# Both types of BCR, gradient income and cost

Engineering Economics · Chapter 3: Basic Methodologies of Engineering Economic Analysis

- Asked in: 2072 Asoj, 6 marks
- Video: [Engineering Economics: Benefit - Cost Ratio (Part 1/2)](https://www.youtube.com/watch?v=KJa45xBT1PQ) — MEL Designs
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_6/engineering_economics/bcr-both-growing-12years
- Whole chapter: https://www.bctengineer.com/md/semester_6/engineering_economics/chapter-3

## Question

Calculate both types of BCR of a project with the following details. MARR = 12%.
| Initial Investment | Annual Income | Annual Cost | Useful Life | Salvage Value |
|---|---|---|---|---|
| Rs. 100000 | Rs. 20000 at the end of first year and increase by 5% per year | Rs. 3000 at the end of first year and increase by Rs. 500 per year | 12 years | 25000 |

## Short answer

Compute PW of benefits (growing at 5%) = Rs 154,014, PW of O&M (Rs 500 gradient) = Rs 31,559, salvage PW = Rs 6,417. Conventional B/C = 1.23, modified B/C = 1.31 (both >1, acceptable).

## Answer

Assumption: PW formulation is used. Definitions:

- Conventional B/C = PW(B) / [I + PW(O&M) − PW(S)]
- Modified B/C = [PW(B) − PW(O&M)] / [I − PW(S)]

```text
 Benefit : 20,000 grows 5%/yr   -> 20,000, 21,000, 22,050 ...
 Cost    : 3,000 + 500/yr       -> 3,000, 3,500, 4,000 ...
 Year 12 : salvage 25,000;  Year 0: investment 1,00,000
```
Factors at i = 12%, n = 12: (P/A) = 6.1944, (P/G) = 25.9523, (P/F) = 0.2567

**PW of benefits (geometric, g = 5%)**

PW(B) = 20,000 × [1 − (1.05/1.12)^12] / (0.12 − 0.05) = 20,000 × 7.7007 = Rs 154,014

**PW of O&M cost (gradient)**

PW(M) = 3,000 (P/A, 12%, 12) + 500 (P/G, 12%, 12) = 3,000 × 6.1944 + 500 × 25.9523 = 18,583 + 12,976 = Rs 31,559

**PW of salvage**

PW(S) = 25,000 × 0.2567 = Rs 6,417

**Conventional B/C** = 154,014 / (1,00,000 + 31,559 − 6,417) = 154,014 / 125,142 = **1.231**

**Modified B/C** = (154,014 − 31,559) / (1,00,000 − 6,417) = 122,455 / 93,583 = **1.309**

**Answer: conventional B/C = 1.23, modified B/C = 1.31. Both are greater than 1, so the project is acceptable at MARR = 12%.**

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Which formula gives PW of a benefit growing 5% per year at i = 12%?
   A. B1 x (P/A, 12%, 12)
   B. B1 x (P/G, 12%, 12)
   C. B1[1 - (1.05/1.12)^12]/(0.12 - 0.05)
   D. B1 x (P/F, 12%, 12)
   Answer: C. Geometric series: PW = B1[1 - ((1+g)/(1+i))^n]/(i - g) = 154,014. (Key point: PW of benefits)

2. How is the cost 3,000 rising by 500 per year valued?
   A. 3,000(P/A) + 500(P/G)
   B. 3,000(P/A) only
   C. 3,000(P/G) + 500(P/A)
   D. 3,500(P/A)
   Answer: A. A base annuity plus a gradient: 18,583 + 12,976 = 31,559. (Key point: PW of O&M)

3. Which ratio is higher here and why?
   A. Conventional, since salvage is added
   B. Modified (1.31), since O&M is netted from benefits
   C. They are equal
   D. Conventional, since O&M is smaller
   Answer: B. When B/C > 1, moving O&M from the denominator to the numerator raises the ratio. (Key point: Conventional vs modified)

4. How is the Rs 25,000 salvage treated?
   A. Added to benefits at full value
   B. Ignored
   C. Divided by 12
   D. Discounted from year 12 (x 0.2567) and subtracted from investment side
   Answer: D. PW(S) = 6,417 is subtracted in the denominator. (Key point: Salvage)

## Related in Engineering Economics

- [Both types of BCR with FW, growing income](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Abcr-fw-growing-income) — Engineering Economics, chapter 3
- [Both BCR with FW, gradient revenue](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Abcr-fw-gradient-revenue-250000) — Engineering Economics, chapter 3
- [PW sensitivity to investment, income, life by ±25%](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Asensitivity-pw-400000-60000-25) — Engineering Economics, chapter 6
- [Both types of BCR (FW) for Machine A](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Abcr-fw-machine-a-10yr) — Engineering Economics, chapter 3
- [Sensitivity of PW to investment and MARR](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Asensitivity-investment-marr-10-50) — Engineering Economics, chapter 6, asked 2×
- [Sensitivity on initial cost and life; interpret](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Asensitivity-30-initial-cost-life-25) — Engineering Economics, chapter 6

## Related in other subjects

- [Capital budgeting; ARR numerical, Rs 100000](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Acapital-budgeting-arr-numerical-c72) — Project Engineering, chapter 6
- [Feasibility using two methods, MARR 15%](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Afeasibility-two-methods-marr-15) — Project Engineering, chapter 6
- [EPS and book value; ABC project Rs 6,00,000](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeps-bv-abc-project-600000-b79) — Project Engineering, chapter 6
- [Capitalized value of 80-year building](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Avalue-building-80-years-2078) — Construction Management, chapter 13