# Settlement 4 cm in 2 months, time for 10 cm

Soil Mechanics · Chapter 9: Compressibility of Soil

- Asked in: 2078 Chaitra, 3 marks
- Video: [Finding Primary Consolidation Settlement, Degree of Consolidation and Settlement at any time](https://www.youtube.com/watch?v=Ule5gdMiWhs) — Master Civil Engineering
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_4/soil_mechanics/settlement-time-ratio-months
- Whole chapter: https://www.bctengineer.com/md/semester_4/soil_mechanics/chapter-9

## Question

A compressible layer whose total settlement under a given loading is expected to be 20 cm settles 4 cm at the end of 2 months. How many months will be required to reach a settlement of 10 cm? Assume double drainage.

## Short answer

For U < 60%, time is proportional to U². Degrees of consolidation are U1=20%, U2=50%. Required time = 2 months × (50/20)² = 12.5 months.

## Answer

Settlement is proportional to the degree of consolidation $U$, and time is proportional to $T_v$. For $U < 60\%$, $T_v = \frac{\pi}{4}U^2$, so $t \propto U^2$ (same layer, same $c_v$ and drainage).

**Step 1: Degrees of consolidation**

$$
U_1 = \frac{4}{20} = 20\%, \qquad U_2 = \frac{10}{20} = 50\%
$$

Both are below 60%, so the parabolic relation applies.

**Step 2: Time ratio**

$$
\frac{t_2}{t_1} = \left(\frac{U_2}{U_1}\right)^2 = \left(\frac{50}{20}\right)^2 = 6.25
$$

$$
t_2 = 6.25 \times 2 = 12.5\ \text{months}
$$

**Answer: about 12.5 months from the start of loading.** The double drainage condition does not change the ratio, because $H_{dr}$ is the same in both cases.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. How is the degree of consolidation found from settlement?
   A. U = settlement / (1+e0)
   B. U = total settlement / settlement at time t
   C. U = settlement x time
   D. U = settlement at time t / total settlement
   Answer: D. Settlement is proportional to U, so 4/20 = 20% and 10/20 = 50%. (Key point: Settlement and U)

2. For U < 60%, how is time related to U?
   A. t is proportional to U
   B. t is proportional to U^2 (Tv = pi U^2/4)
   C. t is proportional to sqrt(U)
   D. t is proportional to log U
   Answer: B. In the early part of consolidation Tv = (pi/4) U^2, so time varies with the square of U. (Key point: Relation for U below 60%)

3. What is the time to reach 10 cm settlement?
   A. 5 months
   B. 6.25 months
   C. 12.5 months
   D. 10 months
   Answer: C. t2 = 2 x (50/20)^2 = 12.5 months from the start of loading. (Key point: Time required)

## Related in Soil Mechanics

- [Clay 10 m, 2.54 cm sample, half settlement](https://www.bctengineer.com/question.md?key=semester_4%2Fsoil_mechanics%3Aclay-10m-half-settlement-time-ratio) — Soil Mechanics, chapter 9
- [Time-settlement curve, 3 m clay](https://www.bctengineer.com/question.md?key=semester_4%2Fsoil_mechanics%3Atime-settlement-curve-3m-clay) — Soil Mechanics, chapter 9
- [3 m clay, cv 0.025 cm²/min, times](https://www.bctengineer.com/question.md?key=semester_4%2Fsoil_mechanics%3Aclay-3m-cv-time-80-percent) — Soil Mechanics, chapter 9
- [Double diffuse layer in clay](https://www.bctengineer.com/question.md?key=semester_4%2Fsoil_mechanics%3Adouble-diffuse-layer-explain) — Soil Mechanics, chapter 4
- [One-way vs two-way drainage time](https://www.bctengineer.com/question.md?key=semester_4%2Fsoil_mechanics%3Aone-way-two-way-drainage-time) — Soil Mechanics, chapter 9
- [Clay 4 m, 90% in 4 hours, time in years](https://www.bctengineer.com/question.md?key=semester_4%2Fsoil_mechanics%3Aclay-bed-90-percent-years) — Soil Mechanics, chapter 9

## Related in other subjects

- [Network errors; expected time of engineers](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Anetwork-errors-expected-time-engineers) — Project Engineering, chapter 3
- [PERT expected time and completion probability](https://www.bctengineer.com/question.md?key=semester_6%2Findustrial_engineering_and_management%3Apert-probability-of-completion) — Industrial Engineering and Management, chapter 3
- [Slope deflection: D rotates, C settles 4 mm](https://www.bctengineer.com/question.md?key=semester_5%2Ftheory_of_structures_ii%3Aslope-deflection-beam-25kn-d-rotation) — Theory of Structures II, chapter 3
- [Fixed beam: end moments from support rotation or settlement](https://www.bctengineer.com/question.md?key=semester_5%2Ftheory_of_structures_ii%3Afixed-beam-end-moments-rotation-settlement) — Theory of Structures II, chapter 3, asked 4×