# 2-hr UH from sketch, net rain 5 in/hr

Engineering Hydrology · Chapter 5: Hydrograph Analysis

- Asked in: 2071 Chaitra, 6+3+5 marks
- Video: [Unit Hydrograph concept-derivation and Numericals](https://www.youtube.com/watch?v=FbPqxFotoeI) — Chandrakant Jejurkar
- Answer checked by Claude Sonnet 5.5 on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_5/engineering_hydrology/uh-2hr-sketch-5in-cfs
- Whole chapter: https://www.bctengineer.com/md/semester_5/engineering_hydrology/chapter-5

## Question

A 2-hr unit hydrograph for a basin is shown in the sketch.

[Figure: 2-hr unit hydrograph, discharge (cfs) versus time (hr), t = 0 to 9. The curve rises from 0 at t = 0, passes about 200 cfs near t = 1 and 400 cfs near t = 2, peaks at 600 cfs at t = 3, then falls through about 400 cfs near t = 4 and 200 cfs near t = 5, and tails off to near zero by about t = 9. Note: in = inches; 12 inches = 1 feet; cfs = cubic feet/sec; a unit hydrograph is the response of catchment due to 1 inch effective rainfall over it.]

(a) Determine the peak discharge (in cfs) for a net rain of 5.00 in./hr and a duration of 2 hr.
(b) What is the total direct surface runoff (in inches) for the storm described in part (a)?
(c) A different storm with a net rain of 0.50 in./hr lasts for 4 hr. What is the discharge at 8 p.m. if the rainfall started at 4 p.m.?

## Short answer

For 5 in/hr for2hr, net rain is10 in, so peak discharge =10×600 =6000 cfs. Total direct runoff equals rainfall depth,10 in. For 0.5 in/hr for4 hr, net rain 2 in gives two 1-in blocks; at 8 p.m. (t=4 hr) Q =400+400=800 cfs.

## Answer

A 2-hr UH gives the response to **1 inch of net rain in 2 hr** (intensity 0.5 in/hr). Ordinates are directly proportional to the net rain depth, and responses of successive blocks are added with a time lag (principle of proportionality and superposition).

Read from the sketch (t, hr: Q, cfs): 0: 0; 1: 200; 2: 400; 3: 600 (peak); 4: 400; 5: 200; tail to about 0 at 9.

#### (a) Peak discharge for 5.00 in/hr for 2 hr
Duration is the same as the UH duration (2 hr), so just scale.

$$
\begin{aligned} \text{net rain} &= 5.00 \times 2 = 10 \text{ in} \\ Q_{peak} &= 10 \times 600 = 6000 \text{ cfs} \end{aligned}
$$

**Answer: 6000 cfs** (at t = 3 hr).

#### (b) Total direct surface runoff
Direct runoff depth equals net (effective) rain depth.

$$
\text{Runoff} = 5.00 \text{ in/hr} \times 2 \text{ hr} = 10 \text{ in}
$$

**Answer: 10 inches** over the basin.

#### (c) Storm of 0.50 in/hr for 4 hr, discharge at 8 p.m.
Net rain is 0.5 × 4 = 2 in, which is two successive 2-hr blocks of 0.5 in/hr × 2 hr = 1 in each. Each block gives one UH (multiplier 1); the second is lagged by 2 hr.

Rain starts at 4 p.m., so 8 p.m. is t = 4 hr:

$$
Q(4) = 1\times U(4) + 1\times U(4-2) = 400 + 400 = 800 \text{ cfs}
$$

**Answer: 800 cfs at 8 p.m.**

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. The UH is for 1 in of net rain in 2 hr. For a 2-hr storm of 10 in net rain, how are ordinates found?
   A. Multiply every UH ordinate by 10
   B. Multiply by 5 (the intensity only)
   C. Multiply by 2 (the duration only)
   D. Shift the UH by 10 hr
   Answer: A. Same duration, so ordinates scale directly with depth (principle of proportionality). (Key point: Proportionality)

2. What is the peak for 5 in/hr for 2 hr, given UH peak 600 cfs?
   A. 3000 cfs
   B. 6000 cfs
   C. 1200 cfs
   D. 600 cfs
   Answer: B. Net rain = 10 in, so Qpeak = 10 x 600 = 6000 cfs. (Key point: Peak discharge)

3. For 0.5 in/hr for 4 hr, how is the discharge at t = 4 hr obtained?
   A. 2 x U(4) = 800 cfs but without lag, since total is 2 in
   B. U(4) only = 400 cfs
   C. 1 x U(4) + 1 x U(2), two 1-in blocks with the second lagged by 2 hr, giving 800 cfs
   D. U(4) + U(4+2) = 600 cfs
   Answer: C. Each 2-hr block gives 1 in; the second is lagged 2 hr: 400 + 400 = 800 cfs. (Key point: Superposition)

## Related in Engineering Hydrology

- [2-hr UH from figure: area, flood, Tc, two storms](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Auh-2hr-figure-four-parts) — Engineering Hydrology, chapter 5
- [Direct runoff hydrograph analysis, 4250-acre basin](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Atrapezoid-dro-4250-acre) — Engineering Hydrology, chapter 5
- [S-curve: 2-hr hydrograph from 4-hr UH](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Ascurve-4hr-to-2hr-12-5) — Engineering Hydrology, chapter 5
- [Rainfall, lag time and time of concentration from hydrograph](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Ahydrograph-figure-lag-tc) — Engineering Hydrology, chapter 5
- [Storm hydrograph from 6-h UH, 3-hr storm](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Astorm-hydrograph-6h-uh-3hr-storm) — Engineering Hydrology, chapter 5, asked 2×
- [2-hr UH and flood hydrograph from storm](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Auh-2h-from-4h-three-storms) — Engineering Hydrology, chapter 5

## Related in other subjects

- [Flow net discharge, 200 cc/day](https://www.bctengineer.com/question.md?key=semester_4%2Fsoil_mechanics%3Aflow-net-discharge-numerical-200cc) — Soil Mechanics, chapter 7
- [Unit and mortar for 200 x 400 column](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Acolumn-200x400-120kn) — Concrete Technology and Masonry Structure, chapter 8
- [Vertical curve 200 m, +1.50% then -2.5%](https://www.bctengineer.com/question.md?key=semester_4%2Fsurveying_ii%3Avertical-curve-200m-upward-15-down) — Surveying II, chapter 6
- [Checking whether root locus passes through point P](https://www.bctengineer.com/question.md?key=semester_3%2Fcontrol_systems%3Arl-point-p-dominant) — Control Systems, chapter 5