title: "Vertical curve -0.7% and +0.5%, IP RL 650"
subject: "Surveying II"
chapter: 6
key: "semester_4/surveying_ii:vertical-curve-neg07-pos05-rl-ip"
source: https://www.bctengineer.com/q/semester_4/surveying_ii/vertical-curve-neg07-pos05-rl-ip
site: BCT Engineering
---

# Vertical curve -0.7% and +0.5%, IP RL 650

Surveying II · Chapter 6: Curves

- Asked in: 2075 Baisakh, 8 marks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_4/surveying_ii/vertical-curve-neg07-pos05-rl-ip
- Whole chapter: https://www.bctengineer.com/md/semester_4/surveying_ii/chapter-6

## Question

A grade of -0.7% is followed by another grade of +0.5%. The two ends of these portions are connected by a parabolic vertical curve. The chainage and RL of intersection point are 1000 and 650 m respectively. Calculate RLs of all the points on the curve. Take peg interval of 20 m and rate of change of grade is 0.1% per 20 m.

## Short answer

Length 240 m based on grade change of 1.2% at rate 0.1% per 20 m. BVC at 880 m (RL 650.84 m), EVC at 1120 m (RL 650.60 m). Lowest point at chainage 1020 m, elevation 650.35 m.

## Answer

A parabolic vertical curve with a constant rate of change of grade is set out using the tangent-offset method.

#### Step 1: Length of the curve
Rate of change of grade $r = 0.1\%$ per 20 m, algebraic change in grade $= 0.5 - (-0.7) = 1.2\%$.

$$
L = \frac{|g_2-g_1|}{r}\times 20 = \frac{1.2}{0.1}\times 20 = 240\ \text{m}
$$

#### Step 2: BVC, EVC and their levels
The curve is a sag (valley) curve with equal tangent lengths $L/2 = 120$ m.

$$
\begin{aligned}
\text{Ch. of BVC} &= 1000 - 120 = 880\ \text{m}\\
\text{Ch. of EVC} &= 1000 + 120 = 1120\ \text{m}\\
\text{RL of BVC} &= 650 - \frac{(-0.7)}{100}\times 120 = 650.84\ \text{m}\\
\text{RL of EVC} &= 650 + \frac{(0.5)}{100}\times 120 = 650.6\ \text{m}
\end{aligned}
$$

#### Step 3: RL of curve points
Using the tangent-offset form of the parabola ($x$ measured from BVC, grades in %):

$$
y_x = \text{RL}_{BVC} + \frac{g_1 x}{100} + \frac{(g_2-g_1)x^2}{200L}
$$

with $g_1 = -0.7\%$, $g_2 = 0.5\%$, $L = 240$ m, so the offset is $y = \frac{(1.2)x^2}{200\times 240}$ and pegs are taken at multiples of 20 m.

| Chainage (m) | x from BVC (m) | Tangent RL (m) | Offset y (m) | Curve RL (m) |
|---|---|---|---|---|
| 880 | 0 | 650.840 | 0.000 | 650.840 |
| 900 | 20 | 650.700 | +0.010 | 650.710 |
| 920 | 40 | 650.560 | +0.040 | 650.600 |
| 940 | 60 | 650.420 | +0.090 | 650.510 |
| 960 | 80 | 650.280 | +0.160 | 650.440 |
| 980 | 100 | 650.140 | +0.250 | 650.390 |
| 1000 | 120 | 650.000 | +0.360 | 650.360 |
| 1020 | 140 | 649.860 | +0.490 | 650.350 |
| 1040 | 160 | 649.720 | +0.640 | 650.360 |
| 1060 | 180 | 649.580 | +0.810 | 650.390 |
| 1080 | 200 | 649.440 | +1.000 | 650.440 |
| 1100 | 220 | 649.300 | +1.210 | 650.510 |
| 1120 | 240 | 649.160 | +1.440 | 650.600 |

Check: the last curve RL (650.6 m) equals the RL of EVC (650.6 m), and the curve at the IP chainage lies 0.36 m above the IP, at RL 650.36 m.

#### Step 4: Lowest point
At the lowest point the grade is zero, so $x = \dfrac{-g_1 L}{g_2-g_1} = \dfrac{0.7\times 240}{1.2} = 140$ m from BVC.

- Chainage = 880 + 140 = 1020 m
- RL = 650.84 + (-0.7/100)(140) + (1.2)(140)²/(200 × 240) = 650.35 m

**Answer:** $L = 240$ m, BVC at 880 m (RL 650.84 m), EVC at 1120 m (RL 650.6 m); curve levels as tabulated.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. With rate of change of grade 0.1% per 20 m and total change 1.2%, L is
   A. 240 m
   B. 120 m
   C. 24 m
   D. 60 m
   Answer: A. L = (1.2/0.1) x 20 = 240 m. (Key point: Length from rate of change)

2. How are BVC chainage and RL found?
   A. Chainage = IP - L = 760 m
   B. Chainage = IP - L/2 = 880 m; RL = RL of IP - g1 x L/2/100 = 650.84 m
   C. RL of BVC = 650 - 0.84 = 649.16 m
   D. Chainage = IP + L/2 = 1120 m
   Answer: B. The BVC is L/2 before the IP, and with a falling first grade it lies higher than the IP by 0.007 x 120. (Key point: BVC chainage and RL)

3. What is the offset of the curve from the tangent at distance x?
   A. y = (g2 - g1)x/(200L)
   B. y = (g2 + g1)x^2/(200L)
   C. y = (g2 - g1)x^2/(200L)
   D. y = g1 x^2/(100L)
   Answer: C. The parabolic offset is proportional to x^2: y = (g2 - g1)x^2/(200L) with grades in %. (Key point: Offset formula)

4. Where is the lowest point?
   A. x = 120 m, chainage 1000 m
   B. x = 100 m, chainage 980 m
   C. x = 240 m, chainage 1120 m
   D. x = -g1 L/(g2 - g1) = 140 m from BVC, chainage 1020 m, RL 650.35 m
   Answer: D. The grade becomes zero at x = 0.7 x 240/1.2 = 140 m. (Key point: Lowest point)

## Related in Surveying II

- [Vertical curve +0.5% and -0.7%, IP RL 350.750](https://www.bctengineer.com/question.md?key=semester_4%2Fsurveying_ii%3Avertical-curve-pos05-neg07-ip-500) — Surveying II, chapter 6
- [Vertical curve -1% and +0.5% by parabolic method](https://www.bctengineer.com/question.md?key=semester_4%2Fsurveying_ii%3Avertical-curve-parabolic-neg1-pos05-ip) — Surveying II, chapter 6, asked 2×
- [Vertical curve -0.5% and +0.7%, IP RL 500](https://www.bctengineer.com/question.md?key=semester_4%2Fsurveying_ii%3Avertical-curve-neg05-pos07-ip-1000) — Surveying II, chapter 6
- [Vertical curve 180 m, -3.5% then +4.5%, IP 2450](https://www.bctengineer.com/question.md?key=semester_4%2Fsurveying_ii%3Avertical-curve-35down-45up-ip-2450) — Surveying II, chapter 6, asked 2×
- [Vertical curve -1% and +0.5%, IP 500 m](https://www.bctengineer.com/question.md?key=semester_4%2Fsurveying_ii%3Avertical-curve-falling-1-rising-05) — Surveying II, chapter 6, asked 2×
- [Vertical curve -2% and +3%, IP 2600, 0.5% per 20 m](https://www.bctengineer.com/question.md?key=semester_4%2Fsurveying_ii%3Avertical-curve-2down-3up-ip-2600) — Surveying II, chapter 6

## Related in other subjects

- [Vertical curve chainage and elevations, R 8000 m](https://www.bctengineer.com/question.md?key=semester_6%2Ftransportation_engineering_i%3An-69bh-vc-chainage) — Transportation Engineering I, chapter 3
- [Vertical curve, -3% and 1.5% at chainage 2000](https://www.bctengineer.com/question.md?key=semester_6%2Ftransportation_engineering_i%3An-79a-vc-2000) — Transportation Engineering I, chapter 3
- [Vertical curve with 300 m grade sections](https://www.bctengineer.com/question.md?key=semester_6%2Ftransportation_engineering_i%3An-65k-vc-300) — Transportation Engineering I, chapter 3
- [Vertical curve 35 m headlight and momentum grade](https://www.bctengineer.com/question.md?key=semester_6%2Ftransportation_engineering_i%3An-80c-vc-headlight-35m) — Transportation Engineering I, chapter 3