 = 300 - 240 = 60 m), so 60 m is the **vertical thickness**. First find the attitude of the bed (three-point problem), then convert vertical thickness to true thickness.

#### Step 1: coordinates (B at origin, x east, y north)
$$
\begin{aligned}
A &: x = 600\sin 28^\circ = 281.68\ \text{m},\ y = 600\cos 28^\circ = 529.77\ \text{m} \\
C &: x = 400\sin 190^\circ = -69.46\ \text{m},\ y = 400\cos 190^\circ = -393.92\ \text{m}
\end{aligned}
$$

#### Step 2: plane of the top of the bed
Depth to the top: $d = 220 + a x + b y$. Substituting A and C:
$$
\begin{aligned}
200 &= 220 + 281.68a + 529.77b \\
240 &= 220 - 69.46a - 393.92b
\end{aligned}
$$
Solving gives $a = 0.0366$ and $b = -0.0572$ (metres of depth per metre).

#### Step 3: dip and dip direction
$$
\tan\delta = \sqrt{a^2+b^2} = 0.0680 \Rightarrow \delta = 3.89^\circ
$$
The bed becomes deeper towards the direction $(a,b)$, so the dip direction is $\arctan(a/b)$ measured from north = $147.38^\circ$ (toward SSE). The strike is perpendicular to this: $57.38^\circ$, i.e. **N57.4°E**.

**Attitude of the bed: N57.4°E / 3.9° towards SSE** (dip direction 147°).

#### Step 4: true thickness
$$
t = t_v\cos\delta = 60\cos 3.89^\circ = 59.86\ \text{m}
$$
(The bed is almost flat, so the true thickness is only slightly less than 60 m.)

**Answer: true thickness of the limestone = 59.86 m (about 59.9 m); bed dips 3.9° towards SSE.**

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Why is 60 m not the true thickness here?
   A. The boreholes are inclined
   B. It is a vertical thickness measured in vertical holes, and the bed is dipping
   C. The bed is overturned
   D. The depths are wrong
   Answer: B. Vertical holes give vertical thickness; true thickness = vertical thickness x cos(dip). (Key point: Vertical vs true thickness)

2. Which method finds the bed attitude?
   A. Three-point problem using tops at A, B and C
   B. Using only borehole A
   C. Mohr circle
   D. Averaging depths
   Answer: A. The top depths at three non-collinear points define the plane. (Key point: Method)

3. The attitude is about 3.9° dipping SSE. What is the true thickness?
   A. 60 m
   B. 60 sin 3.89° = 4.07 m
   C. 60 / cos 3.89° = 60.14 m
   D. 60 cos 3.89° = 59.86 m
   Answer: D. t = tv cos(delta) = 59.86 m, slightly less than 60 m. (Key point: Dip)

4. With B at the origin, how are A's coordinates found?
   A. x = 600 cos 28°, y = 600 sin 28°
   B. x = 600 sin 28°, y = 600 cos 28° (N28°E, x east, y north)
   C. x = 400 sin 10°
   D. x = y = 600
   Answer: B. A is 600 m at azimuth 28°: x = 600 sin 28° = 281.68 m, y = 600 cos 28° = 529.77 m. (Key point: Coordinates)

## Related in Engineering Geology II

- [True thickness: limestone vertical 600 m](https://www.bctengineer.com/question.md?key=semester_4%2Fengineering_geology_ii%3Atrue-thickness-limestone-600m) — Engineering Geology II, chapter 7
- [Bedrock attitude: A 700 m N23E, C S71W](https://www.bctengineer.com/question.md?key=semester_4%2Fengineering_geology_ii%3Abh-hydropower-a700-n23e) — Engineering Geology II, chapter 6
- [Limestone true thickness across stream](https://www.bctengineer.com/question.md?key=semester_4%2Fengineering_geology_ii%3Astream-limestone-true-thickness) — Engineering Geology II, chapter 6
- [Tunnel alignment from three boreholes](https://www.bctengineer.com/question.md?key=semester_4%2Fengineering_geology_ii%3Atunnel-alignment-three-boreholes) — Engineering Geology II, chapter 6
- [Sandstone attitude: A N45W 900 m, C S20E 700 m](https://www.bctengineer.com/question.md?key=semester_4%2Fengineering_geology_ii%3Abh-sandstone-a-n45w-c-s20e) — Engineering Geology II, chapter 6
- [True thickness from apparent thickness 210 m](https://www.bctengineer.com/question.md?key=semester_4%2Fengineering_geology_ii%3Abh-quartzite-thickness-210-attitude) — Engineering Geology II, chapter 6

## Related in other subjects

- [Three-point problem: A 600 m N, C 400 m W (400, 100, 300)](https://www.bctengineer.com/question.md?key=semester_3%2Fengineering_geology_i%3Athreepoint-problem-a-600-m-n) — Engineering Geology I, chapter 5, asked 4×
- [Three-point problem: A 600 m N, C 300 m E (500, 100, 400)](https://www.bctengineer.com/question.md?key=semester_3%2Fengineering_geology_i%3Athreepoint-problem-a-600-m-2) — Engineering Geology I, chapter 5, asked 4×
- [Three-point problem: A 600 m N, C 300 m E (500, 400, 400)](https://www.bctengineer.com/question.md?key=semester_3%2Fengineering_geology_i%3Athreepoint-problem-a-600-m) — Engineering Geology I, chapter 5
- [Bore hole altitude of fractured bedrock](https://www.bctengineer.com/question.md?key=semester_3%2Fengineering_geology_i%3Abore-hole-altitude-of-fractured) — Engineering Geology I, chapter 5