title: "Maximum demand and need to calculate it"
subject: "Industrial Power Distribution and Illumination"
chapter: 1
key: "semester_6/industrial_power_distribution_and_illumination:maximum-demand-need"
source: https://www.bctengineer.com/q/semester_6/industrial_power_distribution_and_illumination/maximum-demand-need
site: BCT Engineering
---

# Maximum demand and need to calculate it

Industrial Power Distribution and Illumination · Chapter 1: Introduction

- Asked in: 2073 Magh, 2+6 marks
- Video: [मैक्सिमम डिमांड क्या होता है || What is MD (Maximum demand) hindi | How work M.D. power electrical](https://www.youtube.com/watch?v=oHBP-M48cX4) — Electrical Dost
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_6/industrial_power_distribution_and_illumination/maximum-demand-need
- Whole chapter: https://www.bctengineer.com/md/semester_6/industrial_power_distribution_and_illumination/chapter-1

## Question

What is Maximum Demand? With suitable example, explain the need to calculate Maximum Demand in an industrial building.

## Short answer

Maximum demand (MD) is the highest average load (kW/kVA) over a 15-30 min period. It sizes transformers, cables, switchgear; sets contract demand and demand charges; guides protection settings; enables load shifting to reduce MD; aids utility planning; and determines capacitor sizing. Example: factory with 80 kW connected load has actual MD 60 kW, leading to 100 kVA transformer and 70 kVA contract demand.

## Answer

**Maximum demand (MD)** is the greatest load (kW or kVA) drawn by an installation during a given period. It is usually measured as the highest average demand over a short interval, normally 15 or 30 minutes, by an MD meter. It is always less than or equal to the connected load.

#### Need to calculate maximum demand in an industrial building
1. **Sizing the transformer and generator:** the substation transformer and standby DG set are chosen to supply the maximum demand plus a margin, not the total connected load. This avoids heavy oversizing.
2. **Sizing cables, busbars and switchgear:** the main incomer, busbars and feeders must carry the maximum demand current without overheating.
3. **Contract demand and tariff:** industrial consumers pay a **demand charge** (Rs per kVA or kW of MD) plus an energy charge. Knowing the MD lets the plant choose the right contract demand and avoid penalty for exceeding it.
4. **Protection settings:** relay and breaker settings are based on the maximum load current.
5. **Demand control:** knowing when MD occurs lets the plant shift loads (for example run pumps or furnaces off-peak) to lower the MD and the bill.
6. **Planning:** the utility needs the MD to design the feeder and to plan generation.
7. **Power factor correction:** capacitor sizing uses the kW and kVA at maximum demand.

#### Example
A garment factory has a connected load of:

| Load | Rating |
|---|---|
| 50 sewing machines | 0.4 kW each = 20 kW |
| 2 boilers/irons | 30 kW |
| Lighting and fans | 15 kW |
| Compressor | 15 kW |
| **Total connected** | **80 kW** |

If 80% of the sewing machines, both boilers, all lighting and the compressor were assumed to run together at full rating, the worst-case estimate would be:

```text
0.8×20 + 30 + 15 + 15 = 76 kW
```
But the boilers and the compressor switch on and off with their thermostats and pressure switches, so they are not all at full load in the same 30 minutes. MD meter records show the actual peak is about **60 kW**. Then:
- Demand factor = 60/80 = 0.75.
- A transformer of about 60/0.85 ≈ 71 kVA plus margin → **100 kVA** is chosen, not one based on 80 kW plus large margins.
- The contract demand is fixed near 70 kVA, saving demand charges every month.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. How is maximum demand usually measured?
   A. As the sum of all nameplate ratings
   B. As the highest average load over a 15 or 30 minute interval by an MD meter
   C. As the instantaneous peak lasting a microsecond
   D. As total energy divided by 24
   Answer: B. MD is the highest average demand over a short interval. (Key point: Definition of MD)

2. Why are the transformer and DG set sized on maximum demand?
   A. To avoid heavy oversizing based on total connected load
   B. Because connected load is always smaller
   C. To make them run at no load
   D. Because MD includes all spare equipment
   Answer: A. They are chosen for MD plus a margin, not the sum of ratings. (Key point: Sizing)

3. Why does knowing MD help with the tariff?
   A. It removes the energy charge
   B. It makes demand charge zero
   C. It lets the plant ignore the utility
   D. It lets the plant choose the right contract demand and avoid penalties for exceeding it
   Answer: D. Demand charge is based on MD, so contract demand must match it. (Key point: Tariff)

4. In the example, connected load is 80 kW and actual MD is 60 kW. What is the demand factor?
   A. 1.33
   B. 0.60
   C. 0.75
   D. 0.85
   Answer: C. 60/80 = 0.75. (Key point: Garment factory example)

## Related in Industrial Power Distribution and Illumination

- [Load centre, connected load, maximum demand](https://www.bctengineer.com/question.md?key=semester_6%2Findustrial_power_distribution_and_illumination%3Aload-centre-connected-load-md) — Industrial Power Distribution and Illumination, chapter 1
- [Wires and cables in industrial building](https://www.bctengineer.com/question.md?key=semester_6%2Findustrial_power_distribution_and_illumination%3Awires-cables-industrial-building) — Industrial Power Distribution and Illumination, chapter 3
- [Planning electrical installation of industrial building](https://www.bctengineer.com/question.md?key=semester_6%2Findustrial_power_distribution_and_illumination%3Aplanning-industrial-installation) — Industrial Power Distribution and Illumination, chapter 5
- [Load factor and demand factor numerical](https://www.bctengineer.com/question.md?key=semester_6%2Findustrial_power_distribution_and_illumination%3Aconsumer-load-demand-factor) — Industrial Power Distribution and Illumination, chapter 1
- [Connected load, MD, demand, diversity, load factor](https://www.bctengineer.com/question.md?key=semester_6%2Findustrial_power_distribution_and_illumination%3Aload-terminology-five-terms) — Industrial Power Distribution and Illumination, chapter 1
- [Demand factor and diversity factor of substation](https://www.bctengineer.com/question.md?key=semester_6%2Findustrial_power_distribution_and_illumination%3Aload-centre-demand-diversity-numerical) — Industrial Power Distribution and Illumination, chapter 1

## Related in other subjects

- [I-section purlin for industrial building](https://www.bctengineer.com/question.md?key=semester_6%2Fdesign_of_steel_and_timber_structure%3Apurlin-i-section-industrial) — Design of Steel and Timber Structure, chapter 8
- [Need for diversity; maximum ratio combining](https://www.bctengineer.com/question.md?key=semester_7%2Fwireless_communication%3Adiversity-need-mrc) — Wireless Communication, chapter 5
- [Wind load on industrial truss, 40 m span](https://www.bctengineer.com/question.md?key=semester_6%2Fdesign_of_steel_and_timber_structure%3Awind-industrial-40m-span) — Design of Steel and Timber Structure, chapter 8
- [Classifying consumers; factors influencing demand](https://www.bctengineer.com/question.md?key=semester_7%2Futilization_of_electrical_energy%3Aclassifying-consumers-demand-factors) — Utilization of Electrical Energy, chapter 1