# Significance and requirements of rate analysis

Estimating and Costing · Chapter 4: Analysis of Rates

- Asked in: 2081 Baisakh, 3+3 marks; 2075 Chaitra, 3+3 marks; 2068 Baisakh (old course), 2 marks (asked 3 times)
- Video: [What is the rate analysis of civil engineering projects and how to estimate the cost rate](https://www.youtube.com/watch?v=V-WmiQWHQJ0) — Cost Engineering Professional
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/estimating_and_costing/rate-analysis-significance-requirements
- Whole chapter: https://www.bctengineer.com/md/semester_7/estimating_and_costing/chapter-4

## Question

Explain the significance of analysis of rates in civil engineering projects. What are the requirements for analysis of rates?

## Short answer

Rate analysis provides unit rates for estimating, material/labour needs, tender evaluation, and cost control. It requires drawings, material and labour rates, consumption norms, equipment data, wastage allowances, overhead/profit, and site data.

## Answer

#### Significance of rate analysis in civil projects
1. Gives the **unit rate** of every item, which with the quantities gives the cost of the project.
2. Gives the **consumption of materials, labour and equipment**, for procurement and scheduling.
3. Provides a sound basis for **tender evaluation**, and for judging abnormally low or high bids.
4. Helps to price **extra items and variations** fairly.
5. Allows **comparison of alternatives** (materials, methods, mix proportions).
6. Helps in **cost control** during construction, and standardizes the rates in the government departments.

#### Requirements for rate analysis
1. **Drawings and specifications** of the item (to know the dimensions, quality and method).
2. **Material rates:** local market rates and the District Rate of the materials, with the transport (lead) and loading/unloading charges.
3. **Labour rates:** wages of skilled and unskilled labour from the District Rate, and the labour productivity.
4. **Norms:** the standard consumption of materials and labour per unit of work (DUDBC norms for building and sanitary work, Department of Roads norms for road work).
5. **Equipment data:** hire or running cost of machines, with their output.
6. **Wastage allowances** and conversion factors, such as dry volume of mortar and compaction factors.
7. **Overhead, profit and tax:** contractor's overhead and profit (15% in the DUDBC norms), VAT 13% and any royalty or insurance.
8. **Site data:** lead, lift, location and conditions of the work.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Which is a significance of rate analysis?
   A. It gives the unit rate of each item and helps evaluate tenders and price variations
   B. It replaces drawings
   C. It removes need for estimates
   D. It fixes the design loads
   Answer: A. Unit rates with quantities give the cost; also used for tender evaluation and variations. (Key point: Significance)

2. Which norms are used for building and sanitary work vs road work?
   A. DoR for buildings, DUDBC for roads
   B. DUDBC norms for buildings/sanitary, Department of Roads norms for roads
   C. IS codes for both
   D. NBC for both
   Answer: B. DUDBC covers building and sanitary; DoR covers road work. (Key point: Norms used)

3. What overhead/profit and VAT are normally taken?
   A. 10% overhead, 15% VAT
   B. 5% overhead, 13% VAT
   C. 15% contractor's overhead and profit, 13% VAT
   D. 15% overhead, 5% VAT
   Answer: C. DUDBC norms use 15% overhead and profit and VAT is 13%. (Key point: Overhead and tax)

## Related in Estimating and Costing

- [Importance of rate analysis; how rates taken](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-analysis-importance-rates-taken) — Estimating and Costing, chapter 4
- [Requirements and factors of rate analysis](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-analysis-requirements-factors) — Estimating and Costing, chapter 4, asked 2×
- [Rate analysis: plain cement concrete (1:3:4)](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-pcc-1-3-4) — Estimating and Costing, chapter 4
- [Factors affecting rate analysis; necessity](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Afactors-affecting-rate-necessity) — Estimating and Costing, chapter 4
- [Rate analysis: 10 cm compacted gravel subgrade](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-gravel-subgrade-10cm) — Estimating and Costing, chapter 4, asked 2×
- [Rate analysis: 30 cm compacted gravel subgrade](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-gravel-subgrade-30cm) — Estimating and Costing, chapter 4, asked 2×

## Related in other subjects

- [Scope and importance of geology in civil engineering](https://www.bctengineer.com/question.md?key=semester_3%2Fengineering_geology_i%3Ascope-and-importance-of-geology) — Engineering Geology I, chapter 1, asked 24×
- [Important properties of civil engineering materials](https://www.bctengineer.com/question.md?key=semester_3%2Fcivil_engineering_materials%3Aimportant-properties-civil-materials) — Civil Engineering Materials, chapter 1, asked 8×
- [Importance and scope of civil engineering materials](https://www.bctengineer.com/question.md?key=semester_3%2Fcivil_engineering_materials%3Aimportance-scope-subject) — Civil Engineering Materials, chapter 1, asked 8×
- [Classification of civil engineering materials](https://www.bctengineer.com/question.md?key=semester_3%2Fcivil_engineering_materials%3Aclassification-civil-materials) — Civil Engineering Materials, chapter 1, asked 2×