# Safety precautions in electrical works

Building Technology · Chapter 12: Other services in building

- Asked in: 2080 Chaitra, 4 marks; 2078 Poush, 4 marks; 2066 Bhadra (old course), 4 marks (asked 3 times)
- Video: [Electrical Safety Basic Training for Non-Electricians | Schneider Electric](https://www.youtube.com/watch?v=ggJo6m8NZtA) — Schneider Electric
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_6/building_technology/electrical-safety
- Whole chapter: https://www.bctengineer.com/md/semester_6/building_technology/chapter-12

## Question

Explain the safety precautions to be taken during electrification (electrical wiring works) of a building.

## Short answer

Earthing all metal parts (resistance <5 ohm) and using MCB, ELCB/RCD (30 mA) prevent shock and fire. Switches and fuses connect only the phase; wires must be properly sized, insulated, and kept from water and heat. Work only when supply is off, using insulated tools, and test insulation regularly.

## Answer

Electricity can cause shock, burns and fire, so every stage of the electrification of a building must follow safety rules (Nepal Electricity Act / Regulations, NBC 207 and IS 732).

#### Safety precautions
- **Earthing:** connect all metal parts of appliances and the DB to earth (earth pit with a GI plate/pipe, resistance less than 5 ohm for buildings) to avoid shock.
- **Protective devices:** fuses, MCB, MCCB and ELCB/RCD (30 mA) to cut the supply on overload, short circuit and leakage; a lightning arrester on the roof.
- **Proper materials:** use standard-quality wires, switches and fittings of the correct current rating, and the proper conductor size for the load.
- **Switch only the live (phase) wire:** switches and fuses on the phase; neutral kept solid; use 3-pin plugs.
- **Insulation and joints:** all joints properly made and insulated; no bare wire; use junction boxes.
- **Avoid overloading:** do not connect many appliances to one socket; use separate circuits for heavy loads (AC, geyser).
- **Safe location:** keep wiring away from water pipes, gas lines and hot surfaces; place sockets and switches out of reach of children and away from bathrooms (or use waterproof types), at sufficient height.
- **During work:** switch off the main supply before repair; use insulated tools, rubber gloves and mats, and "danger/men at work" notices; avoid working in wet conditions; employ qualified electricians only.
- **Fire precautions:** keep extinguishers (CO2/dry powder) nearby; never use water on an electrical fire.
- **Testing and maintenance:** test insulation resistance (megger) and earth continuity after installation and periodically.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Why are metal parts earthed?
   A. To avoid shock by providing a path for fault current to earth
   B. To increase voltage
   C. To save energy
   D. To make wires thicker
   Answer: A. Earthing (resistance less than 5 ohm) prevents shock. (Key point: Earthing)

2. Where should switches and fuses be placed?
   A. On the live (phase) wire
   B. On the neutral wire
   C. On the earth wire
   D. Anywhere
   Answer: A. Placing on phase ensures the equipment is dead when off. (Key point: Switch position)

3. What is the role of an ELCB/RCD (30 mA)?
   A. Increase current
   B. Cut supply on earth leakage
   C. Measure insulation
   D. Limit voltage drop
   Answer: B. It trips on small leakage currents. (Key point: ELCB)

4. What should never be used on an electrical fire?
   A. CO2 extinguisher
   B. Dry powder
   C. Water
   D. Switching off main supply
   Answer: C. Water conducts electricity; use CO2 or dry powder. (Key point: Fire)

## Related in Building Technology

- [Electrical services principles, wiring, safety](https://www.bctengineer.com/question.md?key=semester_6%2Fbuilding_technology%3Aelectrical-principles-wiring-safety) — Building Technology, chapter 12
- [Electrical wiring systems](https://www.bctengineer.com/question.md?key=semester_6%2Fbuilding_technology%3Aelectrical-wiring-systems) — Building Technology, chapter 12, asked 3×
- [Fundamental requirements of electrical wiring](https://www.bctengineer.com/question.md?key=semester_6%2Fbuilding_technology%3Aelectrical-wiring-requirements) — Building Technology, chapter 12
- [Electrification system and fire protection](https://www.bctengineer.com/question.md?key=semester_6%2Fbuilding_technology%3Aelectrification-fire) — Building Technology, chapter 12

## Related in other subjects

- [General electrical rules for installation and wiring](https://www.bctengineer.com/question.md?key=semester_6%2Findustrial_power_distribution_and_illumination%3Aelectrical-rules-installation) — Industrial Power Distribution and Illumination, chapter 1, asked 3×
- [Short note: Electrical safety rules](https://www.bctengineer.com/question.md?key=semester_1%2Fbasic_electrical_and_electronics_engineering%3Ashort-note-electrical-safety-rules) — Basic Electrical and Electronics Engineering, chapter 4, asked 2×
- [Basic electrical safety rules and regulations](https://www.bctengineer.com/question.md?key=semester_8%2Fhigh_voltage_engineering%3Aelectrical-safety-rules) — High Voltage Engineering, chapter 2
- [Planning electrical installation of industrial building](https://www.bctengineer.com/question.md?key=semester_6%2Findustrial_power_distribution_and_illumination%3Aplanning-industrial-installation) — Industrial Power Distribution and Illumination, chapter 5