# Financial vs economic analysis; both BCR

Engineering Economics · Chapter 3: Basic Methodologies of Engineering Economic Analysis

- Asked in: 2070 Magh, 2+4 marks
- Video: [Unit:5 | Cost/Benefit Ratio | B/C Ratio | BCRM ratio | Engineering Economics | Prashant YT | BECivil](https://www.youtube.com/watch?v=OyKEBsyVnpM) — Prashant YT
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_6/engineering_economics/financial-vs-economic-bcr-300000
- Whole chapter: https://www.bctengineer.com/md/semester_6/engineering_economics/chapter-3

## Question

What is the difference between financial and economic analysis? Determine both types of B/C ratio from the following cash flow.
Initial investment = 3,00,000
Annual revenue = 85,000
Annual costs = 15,000
Salvage value = 20% of initial investment
Useful life = 6 years
MARR = 10%

## Short answer

Financial analysis uses market prices and owner viewpoint; economic analysis uses shadow prices and society viewpoint, including externalities. With MARR=10%, 6-year life, conventional B/C=1.12, modified B/C=1.15 (both >1, acceptable).

## Answer

#### Financial vs economic analysis
| Basis | Financial analysis | Economic analysis |
|---|---|---|
| Viewpoint | Owner / investor / firm | Society / nation as a whole |
| Measures | Cash revenues and costs actually paid or received | All benefits and costs to society, even if not paid in cash |
| Prices | Market prices | Shadow (economic) prices |
| Taxes, subsidies | Included as real cash flows | Treated as transfers and excluded |
| Externalities | Ignored | Included (pollution, employment, foreign exchange) |
| Interest rate | Company MARR / cost of capital | Social discount rate |
| Aim | Profit and financial viability | Net contribution to national welfare |

#### Numerical (PW formulation, i = 10%, n = 6)
- Salvage S = 20% × 3,00,000 = Rs 60,000
- Factors: (P/A, 10%, 6) = 4.3553; (P/F, 10%, 6) = 0.5645

```text
 yr 0: -3,00,000     yr 1..6: +85,000 revenue, -15,000 cost     yr 6: +60,000
```
- PW(B) = 85,000 × 4.3553 = Rs 370,197
- PW(C: O&M) = 15,000 × 4.3553 = Rs 65,329
- PW(S) = 60,000 × 0.5645 = Rs 33,868

**Conventional B/C** = PW(B) / [I + PW(C) − PW(S)] = 370,197 / (3,00,000 + 65,329 − 33,868) = 370,197 / 331,460 = **1.117**

**Modified B/C** = [PW(B) − PW(C)] / [I − PW(S)] = (370,197 − 65,329) / (3,00,000 − 33,868) = 304,868 / 266,132 = **1.146**

**Answer: conventional B/C = 1.12 and modified B/C = 1.15. Both are greater than 1, so the project is acceptable.**

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Whose viewpoint does economic analysis take?
   A. The owner only
   B. Society or nation as a whole
   C. The bank
   D. The tax office
   Answer: B. Financial analysis is from the owner's viewpoint. (Key point: Viewpoint)

2. How are taxes and subsidies treated in economic analysis?
   A. As transfers, excluded
   B. As real cash flows
   C. As benefits
   D. As salvage
   Answer: A. They are real cash flows in financial analysis but transfers in economic analysis. (Key point: Taxes)

3. What is salvage value here?
   A. Rs 20,000
   B. Rs 3,00,000
   C. Rs 60,000 (20% of 3,00,000)
   D. Rs 15,000
   Answer: C. 0.20 x 3,00,000 = 60,000. (Key point: Salvage value)

4. What are the conventional and modified B/C?
   A. 1.15 and 1.12, reject
   B. 0.89 and 0.87, reject
   C. 1.12 and 1.15, reject
   D. 1.12 and 1.15, both above 1, accept
   Answer: D. 370,197/331,460 = 1.117 and 304,868/266,132 = 1.146. (Key point: Results)

## Related in Engineering Economics

- [AW sensitivity to investment and net annual cash flow](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Asensitivity-aw-500000-75000) — Engineering Economics, chapter 6
- [Both BCR with FW, gradient revenue](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Abcr-fw-gradient-revenue-250000) — Engineering Economics, chapter 3
- [Sensitivity to investment, revenue and life](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Asensitivity-30-investment-revenue-life-500000) — Engineering Economics, chapter 6
- [Sensitivity on investment, revenue and life; interpret](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Asensitivity-30-initial-100000-useful-10) — Engineering Economics, chapter 6
- [Both types of BCR with FW, growing income](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Abcr-fw-growing-income) — Engineering Economics, chapter 3
- [Both types of BCR, gradient income and cost](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Abcr-both-growing-12years) — Engineering Economics, chapter 3

## Related in other subjects

- [EPS and book value; Rs 10,00,000, 3500 shares](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeps-bv-capital-1000000-3500-shares) — Project Engineering, chapter 6
- [EPS and book value; ABC project Rs 6,00,000](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeps-bv-abc-project-600000-b79) — Project Engineering, chapter 6
- [Importance of appraisal; economic vs financial](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aappraisal-importance-economic-financial) — Project Engineering, chapter 2
- [EPS and book value; capital Rs 5,00,000](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeps-bv-capital-500000-2000-shares) — Project Engineering, chapter 6