title: "Bill of quantities for RCC T-beam bridge"
subject: "Estimating and Costing"
chapter: 2
key: "semester_7/estimating_and_costing:boq-rcc-t-beam-decking"
source: https://www.bctengineer.com/q/semester_7/estimating_and_costing/boq-rcc-t-beam-decking
site: BCT Engineering
---

# Bill of quantities for RCC T-beam bridge

Estimating and Costing · Chapter 2: Method of Estimating

- Asked in: 2073 Shrawan
- Video: [ESTIMATION OF RCC T BEAM DECKING](https://www.youtube.com/watch?v=HmdpoBWqEWo) — ADV. LEARNING
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/estimating_and_costing/boq-rcc-t-beam-decking
- Whole chapter: https://www.bctengineer.com/md/semester_7/estimating_and_costing/chapter-2

## Question

Prepare a bill of quantities from the following data for the construction of an RCC T-beam decking bridge.

| Quantity of work | Detail of work | Rate per unit of work |
|---|---|---|
| 108 m³ | PCC (1:1:2) for RCC works | Rs 13,200.00 |
| 3240 m² | Formwork for RCC works | Rs 750.00 |
| 21600 kg | Steel reinforcement for RCC works | Rs 115.00 |
| 18 m³ | PCC (1:2:4) wearing coat | Rs 12090.00 |

## Short answer

Bill of quantities lists each item with unit, quantity, rate and amount; amount equals quantity times rate. The T-beam decking works total Rs 6,557,220.00, comprising PCC Rs 1,425,600, formwork Rs 2,430,000, reinforcement Rs 2,484,000 and wearing coat Rs 217,620.

## Answer

A bill of quantities lists each item with its description, unit, quantity, rate and amount (amount = quantity x rate).

| SN | Description of work | Unit | Quantity | Rate (Rs) | Amount (Rs) |
|---|---|---|---|---|---|
| 1 | PCC (1:1:2) for RCC works | m³ | 108 | 13,200.00 | 1,425,600.00 |
| 2 | Formwork for RCC works | m² | 3,240 | 750.00 | 2,430,000.00 |
| 3 | Steel reinforcement for RCC works | kg | 21,600 | 115.00 | 2,484,000.00 |
| 4 | PCC (1:2:4) wearing coat | m³ | 18 | 12,090.00 | 217,620.00 |
| | **Total** | | | | **6,557,220.00** |

Working of the amounts:
- PCC for RCC: 108 x 13,200 = 1,425,600.00
- Formwork: 3,240 x 750 = 2,430,000.00
- Reinforcement: 21,600 x 115 = 2,484,000.00
- Wearing coat: 18 x 12,090 = 217,620.00

**Answer: Total cost of the T-beam decking works = Rs 6,557,220.00.** Contingency and VAT are added to this total if required.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. What does each line of a bill of quantities in this answer list?
   A. Description, unit, quantity, rate and amount
   B. Only the description
   C. Only the drawing number
   D. Only the rate and VAT
   Answer: A. Amount is quantity x rate for each item. (Key point: BOQ contents)

2. What is the amount for formwork of 3,240 m2 at Rs 750?
   A. Rs 243,000
   B. Rs 2,430,000
   C. Rs 3,990
   D. Rs 24,300,000
   Answer: B. 3,240 x 750 = 2,430,000. (Key point: Formwork amount)

3. What is the total cost of the T-beam decking works?
   A. Rs 6,339,600
   B. Rs 4,127,220
   C. Rs 6,557,220
   D. Rs 6,775,200
   Answer: C. 1,425,600 + 2,430,000 + 2,484,000 + 217,620 = 6,557,220. (Key point: Total)

## Related in Estimating and Costing

- [T-beam decking: PCC for RCC and steel](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3At-beam-pcc-rcc-reinforcement) — Estimating and Costing, chapter 6
- [T-beam decking: RCC and wearing coat](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3At-beam-decking-rcc-wearing) — Estimating and Costing, chapter 6, asked 2×
- [T-beam decking quantities (6 m clear span)](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3At-beam-decking-all-quantities) — Estimating and Costing, chapter 6
- [Prepare AOC, BOQ and summary of cost](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aaoc-boq-summary-numerical) — Estimating and Costing, chapter 2
- [Rate analysis: M20 (1:1½:3) RCC per 10 m³](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-m20-rcc-10m3) — Estimating and Costing, chapter 4
- [Rate analysis: PCC 1:3:6 per m³](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-pcc-1-3-6-per-m3) — Estimating and Costing, chapter 4

## Related in other subjects

- [Contractor asks supervisor to prepare running bill](https://www.bctengineer.com/question.md?key=semester_8%2Fengineering_professional_practice%3Acontractor-running-bill-bribe) — Engineering Professional Practice, chapter 7
- [EVA; 60 days, 25% work, Rs 12,00,000](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeva-numerical-60-days-25-percent) — Project Engineering, chapter 4
- [EVA and S-curve; Rs 30,00,000, 24 months](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeva-s-curve-24-months-c76) — Project Engineering, chapter 4
- [EVA application; 35 days, Rs 8,00,000 spent](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeva-applicable-monitoring-numerical-b82) — Project Engineering, chapter 4