# First quarterly progress report: urban internet project (memo)

Communication English · Chapter 7: Informal Reports

- Asked in: 2075 Chaitra, 6 marks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_5/communication_english/first-quarterly-progress-report-urban-internet-memo
- Whole chapter: https://www.bctengineer.com/md/semester_5/communication_english/chapter-7

## Question

Suppose you are the chief consultant of a urban internet connectivity project and the work is going on in your local town. Write a first quarterly progress report in memo format.

## Short answer

A memo reports the first quarter of an urban internet project in Lalitpur. Survey and design finished, 14 km ducts laid, 6 km fibre installed, four hotspots active, and Rs. 1.2 crore spent. Progress is 25 percent against 28 percent plan.

## Answer

```text
                        MEMORANDUM

To      : Mayor, Lalitpur Metropolitan City
From    : Er. Rina Maharjan, Chief Consultant
Date    : 10 April 2027
Subject : First quarterly progress report on the Urban
Internet Connectivity Project (January-March 2027)
```

#### Introduction

The project aims to provide free Wi-Fi in 25 public places and high-speed fibre internet in 15 wards of the city. It started on 1 January 2027 and will run for 12 months. This is the first quarterly report.

#### Work completed

1. The survey and design were completed; the locations of the 25 hotspots and a 42 km fibre route were finalised.
2. The contract for fibre and equipment was signed with a registered ISP in February.
3. 14 km of ducts were laid, and 6 km of fibre was installed.
4. Four hotspots were set up, at Patan Durbar Square, Pulchowk, Jawalakhel and the bus park, and they serve 300 users a day.
5. A network control room was established at the municipal office.
6. A user registration portal is being tested.
7. Expenditure: Rs. 1.2 crore (24 percent of the budget).

#### Problems faced

- Delays in getting permits to dig roads in the core areas.
- Some hotspot locations had to be changed because there was no power supply.

#### Work planned for the next period

1. Complete 20 km of fibre and 8 more hotspots.
2. Train municipal staff in network operation.
3. Test the speed and coverage, and conduct a user survey.

#### Conclusion

The project has completed 25 percent of its work against the plan of 28 percent. We are confident that the project will be completed within the planned time.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. What does the urban internet project aim to provide?
   A. Free Wi-Fi in 25 public places and fibre internet for 15 wards
   B. Mobile towers only
   C. A national backbone
   D. Internet only for the mayor's office
   Answer: A. It aims at free Wi-Fi in 25 public places and high-speed fibre for 15 wards. (Key point: Project aim)

2. What was physically installed by the end of the first quarter?
   A. All 25 hotspots
   B. 14 km of ducts, 6 km of fibre and four hotspots
   C. 42 km of fibre
   D. Nothing
   Answer: B. 14 km of ducts and 6 km of fibre were laid, and four hotspots were set up; 42 km is the whole planned route. (Key point: Work completed)

3. What do the figures in the conclusion and expenditure show?
   A. 28 percent done against 25 percent planned
   B. Fully complete
   C. 25 percent done against a plan of 28 percent; Rs. 1.2 crore spent (24 percent)
   D. Rs. 1.2 crore is 100 percent of the budget
   Answer: C. Work is 25 percent complete vs 28 percent planned, a small lag, and 24 percent of the budget has been spent. (Key point: Progress and expenditure)

4. Which are the problems faced?
   A. Lack of ISP
   B. Public opposition
   C. Equipment theft
   D. Delay in road-digging permits in core areas and change of hotspot locations due to power supply
   Answer: D. Permits for digging delayed the work and some hotspot sites lacked power supply. (Key point: Problems faced)

## Close variants set in other exams

- [First monthly progress report: internet connectivity (memo)](https://www.bctengineer.com/question.md?key=semester_5%2Fcommunication_english%3Afirst-monthly-progress-report-internet-connectivity) — Communication English, chapter 7, asked 2×

## Related in Communication English

- [Second quarterly progress report in memo format](https://www.bctengineer.com/question.md?key=semester_5%2Fcommunication_english%3Aquarterly-progress-report-housing-memo) — Communication English, chapter 7
- [First quarterly progress report of a project](https://www.bctengineer.com/question.md?key=semester_5%2Fcommunication_english%3Aquarterly-progress-report-five-year-project) — Communication English, chapter 7
- [First monthly progress report in memo format](https://www.bctengineer.com/question.md?key=semester_5%2Fcommunication_english%3Afirst-monthly-progress-report-suspension-bridge) — Communication English, chapter 7, asked 2×
- [Quarterly progress report: hydro-electricity supply centre (memo)](https://www.bctengineer.com/question.md?key=semester_5%2Fcommunication_english%3Aquarterly-progress-report-hydro-supply-memo) — Communication English, chapter 7
- [First monthly progress report: lab construction (memo)](https://www.bctengineer.com/question.md?key=semester_5%2Fcommunication_english%3Afirst-monthly-progress-report-lab-memo) — Communication English, chapter 7
- [Second quarterly progress report: road expansion](https://www.bctengineer.com/question.md?key=semester_5%2Fcommunication_english%3Aquarterly-progress-report-road-expansion) — Communication English, chapter 7