# Layout planning of surface drainage system

Irrigation and Drainage Engineering · Chapter 9: Water Logging and Drainage

- Asked in: 2079 Asoj, 4 marks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_6/irrigation_and_drainage_engineering/surface-drainage-layout-planning
- Whole chapter: https://www.bctengineer.com/md/semester_6/irrigation_and_drainage_engineering/chapter-9

## Question

Discuss with sketch the layout planning of the various components of surface drainage system.

## Short answer

Field drains collect from bunded fields, discharging into collector drains that feed a main drain to a natural stream. Drains follow lowest ground; canals run on ridges, drains in valleys, and water levels are kept at least 0.3 m below outlets.

## Answer

The layout of a surface drainage system is planned so that every field outlet discharges by gravity into a drain, and the water moves from small drains to larger ones until it reaches the natural outlet.

#### Components
1. **Field drains (laterals):** shallow drains at the lower side of the fields, which receive water from the bunded fields' outlets.
2. **Collector drains:** receive water from several field drains; run across or along the ground slope.
3. **Main (outfall) drain:** receives the flow of the collectors and delivers it to a natural drain/river.
4. **Outlet:** structure at the junction with the river with a flap gate or sill to prevent backflow.
5. **Structures:** culverts at crossings of roads/canals, drops where the slope is steep.

```text
        irrigation canal ======================
        | field | field | field |  <- bunded fields
  ------+-------+-------+-------+----- field drains
        |       |       |       |
        v       v       v       v
  ===========================>  collector drain
                |
                v  main drain
              ~~~~~~~~~~~~~~~~~~~ natural river
```

#### Planning principles
- Drains follow the **lowest lines** of the land (natural depressions), and are kept parallel to the contours for the field drains and along the slope for collectors.
- The irrigation canal runs on the ridge, the drains in the valleys; drain and canal do not run side by side.
- The spacing of the field drains depends on the size of fields and the land slope (typically 100–300 m).
- Water level in each drain is at least 0.3 m below the outlets it receives.
- Minimum number of crossings and a short route to the outfall; the layout should avoid cutting through villages and roads.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. In what order does water move in a surface drainage layout?
   A. Field drain, collector drain, main drain, then natural river
   B. Main drain, collector, field drain, river
   C. Collector, river, field drain
   D. Field drain straight to river always
   Answer: A. Water moves from small drains to larger ones until it reaches the natural outlet. (Key point: Flow hierarchy)

2. What is provided at the junction with the river?
   A. A canal head regulator
   B. Outlet structure with a flap gate or sill to prevent backflow
   C. A weir to raise water level
   D. Nothing
   Answer: B. A flap gate or sill stops river water flowing back into the drain. (Key point: Outlet protection)

3. Where are canals and drains placed?
   A. Drain on the ridge, canal in the valley
   B. Side by side along the same line
   C. Canal on the ridge, drains in the valleys following the lowest lines
   D. Both along the highest line
   Answer: C. Drains follow the lowest lines of the land; the canal runs on the ridge and they do not run side by side. (Key point: Canal and drain positions)

4. What water-level rule applies?
   A. Drain level 0.3 m above the outlets
   B. Equal to outlet level
   C. Any level
   D. Water level in each drain at least 0.3 m below the outlets it receives
   Answer: D. Keeping the drain level 0.3 m below outlets ensures free gravity drainage. (Key point: Water level in drains)

## Related in Irrigation and Drainage Engineering

- [Components and layout of diversion headworks](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Aheadworks-components-layout) — Irrigation and Drainage Engineering, chapter 5, asked 2×
- [Internal/external drainage; water logging; Terai surface drainage](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Ainternal-external-drainage-water-logging-terai) — Irrigation and Drainage Engineering, chapter 9
- [Design discharge for surface drainage, bunded field](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Asurface-drainage-design-discharge-bunded) — Irrigation and Drainage Engineering, chapter 9
- [Water logging remedies and surface drainage in Terai](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Awater-logging-causes-surface-drainage-terai) — Irrigation and Drainage Engineering, chapter 9
- [Design criteria of surface drainage](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Asurface-drainage-design-criteria) — Irrigation and Drainage Engineering, chapter 9
- [Surface drainage design, 40 ha Terai field](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Asurface-drainage-40ha-terai) — Irrigation and Drainage Engineering, chapter 9

## Related in other subjects

- [Surface drainage system](https://www.bctengineer.com/question.md?key=semester_6%2Ftransportation_engineering_i%3Asurface-drainage-system) — Transportation Engineering I, chapter 4
- [Components of highway drainage system](https://www.bctengineer.com/question.md?key=semester_6%2Ftransportation_engineering_i%3Adrainage-components) — Transportation Engineering I, chapter 4
- [Job layout and site planning factors](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Ajob-layout-site-planning-factors) — Construction Management, chapter 6, asked 2×
- [RoR layout: pressure tunnel and free surface](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Aror-layout-pressure-tunnel-free-flow) — Hydropower Engineering, chapter 2