# Materials: 12 mm plaster 1:6 per 10 m²

Estimating and Costing · Chapter 4: Analysis of Rates

- Asked in: 2075 Asoj, 4 marks
- Video: [Cement and Sand calculation in plastering work 1:6 Ratio ।। Civil engineering technical video](https://www.youtube.com/watch?v=AcbTfzwU0oc) — CIVIL ENGINEER MUNTAZIR
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/estimating_and_costing/materials-plaster-12mm-1-6
- Whole chapter: https://www.bctengineer.com/md/semester_7/estimating_and_costing/chapter-4

## Question

Prepare quantities of material required for 12 mm thick (1:6) cement plastering per 10 m² in brick wall.

## Short answer

For 10 m² of 12 mm plaster in 1:6 mortar, wet volume 0.12 m³, dry volume 0.1524 m³. Cement needed: 0.63 bags (0.0218 m³); sand: 0.131 m³.

## Answer

Assumptions: dry volume = 1.54 × wet volume for concrete and 1.27 × wet volume for mortar; 1 m³ of cement = 28.8 bags of 50 kg; no wastage is added.

**12 mm plaster 1:6 per 10 m²**
- Wet mortar $= 10.0 \times 0.0120 = 0.1200$ m³; dry volume $= 1.27 \times 0.1200 = 0.1524$ m³
- Cement $= 1/7 \times 0.1524 = 0.0218$ m³ $= 0.63$ bags
- Sand $= 6/7 \times 0.1524 = 0.1306$ m³

**Answer per 10 m²: cement = 0.63 bags (0.0218 m³); sand = 0.131 m³.**

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Wet mortar for 10 m^2 of 12 mm plaster?
   A. 0.1524 m^3
   B. 0.1200 m^3
   C. 0.012 m^3
   D. 1.2 m^3
   Answer: B. 10 x 0.012 = 0.12 m^3. (Key point: Wet mortar)

2. Dry volume?
   A. 0.1524 m^3 (1.27 x 0.12)
   B. 0.1848 m^3 (1.54)
   C. 0.12 m^3
   D. 0.0945 m^3
   Answer: A. Mortar factor is 1.27. (Key point: Dry mortar)

3. Cement for 1:6?
   A. 1/6 x 0.1524
   B. 1/7 x 0.12
   C. 6/7 x 0.1524
   D. 1/7 x 0.1524 = 0.0218 m^3 = 0.63 bags
   Answer: D. Sum 7. (Key point: Cement)

## Related in Estimating and Costing

- [Rate analysis: 12.5 mm plaster 1:3, per 100 m²](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-plaster-12-5-1-3-ceiling) — Estimating and Costing, chapter 4
- [Rate analysis: 12.5 mm plaster 1:5, per m²](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-plaster-12-5-1-5) — Estimating and Costing, chapter 4, asked 3×
- [Materials for brick wall 10 m (1:5)](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Amaterials-brick-wall-10m-1-5) — Estimating and Costing, chapter 4, asked 2×
- [Materials: 150 m³ brick 1:4, 120 m² plaster](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Amaterials-brick-150m3-plaster-120m2) — Estimating and Costing, chapter 4
- [Materials for 100 m brick wall 1:6](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Amaterials-brick-wall-100m) — Estimating and Costing, chapter 4
- [Materials for brick wall, two windows 1.5 m](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Amaterials-brick-wall-windows-1-5) — Estimating and Costing, chapter 4

## Related in other subjects

- [Brick and mortar for 230 mm wall (100 kN/m)](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Awall-eccentric-230mm-100kn-5m) — Concrete Technology and Masonry Structure, chapter 8, asked 7×
- [Brick and mortar for 250 mm wall (350 kN/m)](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Awall-eccentric-250mm-350kn) — Concrete Technology and Masonry Structure, chapter 8, asked 7×
- [Thermal resistance of brick wall with plaster](https://www.bctengineer.com/question.md?key=semester_2%2Ffundamental_of_thermodynamics_and_heat_transfer%3Athermal-resistance-plane-brick-wall-plaster) — Fundamental of Thermodynamics & Heat Transfer, chapter 7
- [Cement and sand for 100 m² plastering numerical](https://www.bctengineer.com/question.md?key=semester_6%2Fbuilding_technology%3Aplaster-100m2-1to6) — Building Technology, chapter 3, asked 2×