title: "Circular sedimentation tank, population 35675"
subject: "Sanitary Engineering"
chapter: 7
key: "semester_6/sanitary_engineering:sed-tank-35675"
source: https://www.bctengineer.com/q/semester_6/sanitary_engineering/sed-tank-35675
site: BCT Engineering
---

# Circular sedimentation tank, population 35675

Sanitary Engineering · Chapter 7: Wastewater Treatment

- Asked in: 2068 Magh (old course), 10 marks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_6/sanitary_engineering/sed-tank-35675
- Whole chapter: https://www.bctengineer.com/md/semester_6/sanitary_engineering/chapter-7

## Question

Design a circular sedimentation tank for a locality having population of 35675. The average water demand is 135 lpcd and 80% of the water consumed converts to sewage. Assume that maximum demand is 2.7 times the average demand. Check surface loading also.

## Short answer

One circular tank of 19.5 m diameter, 3.0 m side water depth (total 4.0 m), detention 2.0 h, surface loading 34.8 m³/m²/day.

## Answer

**Assumptions:** sewage $=0.8\times 135 = 108$ lpcd, so the average flow is $35675\times 108/1000 = 3852.9$ m³/day; the design flow is the maximum, $2.7\times$ average. Detention 2 h at maximum flow, depth 3 m.

#### Step 1: Design flow

$$
Q = 35675\times 135\times 0.8\times 2.7/1000 = 10402.8\ \text{m}^3/\text{day}
$$

#### Step 2: Capacity

Adopt detention period $t = 2.0$ h and side water depth $H = 3.0$ m (typical for plain sedimentation: 2-3 h, 2.5-4 m).

$$
V = Q\,t = \frac{10402.8}{24}\times 2.0 = 866.9\ \text{m}^3,\qquad A = \frac{V}{H} = \frac{866.9}{3.0} = 289.0\ \text{m}^2
$$

#### Step 3: Diameter

Provide one circular tank, so $A_1=A$.

$$
D = \sqrt{\frac{4A_1}{\pi}} = \sqrt{\frac{4\times 289.0}{\pi}} = 19.18\ \text{m}\ \Rightarrow\ \text{adopt } D = 19.5\ \text{m}
$$

Adopt a total depth of $H + 0.5\ (\text{free board}) + 0.5\ (\text{sludge zone}) = 4.0$ m, with a central inlet well and a peripheral weir.

#### Step 4: Checks

$$
\begin{aligned}
\text{Surface loading} &= \frac{Q/N}{\pi D^2/4} = \frac{10402.8}{298.6} = 34.8\ \text{m}^3/\text{m}^2\text{/day}\ (\text{usual 25-40 for primary tanks})\\
\text{Weir loading} &= \frac{Q/N}{\pi D} = \frac{10402.8}{\pi\times 19.5} = 169.8\ \text{m}^3/\text{m/day}\ (\text{should be below about 300})\\
\text{Actual detention} &= \frac{(\pi D^2/4)H}{Q/N}\times 24 = 2.07\ \text{h}
\end{aligned}
$$
The surface loading lies within the usual range for primary settling (25-40 m³/m²/day), so the tank is satisfactory. The inlet well, scum board and sludge scraper are provided as shown.

```text
   Section (circular, radial flow)
      inlet well        weir/launder
   ->  |__|~~~~~~~~~~~~~~~~~~~~~|_
       |  \                  /  | H = 3.0 m
       |   \______    ______/   | + sludge zone
       +----------\__/----------+
                  sludge hopper -> sludge pipe
        <---------- D = 19.5 m ---------->
```
**Answer: 1 circular sedimentation tank of diameter 19.5 m, side water depth 3.0 m (total depth about 4.0 m), detention 2.0 h, surface loading 34.8 m³/m²/day.**

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. What is the design flow for 35675 people?
   A. 35675 x 135 x 0.8 / 1000 = 3853 m^3/day
   B. 35675 x 135 x 2.7 / 1000
   C. 35675 x 135 / 0.8 x 2.7
   D. 35675 x 135 x 0.8 x 2.7 / 1000 = 10402.8 m^3/day
   Answer: D. The tank is designed for the maximum flow, 2.7 times the average sewage flow. (Key point: Design flow)

2. How is the tank area found?
   A. A = V / H with V = Q t = 866.9 m^3, so A = 289 m^2
   B. A = Q / H
   C. A = V x H
   D. A = Q x t / 24 x 3
   Answer: A. Volume divided by side depth. (Key point: Area)

3. What is the surface loading and is it acceptable?
   A. 10402.8 m^3/m^2/day, too high
   B. 34.8 m^3/m^2/day, within 25-40 for primary tanks
   C. 2.07 m^3/m^2/day, too low
   D. 169.8 m^3/m^2/day, acceptable
   Answer: B. 10402.8 / 298.6 = 34.8, within the usual range. (Key point: Surface loading check)

4. Why is actual detention (2.07 h) slightly different from 2 h?
   A. The depth was changed
   B. The flow was reduced
   C. The diameter was rounded up to 19.5 m, giving a larger volume
   D. Free board was added
   Answer: C. A larger adopted D gives a larger actual volume for the same flow. (Key point: Actual detention)

## Related in Sanitary Engineering

- [Circular sedimentation tank, population 80000](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Ased-tank-industrial-80000) — Sanitary Engineering, chapter 7, asked 2×
- [Circular sedimentation tank, population 5500](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Ased-tank-industrial-5500) — Sanitary Engineering, chapter 7, asked 2×
- [Circular sedimentation tank for 58 MLD](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Ased-tank-58mld-circular) — Sanitary Engineering, chapter 7
- [Sedimentation tank and oxidation pond design](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Ased-tank-and-oxidation-pond-10000) — Sanitary Engineering, chapter 7
- [Septic tank and soak pits, hotel of 80](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Aseptic-tank-hotel-80-users) — Sanitary Engineering, chapter 9
- [Continuous flow sedimentation tank particle size](https://www.bctengineer.com/question.md?key=semester_6%2Fsanitary_engineering%3Ased-tank-continuous-4m-60m) — Sanitary Engineering, chapter 7

## Related in other subjects

- [Design pipes AB and BC, 75 lpcd, tank 6 m high](https://www.bctengineer.com/question.md?key=semester_5%2Fwater_supply_engineering%3Apd-b81) — Water Supply Engineering, chapter 7
- [Rectangular sedimentation tank, 0.2 mm/s, 25000 population](https://www.bctengineer.com/question.md?key=semester_5%2Fwater_supply_engineering%3Ased-bk79) — Water Supply Engineering, chapter 6, asked 2×
- [Rectangular sedimentation tank, 20000 population, 0.4 mm/s](https://www.bctengineer.com/question.md?key=semester_5%2Fwater_supply_engineering%3Ased-s73) — Water Supply Engineering, chapter 6
- [Rectangular sedimentation tank, 9 million L peak demand](https://www.bctengineer.com/question.md?key=semester_5%2Fwater_supply_engineering%3Ased-c75) — Water Supply Engineering, chapter 6