title: "Slope area method of discharge"
subject: "Hydro Power"
chapter: 2
key: "semester_6/hydro_power:slope-area-method"
source: https://www.bctengineer.com/q/semester_6/hydro_power/slope-area-method
site: BCT Engineering
---

# Slope area method of discharge

Hydro Power · Chapter 2: Introduction to Hydrology

- Asked in: 2071 Magh, 6 marks
- Video: [Discharge Measurement By Slope Area Method tutorial | Slope Area Method for discharge measurement](https://www.youtube.com/watch?v=re3ZXvFBoII) — Civil Guys
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_6/hydro_power/slope-area-method
- Whole chapter: https://www.bctengineer.com/md/semester_6/hydro_power/chapter-2

## Question

How the discharge of a stream or river can be computed by slope area method?

## Short answer

The slope-area method computes flood discharge from high-water marks and surveyed cross-sections. Using Manning’s equation, energy equation, and conveyance, discharge is found by trial as Q = K√(hf/L), where friction slope hf/L is corrected for velocity head changes.

## Answer

The **slope-area method** is an indirect method of finding discharge, mainly used for **flood peaks** when direct current-meter measurement is not possible. Discharge is computed from the water surface slope (from high flood marks) and the channel cross-sections, using Manning's equation.

#### Field work
1. Select a fairly straight, uniform reach (length $L$, about 75 m or more, fall ≥ 0.15 m).
2. After the flood, survey **high water marks** (silt lines, debris) at two (or more) sections 1 and 2.
3. Survey the cross-sections to get area $A$, wetted perimeter $P$ and hydraulic radius $R$ at each section.
4. Estimate Manning's $n$ from bed and bank conditions.

```text
  Sec 1                   Sec 2
  ___ HFL ___  Dz (fall)
  |          ------____
  |  y1        L        ----___ HFL
  |____________________________y2_|
  =========== bed ============>
```

#### Computation
Energy equation between sections 1 and 2:
$$
h_f = (Z_1 - Z_2) + \left(\frac{V_1^2}{2g} - \frac{V_2^2}{2g}\right) - h_e
$$
where $Z$ = water surface elevation, $h_e$ = eddy loss $= K_e\left|\frac{V_1^2}{2g} - \frac{V_2^2}{2g}\right|$ ($K_e \approx 0$–0.1 for contracting, 0.3 for expanding reach).

Conveyance $K = \dfrac{1}{n}AR^{2/3}$ at each section; average $K = \sqrt{K_1K_2}$.
$$
Q = K\sqrt{S_f}, \qquad S_f = \frac{h_f}{L}
$$

Since $V$ depends on $Q$, solve by **trial**:
1. First take $h_f = Z_1 - Z_2$ (fall), find $S_f$ and $Q$.
2. Compute $V_1 = Q/A_1$, $V_2 = Q/A_2$; correct $h_f$ with the velocity head and eddy loss terms.
3. Repeat until $Q$ stops changing (usually 2–3 trials).

Limitations: accuracy depends on the choice of $n$ and on reliable flood marks; the reach must be free of backwater and sudden changes.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. When is the slope-area method mainly used?
   A. To estimate flood peaks when direct measurement is not possible
   B. To calibrate a current meter
   C. To measure low flows with a weir
   D. To compute rainfall
   Answer: A. It is an indirect method for flood peaks, using high flood marks after the flood. (Key point: Purpose of the method)

2. Which field data are needed for the slope-area method?
   A. Rainfall at each gauge
   B. High water marks at two sections, cross-sections and Manning's n
   C. Revolutions of a current meter
   D. Sediment concentration only
   Answer: B. High water marks give the surface slope; cross-sections give A, P and R; n is estimated from channel conditions. (Key point: Field data)

3. How is discharge computed?
   A. Q = K x Sf, with K = AR
   B. Q = K x Sf^2
   C. Q = K sqrt(Sf), with K = (1/n) A R^(2/3)
   D. Q = A / Sf
   Answer: C. Manning's equation gives Q = K sqrt(Sf), where Sf = hf/L. (Key point: Conveyance and discharge)

4. Why is the slope-area solution done by trial?
   A. Because n is unknown
   B. Because the sections are not surveyed
   C. Because L changes each time
   D. Because velocity head in hf depends on Q, which is not yet known
   Answer: D. hf includes velocity head terms depending on Q, so Q is assumed from the fall, then corrected until it stops changing. (Key point: Trial procedure)

## Related in Hydro Power

- [Stream discharge from current meter revolutions (V = 0.51N + 0.03)](https://www.bctengineer.com/question.md?key=semester_6%2Fhydro_power%3Astream-gauging-revolutions-0-51) — Hydro Power, chapter 2, asked 2×
- [Stream discharge from current meter revolutions (v = 0.55N + 0.04)](https://www.bctengineer.com/question.md?key=semester_6%2Fhydro_power%3Astream-gauging-revolutions-0-55) — Hydro Power, chapter 2, asked 2×
- [River discharge by mid-section method](https://www.bctengineer.com/question.md?key=semester_6%2Fhydro_power%3Amid-section-discharge) — Hydro Power, chapter 2
- [Discharge from 0.2d and 0.8d velocities (right bank)](https://www.bctengineer.com/question.md?key=semester_6%2Fhydro_power%3Astream-gauging-right-bank) — Hydro Power, chapter 2
- [Discharge from depth and mean velocity data](https://www.bctengineer.com/question.md?key=semester_6%2Fhydro_power%3Adischarge-depth-mean-velocity) — Hydro Power, chapter 2
- [Stream gauging with calibration equation](https://www.bctengineer.com/question.md?key=semester_6%2Fhydro_power%3Astream-gauging-calibration-no-data) — Hydro Power, chapter 2

## Related in other subjects

- [Slope-area flood discharge, Marin River at Kusuntar](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Aslope-area-marin-kusuntar) — Engineering Hydrology, chapter 4
- [Stream flow by slope-area method](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Aslope-area-method-explain) — Engineering Hydrology, chapter 4, asked 3×
- [Slope-area discharge, 1300 m reach](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Aslope-area-3500-3250) — Engineering Hydrology, chapter 4, asked 2×
- [Slope-area flood discharge, 7 km reach](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Aslope-area-45-50-7km) — Engineering Hydrology, chapter 4, asked 2×