# Departmental norms for rate analysis in Nepal

Estimating and Costing · Chapter 4: Analysis of Rates

- Asked in: 2081 Bhadra, 4 marks
- Video: [How to do rate analysis in Nepal based on norm and district rate?](https://www.youtube.com/watch?v=CewrV3DCK6o) — Abi engineering solutions
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/estimating_and_costing/departmental-norms-nepal
- Whole chapter: https://www.bctengineer.com/md/semester_7/estimating_and_costing/chapter-4

## Question

What are the departmental norms used for analysis of rate in Nepal for building works, road works and sanitary works? Also list the data provided in such norms.

## Short answer

For building/sanitary works DUDBC norms are used; for roads DoR norms; for water supply/sewerage DWSSM norms; for rural roads DoLI norms. The norms give item unit, materials with wastage, skilled/unskilled labour in man-days, equipment hours, conversion factors, transport norms, and 15% overhead and profit allowance.

## Answer

#### Departmental norms used in Nepal
| Type of work | Norms |
|---|---|
| Building works and sanitary works | "Norms for Rate Analysis" of the **Department of Urban Development and Building Construction (DUDBC)**, also used by municipalities and local levels |
| Road and bridge works | "Norms for Rate Analysis of Road and Bridge Works" of the **Department of Roads (DoR)**, used with the DoR Standard Specifications for Road and Bridge Works |
| Water supply and sanitary/sewerage works | Norms of the **Department of Water Supply and Sewerage Management (DWSSM)** |
| Rural roads, irrigation and local infrastructure | Norms of the **Department of Local Infrastructure (DoLI)**, and of the Department of Irrigation for canals |

Each norm is used with the **District Rate** of the district.

#### Data given in the norms
- Item of work with its **unit** and description (mix, thickness and specification).
- **Materials** per unit, with the wastage allowance.
- **Skilled and unskilled labour** in man-days per unit.
- **Equipment** and tools, with hours of use and output.
- Conversion factors and the standard output per day (task or out-turn).
- Transport norms (by road, mule or porter) and the percentage allowance for contractor's overhead and profit (15%).

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Which department's norms are used for building and sanitary works?
   A. DoR
   B. DoLI
   C. Department of Irrigation
   D. DUDBC
   Answer: D. Norms for Rate Analysis by DUDBC. (Key point: Building norms)

2. Which norms are used for road and bridge works?
   A. Department of Roads
   B. DUDBC
   C. DWSSM
   D. DoLI
   Answer: A. DoR standard specifications. (Key point: Road norms)

3. Which data are given in the norms?
   A. Only prices
   B. Materials with wastage, skilled/unskilled man-days, equipment and output
   C. Only drawings
   D. Only taxes
   Answer: B. Norms list resources per unit. (Key point: Norm data)

4. Each norm is used with what?
   A. World Bank rate
   B. Previous contract
   C. The District Rate of the district
   D. Foreign tariff
   Answer: C. Norms give quantity; District Rate gives price. (Key point: District Rate)

## Related in Estimating and Costing

- [Data required for rate analysis (building)](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-analysis-data-required) — Estimating and Costing, chapter 4
- [How Nepal Government takes norms and rates](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Anepal-govt-norms-rates) — Estimating and Costing, chapter 4
- [Rate analysis: one metric ton reinforcement](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-reinforcement-per-mt) — Estimating and Costing, chapter 4
- [Rate analysis: WC commode, low level cistern](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-wc-low-level-cistern) — Estimating and Costing, chapter 4, asked 5×
- [Rate analysis: meaning, purposes, factors](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-analysis-purposes-factors) — Estimating and Costing, chapter 4, asked 4×
- [Rate analysis: sal wood door/window frame per m³](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-sal-wood-frame) — Estimating and Costing, chapter 4, asked 3×

## Related in other subjects

- [Advantages of road transport in Nepal](https://www.bctengineer.com/question.md?key=semester_6%2Ftransportation_engineering_i%3Aroad-transport-advantages) — Transportation Engineering I, chapter 1, asked 8×
- [Report on road construction in remote Nepal](https://www.bctengineer.com/question.md?key=semester_5%2Fcommunication_english%3Areport-road-construction-remote-nepal) — Communication English, chapter 9
- [I/O functions used with data files](https://www.bctengineer.com/question.md?key=semester_1%2Fcomputer_programming%3Afile-io-functions) — Computer Programming, chapter 10, asked 2×
- [Development, energy rate, HDI of Nepal](https://www.bctengineer.com/question.md?key=semester_7%2Fenergy_environment_and_society%3Adevelopment-energy-hdi-nepal) — Energy Environment and Society, chapter 1