# Rate analysis: brickwork 1:4, 10 m³

Estimating and Costing · Chapter 4: Analysis of Rates

- Asked in: 2082 Bhadra, 5 marks
- Video: [Rate analysis of First class brickwork](https://www.youtube.com/watch?v=ZnfJgM3R5j8) — sustainable Civil Engineering Academy
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/estimating_and_costing/rate-brick-1-4-superstructure
- Whole chapter: https://www.bctengineer.com/md/semester_7/estimating_and_costing/chapter-4

## Question

Prepare rate analysis for 10 m³ of brickwork in (1:4) cement sand mortar in superstructure. Take brick size: 230 × 110 × 55 mm and mortar joint thickness: 10 mm.

## Short answer

For 10 m³ 1:4 brickwork superstructure: bricks 5609 nos., cement 19.22 bags, sand 2.67 m³, mason 16 md, labourer 22 md. Direct cost Rs 147,108, plus 15% overhead/profit gives Rs 169,174.20, i.e. Rs 16,917.42 per m³, excluding VAT.

## Answer

#### Mortar and brick quantities for 10 m³
Brick with mortar: $240 \times 120 \times 65$ mm (10 mm joints).
- Number of bricks per m³ = $\dfrac{1}{0.24 \times 0.12 \times 0.065} = 534.19$; for 10 m³ = 5341.88 nos. (net). Add 5% breakage: 5609 nos.
- Volume of bricks alone = 5341.88 x 0.23 x 0.11 x 0.055 = 7.433 m³.
- Wet mortar = 10 - 7.433 = 2.567 m³.
- Dry mortar = 2.567 x 1.30 = 3.337 m³ (1.30 allows for voids in sand and loss).
- For 1:4: cement = 3.337/5 = 0.6674 m³ x 1,440 = 961.0 kg = 19.22 bags; sand = 3.337 x 4/5 = 2.669 m³.

#### Analysis for 10 m³ (rates illustrative; labour norms assumed in DUDBC style)
| Description | Qty | Unit | Rate (Rs) | Amount (Rs) |
|---|---|---|---|---|
| 1st class bricks (230x110x55), net 5,341.88 + 5% wastage | 5609 | nos. | 15.00 | 84,135.00 |
| Cement (0.6674 m³) | 19.22 | bag | 900.00 | 17,298.00 |
| Sand (2.669 m³) | 2.67 | m³ | 2,500.00 | 6,675.00 |
| Mason (skilled) | 16 | md | 1,200.00 | 19,200.00 |
| Helper / labourer (unskilled) | 22 | md | 900.00 | 19,800.00 |
| **Sub-total** | | | | **147,108.00** |
| Contractor's overhead and profit | 15% | | | 22,066.20 |
| **Total for 10 m³** | | | | **169,174.20** |

**Answer: Cost of 10 m³ of 1:4 brickwork in superstructure = Rs 169,174.20, i.e. Rs 16,917.42 per m³** (excluding VAT).

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Bricks with 5% breakage for 10 m³?
   A. 5342
   B. 534
   C. 5609 nos.
   D. 6000
   Answer: C. 5341.88 x 1.05 = 5609. (Key point: Brick count)

2. Wet mortar for 10 m³?
   A. 7.433 m³
   B. 3.337 m³
   C. 2.567 x 1.3 m³
   D. 10 - 7.433 = 2.567 m³
   Answer: D. Bricks alone occupy 7.433 m³. (Key point: Wet mortar)

3. How is cement found?
   A. Dry mortar 3.337/5 = 0.6674 m³ = 19.22 bags
   B. 3.337/4
   C. 3.337/6
   D. 2.567/5
   Answer: A. Ratio sum is 5. (Key point: Cement for 1:4)

4. Rate per m³?
   A. Rs 169,174
   B. Rs 16,917.42
   C. Rs 14,710.80
   D. Rs 22,066
   Answer: B. 169,174.20/10. (Key point: Final rate)

## Related in Estimating and Costing

- [Materials for brickwork 1:4 (230×110×55)](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Amaterials-brick-1-4-sizes) — Estimating and Costing, chapter 4
- [Rate analysis: brick masonry 1:5, superstructure](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-brick-1-5-superstructure) — Estimating and Costing, chapter 4
- [Brick (1:6) materials; PCC (1:2:4) rate](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Amaterials-brick-1-6-and-pcc-rate) — Estimating and Costing, chapter 4
- [Rate analysis: brickwork 1:6 per m³](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-brick-1-6-upper-floor) — Estimating and Costing, chapter 4, asked 2×
- [Rate analysis: 12.5 mm plaster 1:5, per m²](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-plaster-12-5-1-5) — Estimating and Costing, chapter 4, asked 3×
- [Rate analysis: 12.5 mm plaster 1:3, per 100 m²](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-plaster-12-5-1-3-ceiling) — Estimating and Costing, chapter 4

## Related in other subjects

- [Mortar for 10 m³ brickwork (1:4) numerical](https://www.bctengineer.com/question.md?key=semester_6%2Fbuilding_technology%3Amortar-10m3-1to4) — Building Technology, chapter 3
- [Brick and mortar for 230 mm wall (100 kN/m)](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Awall-eccentric-230mm-100kn-5m) — Concrete Technology and Masonry Structure, chapter 8, asked 7×
- [Mortar properties; cement and sand for 10 cum](https://www.bctengineer.com/question.md?key=semester_6%2Fbuilding_technology%3Amortar-quantity-10cum) — Building Technology, chapter 3
- [Detailed specification of cement sand mortar 1:4](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Adetailed-spec-cs-mortar-1-4) — Construction Management, chapter 12, asked 2×