# Cost variance analysis from standard and actual

Engineering Economics · Chapter 1: Introduction

- Asked in: 2068 Jestha, 10 marks
- Video: [Cost Variance | Theory + Numerical | Economics | 2019.2018.2017.2016.2011 PU/TU/KU/PoU](https://www.youtube.com/watch?v=W9bWYDQGCqQ) — Sudip Dhakal
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_6/engineering_economics/cost-variance-analysis-9000-units
- Whole chapter: https://www.bctengineer.com/md/semester_6/engineering_economics/chapter-1

## Question

Perform cost variance analysis.
|  | Standard (Rs) | Actual (Rs) |
|---|---|---|
| Production (Units) | 9,000 | 8,000 |
| Direct Labour (Hours) | 72,000 | 60,000 |
| Direct Labour cost (Rs.) | 756,000 | 600,000 |
| Fixed overhead cost (Rs.) | 900,000 | 810,000 |
| Variable overhead cost (Rs.) | 684,000 | 630,000 |

## Short answer

Labour variance: Rs 72,000 F (rate Rs 30,000 F, efficiency Rs 42,000 F). Fixed overhead: Rs 10,000 A. Variable overhead: Rs 22,000 A. Labour well-controlled; overhead spending above standard.

## Answer

#### Standard rates (from the standard column)
- Standard hours per unit = 72,000 / 9,000 = 8 h
- Standard labour rate = 756,000 / 72,000 = Rs 10.50 per hour
- Fixed overhead rate = 900,000 / 72,000 = Rs 12.50 per hour (budgeted fixed overhead Rs 900,000)
- Variable overhead rate = 684,000 / 72,000 = Rs 9.50 per hour

Actual output = 8,000 units, so **standard hours for actual output (SH) = 8,000 × 8 = 64,000 h**. Actual hours AH = 60,000 h.

#### 1. Direct labour variances
| Variance | Calculation | Rs |
|---|---|---|
| Rate variance | (SR − AR) × AH = (10.50 − 10.00) × 60,000 | 30,000 F |
| Efficiency variance | (SH − AH) × SR = (64,000 − 60,000) × 10.50 | 42,000 F |
| **Total labour cost variance** | Std cost for actual output 672,000 − actual 600,000 | **72,000 F** |

#### 2. Fixed overhead variances
Absorbed FOH = 64,000 × 12.50 = 800,000; actual = 810,000.
| Variance | Calculation | Rs |
|---|---|---|
| Expenditure | Budgeted 900,000 − actual 810,000 | 90,000 F |
| Capacity (volume) | (AH − budgeted hours) × rate = (60,000 − 72,000) × 12.50 | 150,000 A |
| Efficiency | (SH − AH) × 12.50 = 4,000 × 12.50 | 50,000 F |
| Volume variance | 150,000 A + 50,000 F | 100,000 A |
| **Total FOH variance** | Absorbed 800,000 − actual 810,000 | **10,000 A** |

#### 3. Variable overhead variances
Std VOH for actual output = 64,000 × 9.50 = 608,000; actual = 630,000.
| Variance | Calculation | Rs |
|---|---|---|
| Expenditure | AH × SR − actual = 60,000×9.50 − 630,000 = 570,000 − 630,000 | 60,000 A |
| Efficiency | (SH − AH) × 9.50 = 4,000 × 9.50 | 38,000 F |
| **Total VOH variance** | 608,000 − 630,000 | **22,000 A** |

(F = favourable, A = adverse.)

**Answer: Labour 72,000 F (rate 30,000 F, efficiency 42,000 F); fixed overhead 10,000 A; variable overhead 22,000 A.** Overall, labour is well controlled, but overhead spending is above the standard.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Standard hours for actual output of 8,000 units are:
   A. 60,000 h
   B. 8,000 x 8 = 64,000 h
   C. 8,000 x 9 = 72,000 h
   D. 72,000 h
   Answer: B. Standard is 8 h per unit. (Key point: Standard hours for actual output)

2. Labour rate variance = (SR - AR) x AH =
   A. 4,000 x 10.50 = 42,000 F
   B. (10.50 - 10.00) x 64,000 = Rs 32,000 F
   C. (10.50 - 10.00) x 60,000 = Rs 30,000 F
   D. (10.00 - 10.50) x 60,000 = 30,000 A
   Answer: C. Actual hours are paid Rs 0.50 less than standard rate. (Key point: Labour rate variance)

3. Labour efficiency variance = (SH - AH) x SR:
   A. 4,000 x 10 = Rs 40,000 F
   B. 12,000 x 10.50 = Rs 126,000 F
   C. 4,000 x 12.50 = 50,000 F
   D. 4,000 x 10.50 = Rs 42,000 F
   Answer: D. Fewer actual hours than standard for the output is favourable. (Key point: Labour efficiency)

4. Capacity variance for fixed overhead is:
   A. (60,000 - 72,000) x 12.50 = Rs 150,000 A
   B. (64,000 - 60,000) x 12.50 = 50,000 F
   C. 900,000 - 810,000 = 90,000 F
   D. (64,000 - 72,000) x 12.50 = 100,000 A
   Answer: A. Actual hours fell short of budgeted hours. (Key point: Fixed overhead capacity)

## Related in Engineering Economics

- [Fixed overhead cost variance from standard card](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Afixed-overhead-variance-standard-card) — Engineering Economics, chapter 1
- [Variance analysis, 9,300 vs 10,500 units](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Avariance-production-9300-units) — Engineering Economics, chapter 1
- [Standard costing variances for a building company](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Avariances-cement-mason-standard-costing) — Engineering Economics, chapter 1
- [Standard costing variances, 3000 vs 2500 units](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Avariances-3000-units-27-days) — Engineering Economics, chapter 1

## Related in other subjects

- [EVA; 60 days, 25% work, Rs 12,00,000](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeva-numerical-60-days-25-percent) — Project Engineering, chapter 4
- [EVA; 10 days, 50 labour days at Rs 1000](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeva-numerical-labour-days-1000) — Project Engineering, chapter 4, asked 2×
- [EVA; plantation 50 units, 4 weeks, Rs 200](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeva-plantation-4-weeks-200-c74) — Project Engineering, chapter 4, asked 2×
- [EVA; plantation 50 units, 3 weeks, Rs 2500](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeva-plantation-3-weeks-2500-a76) — Project Engineering, chapter 4, asked 2×