title: "Line model classification and short-line ABCD"
subject: "Power System Analysis I"
chapter: 5
key: "semester_4/power_system_analysis_i:classify-models-short-line-abcd"
source: https://www.bctengineer.com/q/semester_4/power_system_analysis_i/classify-models-short-line-abcd
site: BCT Engineering
---

# Line model classification and short-line ABCD

Power System Analysis I · Chapter 5: Transmission Line Modeling

- Asked in: 2082 Kartik (new course), 2+4 marks
- Video: [ABCD parameters of short transmission line by Prof. Irfan Mujawar](https://www.youtube.com/watch?v=cKmgHdoqVW8) — Dr. Irfan Mujawar
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_4/power_system_analysis_i/classify-models-short-line-abcd
- Whole chapter: https://www.bctengineer.com/md/semester_4/power_system_analysis_i/chapter-5

## Question

Classify transmission line models. Find the A, B, C, D parameters of a short transmission line and also draw its phasor diagram with lagging and leading power factor of the load.

## Short answer

Models: short line (≤80 km, series impedance only), medium line (80–250 km, nominal-π or T), long line (>250 km, distributed parameters). Short-line ABCD: A=1, B=Z=R+jX, C=0, D=1. For lagging load, V_S leads V_R and is larger. For leading load, V_S can be less than V_R giving negative regulation.

## Answer

#### Classification of transmission line models
Based on length (for 50 Hz lines):

| Type | Length | Model | Capacitance |
|---|---|---|---|
| Short line | up to about 80 km | Series $R + jX$ only | Neglected |
| Medium line | 80–250 km | Nominal-Π or nominal-T | Lumped |
| Long line | above 250 km | Distributed (exact) / equivalent Π or T | Distributed |

#### ABCD parameters of a short line
The shunt capacitance is neglected, so the same current flows through the whole line.

```text
 IS = IR      R        jX        IR
 o---->----[ R ]----[ jX ]---->----o
 VS                                VR
 o---------------------------------o
```

$$
\begin{aligned}
I_S &= I_R \\
V_S &= V_R + I_R(R + jX) = V_R + Z I_R
\end{aligned}
$$

Comparing with $V_S = AV_R + BI_R$ and $I_S = CV_R + DI_R$:

$$
A = 1, \quad B = Z = R + jX\ \Omega, \quad C = 0, \quad D = 1
$$

Check: $AD - BC = 1 - 0 = 1$.

#### Phasor diagrams
Take $V_R$ as reference. The drop $I_R R$ is parallel to $I_R$ and $I_R X$ leads $I_R$ by 90°. $\delta$ is the angle between $V_S$ and $V_R$.

**Lagging p.f. load** ($I_R$ lags $V_R$ by $\phi_R$):

```text
                               + tip of VS
                    VS     .   |
                       .       | IR.X (90 deg
                   .           |  ahead of IR)
              .  d             |
   O------------------------> VR
    \ phiR                     \ IR.R (along IR)
     \                          +
      v IR
```

Here $V_S > V_R$ and $V_S \approx V_R + I_R R\cos\phi_R + I_R X\sin\phi_R$, so regulation is positive and large.

**Leading p.f. load** ($I_R$ leads $V_R$ by $\phi_R$):

```text
             ^ IR
            /       IR.X   + tip of VS
           /     (90 deg     \
          /    ahead of IR)   \
         /         VS  .       + IR.R
        / phiR    .           /  (along IR)
       /     . d             /
   O------------------------> VR
```

Here $V_S \approx V_R + I_R R\cos\phi_R - I_R X\sin\phi_R$; the $I_R X$ drop tilts backwards, so $V_S$ can be less than $V_R$ (negative regulation).

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Which classification of 50 Hz lines by length is correct?
   A. Short up to 80 km, medium 80-250 km, long above 250 km
   B. Short up to 250 km, medium 250-400 km, long above 400 km
   C. Short up to 20 km, medium 20-100 km, long above 100 km
   D. Short up to 150 km, medium 150-500 km, long above 500 km
   Answer: A. The usual limits are 80 km and 250 km, with nominal-Π or T for medium lines and distributed parameters for long lines. (Key point: Classification by length)

2. The ABCD constants of a short transmission line are:
   A. A = 1, B = Z, C = 0, D = 1
   B. A = Z, B = 1, C = 0, D = Z
   C. A = 1, B = 0, C = Y, D = 1
   D. A = 0, B = Z, C = 1, D = 0
   Answer: A. Since IS = IR and VS = VR + Z IR, A = D = 1, B = Z and C = 0. (Key point: ABCD of short line)

3. For the short line, AD - BC equals:
   A. Z
   B. 0
   C. 1
   D. Z^2
   Answer: C. AD - BC = 1 x 1 - Z x 0 = 1, showing the network is reciprocal. (Key point: Check relation AD - BC)

4. With a leading power factor load on a short line, the sending-end voltage compared with the lagging case:
   A. Is always larger than VR
   B. Is smaller; IR X term tilts backwards and VS can be less than VR (negative regulation)
   C. Is exactly equal to VR
   D. Leads VR by 90 degrees
   Answer: B. VS ≈ VR + IR R cosφ - IR X sinφ for leading load, so VS can fall below VR. (Key point: Phasor diagram for leading load)

## Related in Power System Analysis I

- [Model validity and nominal-π ABCD with phasor](https://www.bctengineer.com/question.md?key=semester_4%2Fpower_system_analysis_i%3Along-model-validity-nominal-pi) — Power System Analysis I, chapter 5
- [Nominal-T phasor diagram and ABCD parameters](https://www.bctengineer.com/question.md?key=semester_4%2Fpower_system_analysis_i%3Anominal-t-phasor-abcd) — Power System Analysis I, chapter 5, asked 2×
- [Nominal-π derivation, losses and UPF phasor diagram](https://www.bctengineer.com/question.md?key=semester_4%2Fpower_system_analysis_i%3Anominal-pi-200km-derivation-losses) — Power System Analysis I, chapter 5
- [220 kV line, 200 MW: sending end from ABCD](https://www.bctengineer.com/question.md?key=semester_4%2Fpower_system_analysis_i%3Aabcd-220kv-200mw) — Power System Analysis I, chapter 6
- [150 mile, 60 Hz line: ABCD and sending end](https://www.bctengineer.com/question.md?key=semester_4%2Fpower_system_analysis_i%3A150-mile-60hz-line-abcd) — Power System Analysis I, chapter 5
- [Nominal-π model ABCD derivation](https://www.bctengineer.com/question.md?key=semester_4%2Fpower_system_analysis_i%3Anominal-pi-abcd-derivation) — Power System Analysis I, chapter 5

## Related in other subjects

- [Synchronous motor drawing lagging and leading current](https://www.bctengineer.com/question.md?key=semester_5%2Felectric_machines_ii%3Amotor-lagging-leading-current) — Electric Machines II, chapter 2, asked 4×
- [Loaded transformer and phasor diagram for inductive load](https://www.bctengineer.com/question.md?key=semester_4%2Felectrical_machines_i%3Atransformer-loaded-operation-phasor-inductive) — Electrical Machines I, chapter 2
- [Synchronous motor features and lagging/leading operation](https://www.bctengineer.com/question.md?key=semester_5%2Felectric_machines_ii%3Amotor-features-lagging-leading) — Electric Machines II, chapter 2
- [Reactive power and power phasor diagram](https://www.bctengineer.com/question.md?key=semester_1%2Fbasic_electrical_engineering%3Areactive-power-phasor-diagram) — Basic Electrical Engineering, chapter 7