title: "Canal earthwork, bed 3 m, free board 0.44 m"
subject: "Estimating and Costing"
chapter: 6
key: "semester_7/estimating_and_costing:channel-q-portion"
source: https://www.bctengineer.com/q/semester_7/estimating_and_costing/channel-q-portion
site: BCT Engineering
---

# Canal earthwork, bed 3 m, free board 0.44 m

Estimating and Costing · Chapter 6: Detailed Estimate

- Asked in: 2070 Chaitra, 10 marks
- Video: [Calculate the quantity of earthwork in irrigation canal | calculate the permanent width | Type #3](https://www.youtube.com/watch?v=WkcdXvl0XiQ) — SBK Concept
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/estimating_and_costing/channel-q-portion
- Whole chapter: https://www.bctengineer.com/md/semester_7/estimating_and_costing/chapter-6

## Question

Calculate the quantity of earth work for a portion of channel with the following data: Bed width = 3 m; Free Board = 0.44 m; Side slope for digging = 1:1; Side slope for banking = 1:1½ (V:H); Fully supply depth = 1 m; Top width of bank = 1.5 m.

| Chainage | 0 | 30 | 60 | 90 | 120 | 150 |
|---|---|---|---|---|---|---|
| RL of GL | 225.24 | 224.8 | 224.43 | 224.12 | 224.5 | 224.98 |
| Proposed level | 224.00 | 223.94 | 223.88 | 223.82 | 223.76 | 223.7 |

Also draw a typical X-section.

## Short answer

Total depth D = 1.44 m, cutting slope 1:1, banking 1.5:1. All stations are part cutting/part banking. Volumes: cutting = 431.93 m³, banking = 579.68 m³, total = 1,011.61 m³.

## Answer

#### Given data and assumptions
- Bed width $3$ m; FSD $1$ m; free board $0.44$ m, so $D = 1.44$ m; top width of each bank $1.5$ m.
- Side slope for digging $1:1$; for banking 1 V : 1½ H, i.e. $1.5:1$ (H:V) on the inner and outer faces of the banks.

#### Method
Total depth of canal section $D = \text{FSD} + \text{free board} = 1.00 + 0.44 = 1.44$ m. At each station the bed level is compared with the ground level; $e = $ GL − bed level.

- If $e \ge D$: full cutting, area $A_c = (b + s_c e)\,e$ (no banks needed).
- If $0 < e < D$: part cutting, part banking. Cutting area $A_c = (b + s_c e)e$; each bank stands $h_b = D - e$ above ground, so bank area (both banks) $A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2$ with $s_i, s_o$ the inner and outer bank slopes.
- If $e \le 0$: full banking, bed above ground. Bank top is $H = D - e$ above ground. Gross embankment $= (T + s_o H)H$ with $T = t_L + t_R + b + 2 s_i D$, and the canal space $(b + s_i D)D$ is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

#### Typical cross-section (part cutting, part banking)

```text
      1.5 m                                  1.5 m
     _______                                _______   top of bank = bed + 1.44 m
    /       \ 1.5:1                  1.5:1 /       \     (FSD 1.0 m + FB 0.44 m)
   /  bank   \                            /  bank   \ 1.5:1
__/___________\________ G.L. ____________/___________\__
               \  1:1               1:1 /
                \      cutting         /    e = GL - bed level
                 \____________________/
                        b = 3 m
```

#### Sectional areas
| Station | GL (m) | Bed RL (m) | $e$ (m) | Condition | Cutting area (m²) | Bank area (m²) |
|---|---:|---:|---:|---|---:|---:|
| 0 | 225.240 | 224.000 | 1.240 | part cutting, part banking | 5.258 | 0.720 |
| 30 | 224.800 | 223.940 | 0.860 | part cutting, part banking | 3.320 | 2.749 |
| 60 | 224.430 | 223.880 | 0.550 | part cutting, part banking | 1.953 | 5.046 |
| 90 | 224.120 | 223.820 | 0.300 | part cutting, part banking | 0.990 | 7.319 |
| 120 | 224.500 | 223.760 | 0.740 | part cutting, part banking | 2.768 | 3.570 |
| 150 | 224.980 | 223.700 | 1.280 | part cutting, part banking | 5.478 | 0.557 |

#### Volumes
| Between | Distance (m) | Cutting (m³) | Banking (m³) |
|---|---:|---:|---:|
| 0 – 30 | 30.0 | 128.66 | 52.04 |
| 30 – 60 | 30.0 | 79.08 | 116.93 |
| 60 – 90 | 30.0 | 44.14 | 185.48 |
| 90 – 120 | 30.0 | 56.36 | 163.33 |
| 120 – 150 | 30.0 | 123.69 | 61.90 |
| **Total** | | **431.93** | **579.68** |

**Answer: Earthwork in cutting = 431.93 m³; earthwork in banking = 579.68 m³; total = 1,011.61 m³.**

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Banking slope is given as 1 V : 1.5 H. How is it used in the formulas?
   A. As 1.5:1 (H:V), so s = 1.5
   B. As s = 1/1.5 = 0.67
   C. As s = 1
   D. As s = 2.5
   Answer: A. 1 vertical to 1.5 horizontal is the same as a horizontal slope of 1.5 per unit of height. (Key point: Slope notation)

2. For a part cutting, part banking section, the area of both banks is
   A. A_b = (b + s e)e
   B. A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with h_b = D - e
   C. A_b = (t_L + t_R)D
   D. A_b = b D + s D^2
   Answer: B. Each bank is a trapezoid of top width t and slope s on both faces, standing h_b = D - e above ground. (Key point: Bank area formula)

3. At 0, e = 1.24 m and D = 1.44 m. Bank area (t = 1.5 each, s = 1.5)?
   A. 1.24 m2
   B. 3.60 m2
   C. 0.72 m2
   D. 0.36 m2
   Answer: C. h_b = 0.20, area = 3.0 x 0.2 + 3.0 x 0.04 = 0.72 m2. (Key point: Bank at station 0)

4. How is the earthwork between two stations found?
   A. Larger of the two end areas x distance
   B. Sum of all areas x 30 m
   C. Area at the start x distance
   D. Average of the two end areas x chainage distance, separately for cutting and banking
   Answer: D. The mean area method is used for each of cutting and banking. (Key point: Volume between stations)

## Related in Estimating and Costing

- [Channel fully in banking, 0.5-1.5 km](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Acanal-fully-banking-i) — Estimating and Costing, chapter 6
- [Channel earthwork and land area, bed 4 m](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Achannel-land-acquisition-f) — Estimating and Costing, chapter 6, asked 2×
- [Channel earthwork, chainage 0+500 to 1+500](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Achannel-b-0500-1500) — Estimating and Costing, chapter 6
- [Irrigation channel earthwork, bed 5 m, 1 in 3000](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Airrigation-channel-j) — Estimating and Costing, chapter 6
- [Channel earthwork and land area, 50 cm fall](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Achannel-land-acquisition-h) — Estimating and Costing, chapter 6, asked 2×
- [Channel earthwork with drop at 0+090](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Achannel-e-drop-0-090) — Estimating and Costing, chapter 6

## Related in other subjects

- [Balancing depth with service bank and free board](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Abalancing-depth-bed8-service-bank) — Irrigation and Drainage Engineering, chapter 3
- [Balancing depth: bed width 20 m](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Abalancing-depth-bed20-cut15-fill2) — Irrigation and Drainage Engineering, chapter 3, asked 3×
- [Balancing depth: bed width 25 m](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Abalancing-depth-bed25) — Irrigation and Drainage Engineering, chapter 3, asked 3×
- [Stable depth and bed width: Q 5, d50 3 cm](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Astable-depth-bed-width-q5-d50) — Irrigation and Drainage Engineering, chapter 4