# Time-settlement curve, 3 m clay

Soil Mechanics · Chapter 9: Compressibility of Soil

- Asked in: 2078 Poush
- Video: [The Mechanics of Soil Consolidation and Time Settlement Curves](https://www.youtube.com/watch?v=9JOLJhn4DY4) — Geotech Guide
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_4/soil_mechanics/time-settlement-curve-3m-clay
- Whole chapter: https://www.bctengineer.com/md/semester_4/soil_mechanics/chapter-9

## Question

A structure built on a 3 m thick single drained clay layer settled 5 cm in 60 days after it was built. If this settlement corresponds to 20 percent average consolidation of the clay layer, plot the time settlement curve of the structure for a period of 3 years from the time it was built.

## Short answer

Final settlement is 25 cm. From t=60 days at U=20%, cv = 47.1 cm²/day. At 3 years (1095 days) the time factor is 0.573, giving U≈80% and settlement ≈20 cm. The curve rises steeply at first and asymptotically approaches 25 cm.

## Answer

**Given:** single-drained layer, $H_{dr} = 3$ m $= 300$ cm. Settlement 5 cm at $t = 60$ days corresponds to $U = 20\%$.

**Step 1: Final settlement**

$$
S_{final} = \frac{5}{0.20} = 25\ \text{cm}
$$

**Step 2: Coefficient of consolidation.** For $U=20\%$, $T_v = \frac{\pi}{4}(0.20)^2 = 0.0314$.

$$
c_v = \frac{T_v H_{dr}^2}{t} = \frac{0.0314 \times 300^2}{60} = 47.1\ \text{cm}^2/\text{day}
$$

**Step 3: Time for various $U$.** $t = T_v H_{dr}^2 / c_v = T_v \times 1910.0$ days. Use $T_v = \frac{\pi}{4}U^2$ for $U<60\%$ and $T_v = 1.781 - 0.933\log_{10}(100-U\%)$ for $U>60\%$. Settlement $= U \times 25$ cm.

| $U$ (%) | $T_v$ | Time (days) | Settlement (cm) |
|---|---|---|---|
| 10 | 0.008 | 15 | 2.5 |
| 20 | 0.031 | 60 | 5.0 |
| 30 | 0.071 | 135 | 7.5 |
| 40 | 0.126 | 240 | 10.0 |
| 50 | 0.196 | 375 | 12.5 |
| 60 | 0.286 | 547 | 15.0 |
| 70 | 0.403 | 769 | 17.5 |
| 80 | 0.567 | 1083 | 20.0 |
| 90 | 0.848 | 1620 | 22.5 |

**Step 4: Settlement at 3 years** ($t = 1095$ days):

$$
T_v = \frac{c_v t}{H_{dr}^2} = \frac{47.1 \times 1095}{300^2} = 0.573 \;\Rightarrow\; U \approx 80\%, \quad S \approx 20\ \text{cm}
$$

**Plot:** draw time (days, 0 to 1095) on the horizontal axis and settlement (cm) downward on the vertical axis; join the points above with a smooth curve. The curve is steep at first and flattens towards 25 cm.

```text
 t (days)  0   200  400  600  800  1000 1095
 S (cm)    0
           |  *
        5  |    *
       10  |        *
       15  |             *
       20  |                    *    *  <- 3 yr
       25  - - - - - - - - - - - - - - (final)
```

**Answer: the structure settles about 20 cm in 3 years; the curve approaches the final value of 25 cm.**

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. How is the final settlement found from the observed data?
   A. S_final = 5 cm x 0.20 = 1 cm
   B. S_final = 5 cm / 0.20 = 25 cm
   C. S_final = 5 + 20 = 25 cm
   D. S_final = 5 / 60 cm
   Answer: B. 5 cm is 20% of the final settlement, so the final is 25 cm. (Key point: Final settlement)

2. How is c_v found from the 60-day observation?
   A. Tv = 0.20 and cv = Tv H^2/t
   B. Tv = (pi/4)(0.20)^2 = 0.0314 and cv = Tv H_dr^2 / t = 47.1 cm^2/day
   C. Tv = 0.848 for U = 20% and cv = Tv H_dr^2/t
   D. Tv = (pi/4)(0.20)^2 and cv = t/(Tv H_dr^2)
   Answer: B. U = 20% is below 60%, so Tv = (pi/4)U^2 = 0.0314, then cv = 0.0314 x 300^2/60. (Key point: Finding c_v)

3. Why is H_dr taken as the full 3 m?
   A. The layer is double drained
   B. Clay always drains over its full thickness
   C. The layer is single drained
   D. Because the structure is 3 m wide
   Answer: C. Only one face drains in a single-drained layer, so the drainage path equals the layer thickness. (Key point: Drainage path)

4. What does the time-settlement curve look like?
   A. A straight line reaching 25 cm at 3 years
   B. Flat at first then steepening
   C. Rising steeply and exceeding 25 cm
   D. Steep at first, flattening towards the 25 cm final value
   Answer: D. Settlement rate falls as excess pore pressure dissipates, so the curve flattens; at 3 years U is about 80%, about 20 cm. (Key point: Shape of the curve)

## Related in Soil Mechanics

- [Clay 4 m, 90% in 4 hours, time in years](https://www.bctengineer.com/question.md?key=semester_4%2Fsoil_mechanics%3Aclay-bed-90-percent-years) — Soil Mechanics, chapter 9
- [Clay 10 m, 2.54 cm sample, half settlement](https://www.bctengineer.com/question.md?key=semester_4%2Fsoil_mechanics%3Aclay-10m-half-settlement-time-ratio) — Soil Mechanics, chapter 9
- [5 m clay, Cc 0.25, 65% consolidation](https://www.bctengineer.com/question.md?key=semester_4%2Fsoil_mechanics%3Aclay-5m-cc-025-65-percent) — Soil Mechanics, chapter 9, asked 2×
- [3 m clay, cv 0.025 cm²/min, times](https://www.bctengineer.com/question.md?key=semester_4%2Fsoil_mechanics%3Aclay-3m-cv-time-80-percent) — Soil Mechanics, chapter 9
- [Settlement 4 cm in 2 months, time for 10 cm](https://www.bctengineer.com/question.md?key=semester_4%2Fsoil_mechanics%3Asettlement-time-ratio-months) — Soil Mechanics, chapter 9
- [5 m clay, Cc 0.25, 50% consolidation](https://www.bctengineer.com/question.md?key=semester_4%2Fsoil_mechanics%3Aclay-5m-cc-025-50-percent) — Soil Mechanics, chapter 9, asked 2×

## Related in other subjects

- [Percent strength gain at 14 days](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Astrength-gain-14-days) — Concrete Technology and Masonry Structure, chapter 4
- [Crest, average and schedule speed; speed-time curve](https://www.bctengineer.com/question.md?key=semester_7%2Futilization_of_electrical_energy%3Acrest-average-schedule-speed-42kmph) — Utilization of Electrical Energy, chapter 4
- [Average demand, village survey 2013, design 25 years](https://www.bctengineer.com/question.md?key=semester_5%2Fwater_supply_engineering%3Ademand-c73) — Water Supply Engineering, chapter 3, asked 2×
- [Demand of rural municipality, base period 3 years](https://www.bctengineer.com/question.md?key=semester_5%2Fwater_supply_engineering%3Ademand-bk79) — Water Supply Engineering, chapter 3