# Time area method for runoff hydrograph

Engineering Hydrology · Chapter 7: Flow Routing

- Asked in: 2071 Chaitra, 8 marks
- Video: [How to Correctly Apply the Time-Area Method in MSMA Manual Saliran Mesra Alam Malaysia JPS Malaysia](https://www.youtube.com/watch?v=Cl62Qfb2QUM) — MSMA Channel
- Answer checked by Claude Sonnet 5.5 on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_5/engineering_hydrology/time-area-method
- Whole chapter: https://www.bctengineer.com/md/semester_5/engineering_hydrology/chapter-7

## Question

Explain in detail the time area method for estimating runoff hydrograph.

## Short answer

The time-area method computes direct runoff hydrograph by convolving effective rainfall blocks with inter-isochrone areas, ignoring storage: Qn = 2.78 ∑ rᵳ Aₙ₋₊ᵳᵳ/Δ t (area in km², r in cm, Δ t in h). It overestimates peaks; Clark improved it by adding linear reservoir routing to account for storage.

## Answer

The **time-area method** estimates the direct runoff hydrograph at the outlet of a catchment from effective rainfall, taking into account only the **translation** of runoff to the outlet and ignoring storage effects.

#### Basic idea

- Lines of equal travel time to the outlet (**isochrones**) are drawn at interval $\Delta t$: $t_1, t_2, \dots, t_c$.
- The area between two consecutive isochrones is $A_1, A_2, \dots, A_N$. Rain falling in $A_1$ reaches the outlet in the first interval, in $A_2$ in the second interval, and so on. The last strip takes time $t_c$ (time of concentration).
- The plot of cumulative area against time (or the histogram of strip areas) is the **time-area diagram**.

#### Time-area histogram

```text
 Area
  A3 |      ____
  A2 |  ___|    |___
  A1 | |    |    |   |
     | |    |    |   |___
     +-+----+----+----+---> t
       0   Δt  2Δt 3Δt  tc
```

#### Procedure

1. Prepare the isochrone map and find the strip areas $A_1, \dots, A_N$.
2. Convert the effective rainfall hyetograph into blocks $r_1, r_2, \dots, r_M$ (cm or mm) of duration $\Delta t$.
3. The discharge at the end of interval $n$ is the sum of contributions of every rainfall block over its corresponding strip:
$$
Q_n = \frac{10^4}{3600\,\Delta t}\sum_{i=1}^{n} r_i\,A_{n-i+1}\quad (A \text{ in km}^2, r \text{ in cm})
$$
i.e. $Q_n = 2.78 \sum r_i A_{n-i+1}/\Delta t$ for $r$ in cm and $\Delta t$ in h. For example, $Q_1 = 2.78\,r_1A_1/\Delta t$, $Q_2 = 2.78\,(r_1A_2 + r_2A_1)/\Delta t$, $Q_3 = 2.78\,(r_1A_3 + r_2A_2 + r_3A_1)/\Delta t$.
4. Plot $Q_n$ against time to get the direct runoff hydrograph.

The calculation is a convolution of the rainfall blocks with the area strips (reversed order), and the base flow is added afterwards.

#### Limitations

- Storage (channel and catchment) is ignored, so peaks are overestimated and the hydrograph is too steep.
- Isochrones are hard to draw accurately and the velocity is assumed constant, independent of flow depth and rainfall intensity.
- Uniform rainfall over each strip is assumed.

Clark improved the method by routing the result through a linear reservoir to include storage.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. What does the time-area method consider?
   A. Only storage
   B. Only translation, ignoring storage
   C. Infiltration only
   D. Evaporation only
   Answer: B. Storage is ignored. (Key point: Assumption)

2. What are isochrones?
   A. Lines of equal travel time to the outlet
   B. Lines of equal rainfall
   C. Lines of equal elevation
   D. Lines of equal infiltration
   Answer: A. Areas between them form the time-area diagram. (Key point: Isochrones)

3. Which expression gives the discharge at end of interval 2?
   A. Q2 = 2.78 (r1 A1 + r2 A2)/dt
   B. Q2 = 2.78 r2 A2/dt
   C. Q2 = r1 + r2
   D. Q2 = 2.78 (r1 A2 + r2 A1)/dt
   Answer: D. Rainfall blocks are convolved with reversed area strips. (Key point: Discharge formula)

4. A main limitation is:
   A. It underestimates peaks
   B. It needs no map
   C. Storage is ignored so peaks are overestimated
   D. It includes storage twice
   Answer: C. Clark added a linear reservoir to fix this. (Key point: Limitation)

## Related in Engineering Hydrology

- [Direct runoff hydrograph analysis, 4250-acre basin](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Atrapezoid-dro-4250-acre) — Engineering Hydrology, chapter 5
- [Derive 4-hr UH from triangular direct runoff hydrograph](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Atriangular-dro-4hr-uh) — Engineering Hydrology, chapter 5
- [Rainfall, lag time and time of concentration from hydrograph](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Ahydrograph-figure-lag-tc) — Engineering Hydrology, chapter 5
- [Basin area from 4-h unit hydrograph ordinates](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Aarea-of-basin-from-4h-uh) — Engineering Hydrology, chapter 5
- [Time-area method with histogram, drawbacks](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Atime-area-method-purpose-drawbacks) — Engineering Hydrology, chapter 7
- [Effect of urbanization on UH and storm runoff](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Aurbanization-uh-peak-increase) — Engineering Hydrology, chapter 5, asked 2×

## Related in other subjects

- [Runoff from a 20 ha built-up area](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Arunoff-builtup-area-20ha) — Sanitary Engineering, chapter 2
- [Time of concentration and time-area graph](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Atime-of-concentration-area-graph) — Sanitary Engineering, chapter 2, asked 3×
- [Components of detail estimate report (road)](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Adetail-estimate-report-road) — Estimating and Costing, chapter 5
- [Estimating sewage quantity for a city](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Aquantity-sewage-nepal-city) — Sanitary Engineering, chapter 2