# Vertical drop design, Q 7.5 m3/s

Irrigation and Drainage Engineering · Chapter 7: Regulating Structures

- Asked in: 2079 Jestha, 8 marks
- Video: [Design of Sarda Fall water Resources engineering](https://www.youtube.com/watch?v=Rncmf2oZ16o) — Study with Civil buddy
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_6/irrigation_and_drainage_engineering/vertical-drop-q75
- Whole chapter: https://www.bctengineer.com/md/semester_6/irrigation_and_drainage_engineering/chapter-7

## Question

Design crest, length and thickness of impervious floor of a vertical drop structure for the following data: Discharge = 7.5 m³/sec; Side slope of the channel = 1:1; FSL U/S = 156.10 m; Bed level U/S = 155.15 m; Bed slope [level] D/S = 154.45 m; Bed width U/S and D/S = 1.5 m; Top width of crest = 0.55 m (for initial assumption); Cd = 0.415; Sp. Gr. of masonry drop structure = 2.25; Bligh's Coefficient = 6.0.

## Short answer

The crest is set at the upstream bed level of 155.15 m with a length of 2.27 m. The total impervious floor length is 11.13 m and its thickness near the drop wall is 0.51 m, tapering to 0.30 m at the end.

## Answer

#### Given data and assumptions
- $Q = 7.5$ m³/s, bed width $B = 1.5$ m, side slope 1:1, u/s FSL $= 156.10$ m, u/s bed $= 155.15$ m, d/s bed $= 154.45$ m.
- Full supply depth u/s $D_u = 0.950$ m, d/s $D_d = 0.950$ m (d/s FSL $= 155.400$ m); drop in water level $H_L = 0.700$ m.
- Bligh's coefficient $C = 6$; specific gravity of masonry/concrete $G = 2.25$.

#### 1. Upstream flow conditions
$$
\begin{aligned} A &= (B + mD_u)D_u = (1.5 + 1\times0.950)(0.950) = 2.327\ \text{m}^2 \\ v &= Q/A = 3.222\ \text{m/s}, \qquad h_a = \frac{v^2}{2g} = 0.529\ \text{m} \end{aligned}
$$

#### 2. Crest length, head and crest level
Discharge over a rectangular crest: $Q = C_d\sqrt{2g}\,L\,H^{3/2}$ with $C_d\sqrt{2g} = 1.838$, where $H$ is the total head over the crest (including $h_a$).
With $L = B = 1.5$ m the head needed would put the crest below the u/s bed. The crest is therefore fixed at the u/s bed level and its length increased (splayed wing walls):
$$
\begin{aligned} H &= (FSL_u + h_a) - \text{crest} = 156.629 - 155.150 = 1.479\ \text{m} \\ L &= \frac{Q}{1.838\,H^{3/2}} = 2.27\ \text{m} \end{aligned}
$$
Height of crest above d/s bed $d_c = 155.15 - 154.45 = 0.70$ m.

#### 3. Cistern (energy dissipation)
Discharge per metre length of crest $q = Q/L = 3.307$ m²/s. Energy available above the d/s bed $E_1 = FSL_u + h_a - \text{d/s bed} = 2.179$ m. For a cistern of depth $X$ below the d/s bed, the jump must form with the conjugate depth $y_2$ equal to the tail water over the cistern, $y_2 = D_d + X$. Solving with $E_1 + X = y_1 + q^2/(2gy_1^2)$ and $y_2 = \frac{y_1}{2}(\sqrt{1+8F_1^2} - 1)$:
- Required $X = 1.076$ m. Provide **$X = 1.10$ m** (cistern floor level $= 153.35$ m).
- With this $X$: $y_1 = 0.443$ m, $F_1 = 3.58$, $y_2 = 2.032$ m.

Length of cistern (hydraulic jump length) $L_c = 5(y_2 - y_1) = 5(2.032 - 0.443) = 7.94$ m.

#### 4. Crest (drop) wall
Top width (assumed) $T = 0.55$ m. Height of wall from cistern floor to crest $H_w = 155.15 - 153.35 = 1.80$ m. Bottom width for a gravity masonry wall:
$$
B_w = \frac{H_w + H}{\sqrt{G}} = \frac{1.80 + 1.48}{\sqrt{2.25}} = 2.19\ \text{m}
$$
Adopt bottom width $B_w = 2.19$ m (not less than the top width), with the d/s face vertical or slightly battered.

#### 5. Length of impervious floor (Bligh's theory)
Total creep length required $L = C\,H_L = 6\times0.700 = 4.20$ m. Cut-offs: u/s $d_1 = 0.6$ m, d/s $d_2 = 0.9$ m.
Downstream floor length (Bligh) with $q$ in m²/s:
$$
L_d = 2.21\,C\sqrt{H_L\sqrt{q/75}} = 2.21\times6\sqrt{0.700\sqrt{3.307/75}} = 5.08\ \text{m}
$$
The d/s floor (measured from the toe of the wall) must also contain the cistern, so adopt $L_d = 7.94$ m. Creep already provided by cut-offs and wall $= 2(d_1 + d_2) + B_w = 5.19$ m, so the u/s floor needed is
$$
b_u = L - [2(d_1+d_2) + B_w + L_d] = -8.93\ \text{m}
$$
Bligh's creep is already satisfied, so a nominal u/s floor of **1.0 m** is provided. Actual creep $= 14.13$ m $\ge 4.20$ m, safe.
Total floor length $= b_u + B_w + L_d = 11.13$ m.

#### 6. Thickness of the floor
Pressure head at the toe of the wall: creep to that point $= 4.39$ m, so residual head $h_1 = H_L\,\dfrac{L_{act} - 4.39}{L_{act}} = 0.483$ m. At the end of the cistern the creep is 12.33 m and $h_2 = 0.089$ m.
$$
t_1 = \frac{4}{3}\frac{h_1}{G-1} = \frac{4}{3}\times\frac{0.483}{1.25} = 0.51\ \text{m}
$$
Adopt floor thickness **0.51 m** under the cistern near the wall, tapering to 0.30 m at the end of the floor (minimum 0.30 m).

#### Summary
| Component | Value |
|---|---|
| Crest level | 155.15 m |
| Crest length / head $H$ | 2.27 m / 1.48 m |
| Crest wall top / bottom width | 0.55 m / 2.19 m |
| Cistern depth / length | 1.10 m / 7.94 m |
| Floor: u/s 1.0 m, d/s 7.94 m, cut-offs 0.6 / 0.9 m | total creep 14.13 m |
| Floor thickness | 0.51 m (taper to 0.30 m) |

**Answer:** crest level 155.15 m, crest length 2.27 m, crest wall 0.55 m top and 2.19 m bottom width, cistern depth 1.10 m and length 7.94 m, floor length 11.13 m, floor thickness 0.51 m.

Sketch:
```text
 FSL u/s ~~~~~~~~~~~|
                    |  crest
 u/s bed ___________|__          FSL d/s ~~~~
        |  u/s floor |  \  drop        ~~~~~
     d1 |            |   \_____cistern________ d/s bed
        |            |<-Lc->|   d/s floor   | d2
                     |____ floor thickness __|
```

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Why is the crest fixed at the u/s bed level and the crest length increased?
   A. Because the cistern is too deep
   B. Because Bligh's C is high
   C. Because the floor is thick
   D. With L = B = 1.5 m the required head would put the crest below the u/s bed, so crest is kept at bed level and splayed to 2.27 m
   Answer: D. A 1.5 m crest would need a head putting the crest below the bed, so crest level 155.15 m is adopted and L = Q/(1.838 H^1.5) = 2.27 m. (Key point: Crest fixed at u/s bed)

2. How is the cistern depth X decided?
   A. So the conjugate depth y2 equals the tail water depth over the cistern, D_d + X (required X = 1.076 m, 1.10 m provided)
   B. As half the drop
   C. As equal to the crest length
   D. As 0.30 m minimum
   Answer: A. The jump forms in the cistern when y2 = D_d + X, solved with the energy equation, giving X = 1.10 m. (Key point: Cistern design)

3. How does Bligh's creep check turn out?
   A. Required creep 4.20 m is not met
   B. Required 6 x 0.70 = 4.20 m is exceeded easily; actual creep 14.13 m is safe, so a nominal 1.0 m u/s floor is provided
   C. Required creep is 14.13 m
   D. Creep is not checked
   Answer: B. L = C H_L = 4.2 m; cut-offs, wall and the d/s floor needed for the cistern already exceed this. (Key point: Creep length)

4. Why is the d/s floor length adopted as 7.94 m rather than the Bligh value 5.08 m?
   A. Because Bligh's formula gives 7.94 m
   B. Because the u/s floor is negative
   C. The d/s floor must contain the cistern (hydraulic jump length)
   D. To thicken the floor
   Answer: C. The floor from the wall toe has to contain the jump length of 7.94 m, which exceeds the Bligh requirement. (Key point: Floor length driver)

5. How is floor thickness near the wall found?
   A. t = h1/(G + 1)
   B. t = 4/3 x h1/(G - 1) = 0.51 m, using residual uplift head at that point
   C. t = H_L
   D. t = 0.30 m everywhere
   Answer: B. Thickness resists uplift: t = (4/3) h/(G - 1) with h1 = 0.483 m and G = 2.25, giving 0.51 m, tapering to a minimum of 0.30 m. (Key point: Floor thickness)

## Close variants set in other exams

- [Vertical drop design, Q 5.2 m3/s](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Avertical-drop-q52) — Irrigation and Drainage Engineering, chapter 7, asked 4×
- [Vertical drop design, Q 2.1 m3/s](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Avertical-drop-q21) — Irrigation and Drainage Engineering, chapter 7, asked 4×
- [Vertical drop design, Q 1.8 m3/s (bed 205.05)](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Avertical-drop-q18-bed20505) — Irrigation and Drainage Engineering, chapter 7, asked 4×

## Related in Irrigation and Drainage Engineering

- [Vertical drop crest level and width, Q 30](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Avertical-drop-crest-q30-fsl315) — Irrigation and Drainage Engineering, chapter 7
- [Crest width, cistern length of vertical drop, Q 1.55](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Avertical-drop-q155-drop075) — Irrigation and Drainage Engineering, chapter 7, asked 2×
- [Vertical drop design, Q 5.1 m3/s](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Avertical-drop-q51) — Irrigation and Drainage Engineering, chapter 7
- [Vertical drop design, Q 1.8 m3/s (drop 0.75 m)](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Avertical-drop-q18-drop075) — Irrigation and Drainage Engineering, chapter 7, asked 2×
- [Vertical drop crest and cistern, Q 4.5](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Avertical-drop-q45-fsl1065) — Irrigation and Drainage Engineering, chapter 7
- [Minimum impervious floor length, 10000 m3/s](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Abarrage-min-floor-length-q10000) — Irrigation and Drainage Engineering, chapter 5, asked 2×

## Related in other subjects

- [Channel earthwork with drop at 0+090](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Achannel-e-drop-0-090) — Estimating and Costing, chapter 6
- [Vertical curve at PVI 243.154 m](https://www.bctengineer.com/question.md?key=semester_6%2Ftransportation_engineering_i%3An-64s-vc-243) — Transportation Engineering I, chapter 3
- [Design of side intake with trashrack](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Aintake-side-design-3315masl) — Hydropower Engineering, chapter 5
- [Economical trapezoidal channel side length](https://www.bctengineer.com/question.md?key=semester_6%2Fhydro_power%3Aeconomical-trapezoidal-side-length) — Hydro Power, chapter 1