# Oxidation pond and area procedure

Sanitary Engineering · Chapter 7: Wastewater Treatment

- Asked in: 2077 Chaitra, 4+4 marks
- Video: [Oxidation Pond | Waste Water Engineering](https://www.youtube.com/watch?v=HqJ4GCWqJjI) — APSEd
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_6/sanitary_engineering/oxidation-pond-area-procedure
- Whole chapter: https://www.bctengineer.com/md/semester_6/sanitary_engineering/chapter-7

## Question

Briefly illustrate about oxidation pond. With suitable example, state its procedure to calculate its area.

## Short answer

Find sewage flow Q (population × per capita) and BOD load (kg/day = Q × BOD / 1000). Divide load by permissible surface loading (200–400 kg/ha/day) to get area; volume = area × depth, detention = V/Q. Example: 5000 people, 100 lpcd, 250 mg/l BOD, 300 kg/ha/day gives 0.42 ha (about 46 m × 91 m) and 10 days.

## Answer

#### Oxidation pond
An oxidation pond is a shallow (1-1.5 m) earthen pond in which sewage is stabilised by the symbiotic action of bacteria and algae in sunlight. Bacteria oxidise the organics using oxygen produced by algae; algae use the CO₂ and nutrients released by the bacteria. Settled solids are digested anaerobically at the bottom. It needs little energy and little skill but a large area, and removes 70-90% of BOD.

```text
   sunlight -> algae --O2--> bacteria
                   <--CO2,NH3,PO4--
   ~~~~~~~~~ water surface ~~~~~~~~~
   anaerobic sludge layer at bottom
```

#### Procedure to calculate the area
1. Find the sewage flow $Q$ (m³/day) = population × per capita sewage.
2. Find the BOD load: $\text{Load}=Q\times BOD\times10^{-3}$ kg/day.
3. Adopt a permissible surface organic loading $\lambda_s$ (kg BOD/ha/day), 200-400 depending on temperature.
4. Area $A=\dfrac{\text{Load}}{\lambda_s}$ (ha).
5. Adopt depth $d$ (1-1.5 m); volume $V=A\,d$; detention time $t=V/Q$ (check 5-30 days).
6. Fix the length-to-width ratio (2:1 to 3:1) and provide embankment, free board and inlet/outlet.

#### Example
Population = 5000, sewage 100 lpcd, BOD = 250 mg/l, loading 300 kg/ha/day, depth 1.2 m (assumed data).

$$
\begin{aligned}
Q &= 5000\times100/1000 = 500\ \text{m}^3/\text{day}\\
\text{Load} &= 500\times250/1000 = 125\ \text{kg/day}\\
A &= \frac{125}{300}=0.4167\ \text{ha}=4167\ \text{m}^2\\
V &= 4167\times1.2 = 5000\ \text{m}^3,\quad t=\frac{5000}{500}=10\ \text{days}
\end{aligned}
$$

For L : W = 2 : 1, $W=\sqrt{4167/2}=45.6$ m and $L=91.3$ m. **Answer: area about 0.42 ha (about 46 m x 91 m), 10 days detention.**

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. In the procedure, the pond area is found from
   A. BOD load divided by the permissible surface organic loading
   B. flow divided by depth only
   C. population divided by 100
   D. detention time multiplied by the flow
   Answer: A. A = Load / lambda_s, with load = Q x BOD x 10^-3 kg/day. (Key point: Basis of area)

2. In the example (5000 persons, 100 lpcd, BOD 250 mg/l, loading 300 kg/ha/day), what is the BOD load?
   A. 500 kg/day
   B. 250 kg/day
   C. 125 kg/day
   D. 62.5 kg/day
   Answer: C. Q = 500 m3/day and load = 500 x 250 / 1000 = 125 kg/day. (Key point: Example calculation)

3. After finding the area, how is detention time obtained and checked?
   A. t = A/d and compared with 1-2 days
   B. t = V/Q, with V = A x d, and checked to lie in 5-30 days
   C. t = Q/V and compared with 100 days
   D. t = load/area and compared with 300
   Answer: B. With V = 4167 x 1.2 = 5000 m3 and Q = 500 m3/day, t = 10 days, within 5-30 days. (Key point: Detention check)

4. What length-to-width ratio is adopted for the pond?
   A. 1 : 1 exactly
   B. 10 : 1 to 20 : 1
   C. 2 : 1 to 3 : 1
   D. 1 : 5
   Answer: C. A rectangular pond of 2:1 to 3:1 is used, giving about 46 m x 91 m in the example. (Key point: Pond shape)

## Related in Sanitary Engineering

- [Oxidation pond for Terai town, 12,000](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Aoxidation-pond-terai-12000) — Sanitary Engineering, chapter 7
- [Oxidation pond theory; colony of 15000](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Aoxidation-pond-15000) — Sanitary Engineering, chapter 7
- [Oxidation pond: theory and commissioning](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Aoxidation-pond-mechanism-commissioning) — Sanitary Engineering, chapter 7, asked 3×
- [Sedimentation tank and oxidation pond design](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Ased-tank-and-oxidation-pond-10000) — Sanitary Engineering, chapter 7
- [Oxidation pond; flushing device role](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Aoxidation-pond-mechanism-flushing) — Sanitary Engineering, chapter 7
- [Oxidation pond theory; 2500 persons](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Aoxidation-pond-2500-persons) — Sanitary Engineering, chapter 7

## Related in other subjects

- [DAD curve procedure and isohyetal area data](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Adad-curve-procedure-isohyetal) — Engineering Hydrology, chapter 2
- [Principle and procedure of slope-area method](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Aslope-area-principle-procedure) — Engineering Hydrology, chapter 4
- [Khosla: residual pressures and HGL, pond 260 m](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Akhosla-weir-profile-pond260) — Irrigation and Drainage Engineering, chapter 5
- [Length of PQ across a pond](https://www.bctengineer.com/question.md?key=semester_3%2Fsurveying_i%3Aobstacle-pond-chain-line) — Surveying I, chapter 3