title: "Define project; road project estimate"
subject: "Estimating and Costing"
chapter: 5
key: "semester_7/estimating_and_costing:project-road-estimate"
source: https://www.bctengineer.com/q/semester_7/estimating_and_costing/project-road-estimate
site: BCT Engineering
---

# Define project; road project estimate

Estimating and Costing · Chapter 5: Project Estimate

- Asked in: 2074 Chaitra, 5 marks
- Video: [cost estimate of road #quantitysurvey](https://www.youtube.com/watch?v=C52qNhizo8Q) — Engr Suliman Khan
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/estimating_and_costing/project-road-estimate
- Whole chapter: https://www.bctengineer.com/md/semester_7/estimating_and_costing/chapter-5

## Question

Define project. Discuss estimation of a road project.

## Short answer

A project is planned interrelated activities with clear objective, scope, time and budget. Road estimate uses survey/design data, quantities for earthwork, pavement, drainage, structures, protection and furniture, and District Rates with lead/lift. Abstract adds overhead/profit, 5% contingency, supervision, VAT 13%, land acquisition and utility shifting; report includes drawings, specs and programme.

## Answer

A **project** is a set of planned, interrelated activities with a clear objective, definite scope, limited time and a fixed budget. A road project is the construction (or upgrading) of a road of a defined standard between two points.

#### Estimation of a road project

1. **Survey and design data:** reconnaissance and detailed survey, centre line, longitudinal section, cross-sections, traffic and soil (CBR) data, design standard (Nepal Road Standard 2070), drainage and structure design.
2. **Quantities** are taken out from the drawings:
   - Earthwork in cutting and filling from cross-sections (mean-area or prismoidal method); rock excavation separately.
   - Sub-base, base course, wearing course (bituminous or concrete).
   - Drainage: side drains, culverts, causeways, bridges.
   - Protection works: retaining and breast walls, gabion, bio-engineering.
   - Road furniture: signs, kilometre stones, guard stones, markings.
3. **Rates** from the District Rates and norms, with lead and lift for materials and plant (roller, grader, paver, tipper).
4. **Abstract of cost:** the cost of all items is totalled; overhead and profit, physical contingency (5%), supervision and administration, environmental mitigation, price adjustment and VAT 13% are added.
5. **Report:** introduction, design standards, quantities and rate analysis, abstract, specifications, drawings and construction programme.

Land acquisition and utility shifting are included as separate heads.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. How is earthwork quantity in a road estimated?
   A. From the weight of the vehicles
   B. From the length multiplied by carriageway width only
   C. From the cost of the pavement
   D. From cross-sections using the mean-area or prismoidal method
   Answer: D. Cut and fill are computed from cross-sections along the centre line. (Key point: Road earthwork)

2. Which standard is mentioned for road design data?
   A. Nepal Road Standard 2070
   B. Nepal Building Code 105
   C. IS 456
   D. DUDBC norm for buildings
   Answer: A. NRS 2070 sets design standard for roads. (Key point: Road standard)

3. What is added to the cost of items in the road abstract?
   A. Only profit
   B. Overhead and profit, contingency (5%), supervision, environmental mitigation, escalation and VAT 13%
   C. Only land cost
   D. Depreciation of plant
   Answer: B. These are added to obtain the total cost. (Key point: Abstract of cost)

## Related in Estimating and Costing

- [Components of detail estimate report (road)](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Adetail-estimate-report-road) — Estimating and Costing, chapter 5
- [Define project; irrigation project estimate](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aproject-irrigation-estimate) — Estimating and Costing, chapter 5, asked 4×
- [Detail estimate report for sewerage project](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aestimate-report-sewerage) — Estimating and Costing, chapter 5, asked 2×
- [Method of quantity estimate for road](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aroad-method-quantity-explain) — Estimating and Costing, chapter 6
- [Tasks in preparing building project estimate](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aworks-considered-building-project-estimate) — Estimating and Costing, chapter 5, asked 2×
- [Stages of project estimate](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Astages-project-estimate) — Estimating and Costing, chapter 5

## Related in other subjects

- [Proposal; feasibility study of a road project](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aproposal-questions-feasibility-road) — Project Engineering, chapter 2
- [Project proposal; cost benefit analysis for road](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aproposal-cba-road-project) — Project Engineering, chapter 2
- [CPM network, road project (days)](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Acpm-network-road-project-b79) — Project Engineering, chapter 3
- [Software process models and effort estimation](https://www.bctengineer.com/question.md?key=semester_5%2Finstrumentation_ii%3Asw-process-models) — Instrumentation II, chapter 9, asked 2×