title: "Measures of workability; role of w/c ratio"
subject: "Concrete Technology and Masonry Structure"
chapter: 3
key: "semester_5/concrete_technology_and_masonry_structure:workability-measures-wc-role"
source: https://www.bctengineer.com/q/semester_5/concrete_technology_and_masonry_structure/workability-measures-wc-role
site: BCT Engineering
---

# Measures of workability; role of w/c ratio

Concrete Technology and Masonry Structure · Chapter 3: Mix design of concrete and property of green concrete

- Asked in: 2078 Bhadra, 4 marks
- Video: [Workability of Cement Concrete](https://www.youtube.com/watch?v=ERnKVQcOfJU) — NCTEL
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_5/concrete_technology_and_masonry_structure/workability-measures-wc-role
- Whole chapter: https://www.bctengineer.com/md/semester_5/concrete_technology_and_masonry_structure/chapter-3

## Question

What are the measures of workability? What is the role of water cement ratio to the workability, strength and durability of concrete?

## Short answer

Measures: slump, compaction factor, Vee-Bee, flow table tests. Higher w/c ratio increases workability but reduces strength (Abrams' law) and durability due to higher permeability. For durability, w/c must be limited (e.g., 0.45–0.55 depending on exposure).

## Answer

#### Measures of workability (IS 1199)
- **Slump test**: slump in mm of a cone-moulded sample (25-125 mm).
- **Compaction factor test**: ratio of the weight of partially compacted concrete to that of fully compacted concrete (0.7-0.95).
- **Vee-Bee test**: time in seconds for the slump-cone concrete to remould into a cylinder under vibration (for dry mixes).
- **Flow table test**: spread diameter of concrete on a table after 15 drops (flowing concrete).
- **Kelly ball penetration test**, remoulding test, and for SCC: slump flow, L-box and V-funnel.

#### Role of the water-cement ratio
- **Workability**: a higher w/c gives a more fluid, workable mix. For a fixed cement content, slump changes directly with the water content (roughly 25 mm of slump for about 3% change in water).
- **Strength**: strength falls as w/c rises (Abrams' law, $f = A/B^{w/c}$), because excess water leaves capillary pores.
- **Durability**: a high w/c gives high permeability, so the ingress of chlorides, sulphates and water causes corrosion and frost damage (IS 456 Table 5 limits the w/c for RCC to 0.55, 0.50, 0.45, 0.45 and 0.40 for mild, moderate, severe, very severe and extreme exposure). Too low a w/c (below about 0.35) gives poor workability and incomplete compaction unless a superplasticiser is used.

So the w/c should be as low as full compaction permits.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Which workability test measures the time taken for a slump cone of concrete to remould into a cylinder under vibration, and suits dry mixes?
   A. Vee-Bee test
   B. Slump test
   C. Compaction factor test
   D. Flow table test
   Answer: A. The Vee-Bee test records the time in seconds for remoulding under vibration, which makes it suitable for dry mixes. (Key point: Vee-Bee test)

2. What does the compaction factor measure?
   A. Spread diameter after 15 drops
   B. Ratio of weight of partially compacted to fully compacted concrete
   C. Vertical subsidence of a cone in mm
   D. Time for a funnel to empty
   Answer: B. Compaction factor is the weight ratio of partially compacted to fully compacted concrete, typically 0.7-0.95. (Key point: Compaction factor)

3. According to Abrams' law, what happens to strength when w/c rises?
   A. It rises because the mix is more workable
   B. It is unchanged for a fixed cement content
   C. It falls because excess water leaves capillary pores
   D. It rises first and then falls sharply
   Answer: C. Excess water evaporates leaving capillary pores, so strength falls as w/c increases. (Key point: w/c and strength)

4. What problem arises if w/c is made too low (below about 0.35) without a superplasticiser?
   A. Excess bleeding
   B. Higher permeability
   C. Frost damage from excess water
   D. Poor workability and incomplete compaction
   Answer: D. A very low w/c gives a stiff mix that cannot be fully compacted unless a superplasticiser is used. (Key point: Low w/c limit)

## Related in Concrete Technology and Masonry Structure

- [Effect of water cement ratio on strength](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Awc-ratio-effect-strength) — Concrete Technology and Masonry Structure, chapter 3, asked 4×
- [Gel/space ratio and strength (550 gm cement)](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Agel-space-ratio-550g) — Concrete Technology and Masonry Structure, chapter 4, asked 3×
- [Gel/space ratio and strength (600 gm cement)](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Agel-space-ratio-600g) — Concrete Technology and Masonry Structure, chapter 4, asked 3×
- [Theoretical strength of moist cured concrete (1 kg cement)](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Atheoretical-strength-1kg-cement) — Concrete Technology and Masonry Structure, chapter 4
- [Effect of w/c ratio on durability](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Awc-ratio-durability) — Concrete Technology and Masonry Structure, chapter 6
- [Role and quality of water in concrete](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Awater-role-quality-impurities) — Concrete Technology and Masonry Structure, chapter 1, asked 3×

## Related in other subjects

- [Compressive strength test of cement](https://www.bctengineer.com/question.md?key=semester_3%2Fcivil_engineering_materials%3Acement-compressive-strength-test) — Civil Engineering Materials, chapter 5, asked 3×
- [Types of stresses in cement concrete pavement](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Arigid-pavement-stresses) — Transportation Engineering II, chapter 2, asked 2×
- [Rate analysis: plain cement concrete (1:3:4)](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-pcc-1-3-4) — Estimating and Costing, chapter 4
- [Construction steps of cement concrete pavement](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Acc-pavement-construction-steps) — Transportation Engineering II, chapter 3