title: "British method of mix design"
subject: "Concrete Technology and Masonry Structure"
chapter: 3
key: "semester_5/concrete_technology_and_masonry_structure:british-method-mix-design"
source: https://www.bctengineer.com/q/semester_5/concrete_technology_and_masonry_structure/british-method-mix-design
site: BCT Engineering
---

# British method of mix design

Concrete Technology and Masonry Structure · Chapter 3: Mix design of concrete and property of green concrete

- Asked in: 2066 Bhadra (old course), 5 marks
- Video: [British DoE (Department of Environment) Method of Mix Design](https://www.youtube.com/watch?v=NnAAEeIJgkc) — Ceylara Academy
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_5/concrete_technology_and_masonry_structure/british-method-mix-design
- Whole chapter: https://www.bctengineer.com/md/semester_5/concrete_technology_and_masonry_structure/chapter-3

## Question

Describe the step by step process of mix design of concrete by using the British method.

## Short answer

DoE method: target mean strength fm = fck + 1.64 s. Determine w/c from strength charts and durability limits. Free water content from tables by slump, max size, aggregate type (uncrushed/crushed). Cement content = water / w/c. Total aggregate = wet density – cement – water. Fine aggregate proportion from grading zone and slump charts. Adjust with trial mix and moisture corrections.

## Answer

The **British (DoE) method** (BRE/DoE 1988, "Design of Normal Concrete Mixes") selects the mix from charts and tables; it is a wet-density method.

#### Steps
1. **Target mean strength**: $f_m = f_{ck} + k\,s$, with $k = 1.64$ (5% defectives) and $s$ = standard deviation (about 4-8 MPa, from site data).
2. **w/c ratio**: from Table 2, find the strength at w/c 0.5 for the cement type, aggregate type (crushed/uncrushed) and age; draw the curve through this point on Fig 1 and read the w/c for the target strength; check the maximum w/c from durability requirements and use the lower value.
3. **Free-water content**: from Table 3, for the slump (0-10, 10-30, 30-60, 60-180 mm) or Vebe time, the maximum size (10, 20, 40 mm) and the aggregate type. When the fine and coarse aggregates are of different types: $W = \frac{2}{3} W_f + \frac{1}{3} W_c$, where $W_f$ and $W_c$ are the water contents for the type of fine and coarse aggregate respectively.
4. **Cement content** = free water / (w/c); check the minimum and maximum limits.
5. **Total aggregate content**: from Fig 3, find the wet density of concrete for the free-water content and the aggregate SG; total aggregate = wet density - cement - water.
6. **Fine aggregate proportion**: from Fig 4, using the grading zone (% passing 600 micron), size, slump and w/c.
7. **Fine and coarse aggregate masses**: FA = proportion $\times$ total aggregate; CA = remainder; the coarse aggregate may be split into sizes.
8. **Trial mix**: adjust for slump and strength; correct for the moisture content at site.

```text
 f_ck+ks -> w/c -> + water -> cement
                       |
   density chart -> total agg -> FA / CA
```

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. In the British method, target mean strength is
   A. fck - 1.64 s
   B. fck + 4
   C. fck
   D. fck + 1.64 s
   Answer: D. fm = fck + k s with k = 1.64 for 5% defectives. (Key point: Target strength)

2. When the w/c from the strength curve and the durability maximum differ, the w/c used is
   A. the lower
   B. the higher
   C. the average
   D. always 0.5
   Answer: A. The lower value satisfies both strength and durability. (Key point: w/c choice)

3. Free water for mixed uncrushed and crushed aggregate is
   A. Wf/2 + Wc/2
   B. 2/3 Wf + 1/3 Wc
   C. 1/3 Wf + 2/3 Wc
   D. Wf + Wc
   Answer: B. W = 2/3 Wf + 1/3 Wc per the answer. (Key point: Mixed aggregate water)

4. Total aggregate content is found as
   A. cement x w/c
   B. water / w/c
   C. wet density - cement - water
   D. volume of CA x bulk density
   Answer: C. The wet density from Fig 3 minus cement and free water gives total aggregate. (Key point: Total aggregate)

## Related in Concrete Technology and Masonry Structure

- [ACI mix design for M35 concrete (numerical)](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Aaci-mix-design-m35-numerical) — Concrete Technology and Masonry Structure, chapter 3, asked 2×
- [ACI mix design for M25 concrete (numerical)](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Aaci-mix-design-m25-numerical) — Concrete Technology and Masonry Structure, chapter 3, asked 2×
- [Fundamental concepts of concrete mix design](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Amix-design-fundamental-concepts) — Concrete Technology and Masonry Structure, chapter 3
- [ACI mix design for 25 MPa concrete (numerical)](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Aaci-mix-design-25mpa-numerical) — Concrete Technology and Masonry Structure, chapter 3
- [DOE mix design for M25 concrete (numerical)](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Adoe-mix-design-m25-numerical) — Concrete Technology and Masonry Structure, chapter 3
- [ACI method of mix design steps](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Aaci-mix-design-steps) — Concrete Technology and Masonry Structure, chapter 3, asked 9×

## Related in other subjects

- [Site engineer uses weaker mortar and concrete mix](https://www.bctengineer.com/question.md?key=semester_8%2Fengineering_professional_practice%3Amortar-ratio-friend-silence) — Engineering Professional Practice, chapter 7
- [Step by step project appraisal process](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aappraisal-steps-process) — Project Engineering, chapter 2
- [Marshall method of bituminous mix design](https://www.bctengineer.com/question.md?key=semester_6%2Ftransportation_engineering_i%3Amarshall-mix-design) — Transportation Engineering I, chapter 6, asked 9×
- [Steps in the design and synthesis process](https://www.bctengineer.com/question.md?key=semester_6%2Fmachine_design_i%3Adesign-process-steps) — Machine Design I, chapter 1