# Materials for 12 cm RCC slab

Estimating and Costing · Chapter 4: Analysis of Rates

- Asked in: 2073 Shrawan, 4 marks
- Video: [RCC Slab Estimation | Materials Quantity Calculation](https://www.youtube.com/watch?v=3oJo1dzvbH0) — Learn Civil Tech & Tricks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/estimating_and_costing/materials-rcc-slab-12cm
- Whole chapter: https://www.bctengineer.com/md/semester_7/estimating_and_costing/chapter-4

## Question

Estimate the quantities of cement, sand and coarse aggregate required for 12 cm thick RCC slab of (1:1½:3) mix proportion. The outside dimensions of slab are 4.20 m × 3 m.

## Short answer

Slab volume is 1.512 m³; dry volume 2.328 m³ for 1:1.5:3 mix. Cement = 12.2 bags (0.423 m³), sand = 0.635 m³, coarse aggregate = 1.270 m³.

## Answer

Assumptions: dry volume = 1.54 × wet volume for concrete and 1.27 × wet volume for mortar; 1 m³ of cement = 28.8 bags of 50 kg; no wastage is added. The slab is taken as one rectangle of the outside dimensions given and the volume of steel is not deducted.

- Volume of slab $= 4.20 \times 3.00 \times 0.12 = 1.512$ m³

**Concrete 1:1½:3**
- Wet volume $= 1.512$ m³; dry volume $= 1.54 \times 1.512 = 2.328$ m³ (sum of ratio $= 5.5$)
- Cement $= 1/5.5 \times 2.328 = 0.423$ m³ $= 0.423 \times 28.8 = 12.2$ bags (50 kg)
- Sand $= 1.5/5.5 \times 2.328 = 0.635$ m³
- Coarse aggregate $= 3/5.5 \times 2.328 = 1.270$ m³

**Answer: cement = 12.2 bags (0.423 m³); sand = 0.635 m³; coarse aggregate = 1.270 m³.**

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Slab volume?
   A. 4.2 x 3 = 12.6
   B. 1.512 x 1.54
   C. 4.20 x 3.00 x 0.12 = 1.512 m^3
   D. 0.12 x 3 x 3
   Answer: C. Length x width x thickness. (Key point: Volume)

2. Is steel deducted?
   A. Yes 0.8%
   B. No, volume not deducted
   C. Yes 2%
   D. Yes, doubled
   Answer: B. Stated assumption. (Key point: Steel)

3. Cement?
   A. 1/5.5 x 2.328 = 0.423 m^3 = 12.2 bags
   B. 1/5.5 x 1.512
   C. 1/3 x 2.328
   D. 1/4.5 x 2.328
   Answer: A. Dry = 1.54 x 1.512. (Key point: Cement)

4. Sand, aggregate?
   A. 1.270 and 0.635
   B. 0.423 and 0.846
   C. 1.0 and 2.0
   D. 0.635 m^3 and 1.270 m^3
   Answer: D. 1.5/5.5 and 3/5.5 of dry. (Key point: Sand and aggregate)

## Related in Estimating and Costing

- [RCC slab culvert (u): four items](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aslab-culvert-u-four-items) — Estimating and Costing, chapter 6
- [RCC slab culvert 1.5 m span: four items](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aslab-culvert-n-four-items) — Estimating and Costing, chapter 6
- [RCC slab culvert: brick, wearing coat, GI pipe, steel](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aslab-culvert-a-fig-b) — Estimating and Costing, chapter 6
- [Well foundation: sinking, brick, sand filling, PCC](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Awell-foundation-g-sand-filling) — Estimating and Costing, chapter 6, asked 2×
- [RCC slab culvert: excavation, PCC foundation, slab](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aslab-culvert-j) — Estimating and Costing, chapter 6
- [Materials: 12 mm plaster 1:6 per 10 m²](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Amaterials-plaster-12mm-1-6) — Estimating and Costing, chapter 4

## Related in other subjects

- [Beam supporting RCC slab, DL 25, IL 20 kN/m](https://www.bctengineer.com/question.md?key=semester_6%2Fdesign_of_steel_and_timber_structure%3Abeam-rcc-slab-6m-25dl-20il) — Design of Steel and Timber Structure, chapter 7, asked 2×
- [Fineness modulus of coarse aggregate (numerical)](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Afineness-modulus-numerical) — Concrete Technology and Masonry Structure, chapter 1
- [Phi-index of storm, 20 cm rain, 12 cm runoff](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Aphi-index-20cm-12cm) — Engineering Hydrology, chapter 3
- [Brick and mortar: 20 cm wall, 3.4 m](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Awall-eccentric-20cm-100kn-3-4m) — Concrete Technology and Masonry Structure, chapter 8, asked 7×