# Factors on which unit rate depends

Estimating and Costing · Chapter 4: Analysis of Rates

- Asked in: 2074 Asoj, 4 marks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/estimating_and_costing/factors-unit-rate-depends
- Whole chapter: https://www.bctengineer.com/md/semester_7/estimating_and_costing/chapter-4

## Question

What are the factors on which the unit rates of a particular item of work depend?

## Short answer

Unit rates depend on location and lead, material availability and price, wage rates and labour productivity, specification and quality, quantity of work, equipment and method, climate and site conditions, time of completion, norms and wastage allowances, and overhead, profit, taxes and contract terms.

## Answer

The unit rate of an item of work depends on:
1. **Location and lead:** the distance of material sources from the site, and the lift; transport can double the cost in remote hills.
2. **Availability and price of materials:** local or imported, royalty, taxes and market fluctuations.
3. **Wage rates and labour productivity:** availability of skilled labour and the output per day.
4. **Specification and quality:** mix proportions, grade, thickness and finish.
5. **Quantity of work:** a large quantity lowers the unit rate.
6. **Equipment and method:** manual or mechanical work, the cost of machines and fuel.
7. **Climate, season and site conditions:** rain, altitude, access, soil and working space, height of work.
8. **Time of completion:** a short time needs more resources.
9. **Norms and wastage allowances** adopted.
10. **Overhead, profit, taxes** and the terms of the contract.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Why can the rate be much higher in a remote hill district?
   A. Higher concrete strength
   B. Lower wages
   C. Lower taxes
   D. Long lead and transport cost of materials
   Answer: D. Transport from the source raises material cost. (Key point: Location and lead)

2. How does quantity of work affect the unit rate?
   A. A large quantity lowers the unit rate
   B. A large quantity raises it
   C. No effect
   D. Only affects labour wages
   Answer: A. Economy of scale. (Key point: Quantity)

3. Why does a short completion time raise the rate?
   A. It lowers wastage
   B. It needs more resources and overtime
   C. It reduces overhead
   D. It removes taxes
   Answer: B. More labour/equipment is needed to finish quickly. (Key point: Time of completion)

4. Which specification factors affect the unit rate?
   A. Colour of drawings
   B. Name of contractor
   C. Mix proportion, grade, thickness and finish
   D. Size of site office
   Answer: C. Quality and mix change material quantity. (Key point: Specification)

## Related in Estimating and Costing

- [Importance of rate analysis; how rates taken](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-analysis-importance-rates-taken) — Estimating and Costing, chapter 4
- [Rate analysis: meaning, purposes, factors](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-analysis-purposes-factors) — Estimating and Costing, chapter 4, asked 4×
- [Requirements and factors of rate analysis](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-analysis-requirements-factors) — Estimating and Costing, chapter 4, asked 2×
- [Factors affecting rate analysis; necessity](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Afactors-affecting-rate-necessity) — Estimating and Costing, chapter 4
- [Factors affecting rate analysis (explain)](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Afactors-affecting-rate-p) — Estimating and Costing, chapter 4
- [How Nepal Government takes norms and rates](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Anepal-govt-norms-rates) — Estimating and Costing, chapter 4

## Related in other subjects

- [Item rate contract](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Aitem-rate-contract) — Construction Management, chapter 5
- [Input/output interface unit design factors](https://www.bctengineer.com/question.md?key=semester_5%2Finstrumentation_ii%3Aio-interface-unit-importance) — Instrumentation II, chapter 7
- [RECORD.txt item cost with VAT](https://www.bctengineer.com/question.md?key=semester_1%2Fcomputer_programming%3Afile-record-txt-invoice) — Computer Programming, chapter 10
- [PW with differential inflation rates](https://www.bctengineer.com/question.md?key=semester_6%2Fengineering_economics%3Apw-constant-dollars-differential-inflation) — Engineering Economics, chapter 8