# Fuse selection for transformer, capacitor, lighting

Switchgear and Protection · Chapter 3: Fuses

- Asked in: 2076 Bhadra, 6 marks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_6/switchgear_and_protection/fuse-selection-transformer-capacitor-lighting
- Whole chapter: https://www.bctengineer.com/md/semester_6/switchgear_and_protection/chapter-3

## Question

What are the considerations in selecting a fuse for (i) Transformer protection (ii) capacitor protection (iii) lighting loads?

## Short answer

Transformer: HV fuse 1.5–2 × I_FL must withstand magnetising inrush (10–12× for 0.1 s), coordinate with LV protection, and have adequate breaking capacity. Capacitor: fuse rating 1.43–1.65 × rated current must endure switching inrush and discharge, with individual unit fuses. Lighting: 1.1–1.25 × I_FL, withstand cold‑filament/driver inrush, low fusing factor, discrimination.

## Answer

#### (i) Transformer protection
1. **Full-load current:** fuse rating above full-load with allowance for permissible overload; HV side typically **1.5–2 × I_FL**, LV side **1.1–1.25 × I_FL** (next standard rating).
2. **Magnetising inrush:** the fuse must not melt on inrush of about **10–12 × I_FL for 0.1 s** (and 25 × I_FL for 0.01 s).
3. **Through-fault clearing:** the HV fuse must clear a short circuit on the LV terminals (I_FL/Z_pu) before the transformer is damaged (within thermal withstand time, e.g. 2 s).
4. **Discrimination:** HV fuse must coordinate with LV fuses or LV breaker (curves referred to the same voltage must not cross).
5. **Breaking capacity** ≥ system fault level; HRC or expulsion (drop-out) fuses on 11 kV.
6. Use striker-pin fuses with a switch to avoid single phasing.

#### (ii) Capacitor protection
1. **Overcurrent due to harmonics and over-voltage:** capacitor current may be up to 1.3 × rated (IEC 60871/60831) plus tolerance, so fuse rating is about **1.43–1.65 × rated capacitor current** (commonly 1.5–1.8 ×).
2. **Switching inrush:** high-frequency inrush at energising (up to 100 × I_rated for back-to-back switching) must not melt the fuse.
3. **Discharge energy:** the fuse must withstand discharge of parallel units into a faulted unit; individual-unit fuses must clear a failed unit before case rupture (fuse curve below tank-rupture curve).
4. Use **individual (internal or external) fuses** for each unit in large banks and a group fuse/breaker for the whole bank.
5. Voltage rating to suit system, considering neutral shift in ungrounded star banks.

#### (iii) Lighting loads
1. Rating just above the normal full-load current of the circuit (e.g. **1.1–1.25 × I_FL**), and not greater than the current-carrying capacity of the wiring.
2. **Switch-on surges:** incandescent lamps (cold filament ≈ 10–15 × for a few ms), discharge lamps and LED drivers (capacitive inrush) – choose a fuse that withstands these surges.
3. Lighting circuits have little overload, so a fuse with low fusing factor can be used; fast HRC or cartridge fuses/MCBs are suitable.
4. **Discrimination** with the distribution-board main fuse (ratio ≥ 1.6:1).
5. Breaking capacity ≥ prospective fault at the board; fuse must clear an earth fault quickly enough for shock protection (fault loop impedance check).
6. Power factor of discharge lamps and harmonic currents in the neutral should be considered.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Which transformer consideration prevents nuisance fuse melting on energising?
   A. Fuse must withstand 10-12 x I_FL magnetising inrush for 0.1 s
   B. Fuse must have zero breaking capacity
   C. Fuse rating must be below I_FL
   D. Fuse must melt at 2 x I_FL immediately
   Answer: A. Inrush of about 10-12 x I_FL lasting 0.1 s must not melt the fuse. (Key point: Transformer inrush)

2. Why is a capacitor fuse rated about 1.43-1.65 x rated capacitor current?
   A. Capacitors have large inrush only
   B. Harmonics and over-voltage allow capacitor current up to 1.3 x rated, plus tolerance
   C. Because capacitors do not carry current normally
   D. To make the fuse blow on harmonics
   Answer: B. Allowed overcurrent of 1.3 x rated plus capacitance tolerance sets the margin. (Key point: Capacitor fuse rating)

3. Why are individual fuses used on each unit in large capacitor banks?
   A. To clear a failed unit before its case ruptures
   B. To increase bank voltage
   C. To avoid switching inrush
   D. To reduce harmonic currents
   Answer: A. The fuse curve must be below the tank-rupture curve so the faulty unit is isolated safely. (Key point: Individual capacitor fuses)

4. For lighting circuits, the fuse must also consider:
   A. Magnetising inrush of 25 x I_FL
   B. Switch-on surges of lamps and drivers
   C. Neutral shift in star banks
   D. Tank rupture curves
   Answer: B. Cold filaments, discharge lamps and LED drivers draw short surges that must not blow the fuse. (Key point: Lighting loads)

## Related in Switchgear and Protection

- [Fuse selection for 250 kVA transformer](https://www.bctengineer.com/question.md?key=semester_6%2Fswitchgear_and_protection%3Atransformer-fuse-selection-250kva) — Switchgear and Protection, chapter 3
- [Selecting HRC fuse rating for motor](https://www.bctengineer.com/question.md?key=semester_6%2Fswitchgear_and_protection%3Ahrc-fuse-motor-rating) — Switchgear and Protection, chapter 3
- [Construction of capacitor voltage transformer](https://www.bctengineer.com/question.md?key=semester_6%2Fswitchgear_and_protection%3Acapacitor-voltage-transformer-construction) — Switchgear and Protection, chapter 2
- [Differential protection of power transformer](https://www.bctengineer.com/question.md?key=semester_6%2Fswitchgear_and_protection%3Atransformer-differential-protection) — Switchgear and Protection, chapter 7
- [Fuse vs MCB; HRC fuse time terms](https://www.bctengineer.com/question.md?key=semester_6%2Fswitchgear_and_protection%3Afuse-vs-mcb-hrc-terms) — Switchgear and Protection, chapter 3
- [Fuse terms with cut-off characteristic sketch](https://www.bctengineer.com/question.md?key=semester_6%2Fswitchgear_and_protection%3Afuse-terms-cutoff-sketch) — Switchgear and Protection, chapter 3

## Related in other subjects

- [Transformer protection, selection and vector group](https://www.bctengineer.com/question.md?key=semester_8%2Fpower_plant_design%3Atransformer-protection-vector-group) — Power Plant Design, chapter 4
- [Selecting distribution transformer size and location](https://www.bctengineer.com/question.md?key=semester_8%2Ftransmission_and_distribution_system_design%3Atransformer-size-and-location) — Transmission and Distribution System Design, chapter 7, asked 2×
- [Electrical considerations in conductor selection](https://www.bctengineer.com/question.md?key=semester_8%2Ftransmission_and_distribution_system_design%3Aconductor-electrical-considerations) — Transmission and Distribution System Design, chapter 4, asked 3×
- [Tunnel lighting factors; river bank protection methods](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Atunnel-lighting-factors-river-bank-methods) — Transportation Engineering II, chapter 5