title: "Rate analysis: one metric ton reinforcement"
subject: "Estimating and Costing"
chapter: 4
key: "semester_7/estimating_and_costing:rate-reinforcement-per-mt"
source: https://www.bctengineer.com/q/semester_7/estimating_and_costing/rate-reinforcement-per-mt
site: BCT Engineering
---

# Rate analysis: one metric ton reinforcement

Estimating and Costing · Chapter 4: Analysis of Rates

- Asked in: 2078 Bhadra, 6 marks
- Video: [Rate Analysis of Reinforcement Steel - Right Method for Costing of Reinforcement Steel Rebars](https://www.youtube.com/watch?v=jl6GldOKVdU) — Factual Civil Engineering
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/estimating_and_costing/rate-reinforcement-per-mt
- Whole chapter: https://www.bctengineer.com/md/semester_7/estimating_and_costing/chapter-4

## Question

Prepare the analysis of rates for one metric ton of reinforcement. Labor norms per MT: skilled 12 no/m³/day, unskilled 12 no/m³/day. Assume suitable rates.

## Short answer

Rate per metric ton of reinforcement is NPR 169,050, including 1,030 kg steel (3% wastage), 8 kg binding wire, 12 skilled and 12 unskilled man-days, plus 15% overhead and 10% profit.

## Answer

The rate covers supplying, cutting, bending, placing and tying the steel bars as per drawing and bar-bending schedule, per metric tonne (MT). Rates are assumed: steel (Fe 500D) NPR 100/kg, binding wire NPR 130/kg, skilled labour NPR 1,500/day, unskilled NPR 1,100/day, overhead 15%, profit 10%. The labour norms are read as 12 skilled and 12 unskilled man-days per MT, as given.

#### Quantities per MT

- Steel $= 1000$ kg plus 3% for cutting waste and laps $= 1030$ kg
- Binding wire $= 8$ kg per MT (DUDBC-type norm)
- Skilled labour $= 12$ days; unskilled labour $= 12$ days

#### Analysis

| Item | Qty | Unit | Rate (NPR) | Amount (NPR) |
|---|---:|---|---:|---:|
| Reinforcement steel (1,000 kg + 3% cutting and lap wastage) | 1,030 | kg | 100.00 | 103,000.00 |
| Binding wire (annealed 16 gauge) | 8 | kg | 130.00 | 1,040.00 |
| Skilled labour (bar bender) | 12 | day | 1,500.00 | 18,000.00 |
| Unskilled labour | 12 | day | 1,100.00 | 13,200.00 |
| **Direct cost** | | | | **135,240.00** |
| Contractor's overhead @ 15% | | | | 20,286.00 |
| Contractor's profit @ 10% | | | | 13,524.00 |
| **Total (rate per MT)** | | | | **169,050.00** |

**Rate = NPR 169,050.00 per MT** (about NPR 169.05 per kg).

If the contract pays only for the steel in the drawing (as per bar-bending schedule), the wastage allowance is not paid separately but is included in the rate as above.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Why is 1,030 kg of steel priced for one tonne of reinforcement?
   A. 3% is added for rust
   B. 30 kg is binding wire
   C. 3% is the contractor's profit
   D. 3% is added for cutting waste and laps
   Answer: D. 1,000 kg + 3% = 1,030 kg for cutting waste and laps. (Key point: Steel quantity)

2. How much binding wire is taken per MT?
   A. 80 kg
   B. 0.8 kg
   C. 8 kg
   D. 30 kg
   Answer: C. The answer uses 8 kg per MT (DUDBC-type norm) at NPR 130/kg. (Key point: Binding wire)

3. How is the given labour norm read?
   A. 12 skilled man-days per m^3 of concrete
   B. 12 skilled and 12 unskilled man-days per MT
   C. 1.2 skilled and 12 unskilled days
   D. 12 days in total for both
   Answer: B. The norm is taken as 12 skilled and 12 unskilled days per MT. (Key point: Labour norm)

4. How does the rate reach NPR 169,050 per MT?
   A. Direct cost 135,240 + 15% overhead + 10% profit
   B. 135,240 + 25% on labour only
   C. 135,240 + 13% VAT
   D. 103,000 + 15% overhead
   Answer: A. 135,240 + 20,286 + 13,524 = 169,050. (Key point: Rate build-up)

## Related in Estimating and Costing

- [Rate analysis: 12.5 mm plaster 1:5, per m²](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-plaster-12-5-1-5) — Estimating and Costing, chapter 4, asked 3×
- [Rate analysis: 12.5 mm plaster 1:3, per 100 m²](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-plaster-12-5-1-3-ceiling) — Estimating and Costing, chapter 4
- [How Nepal Government takes norms and rates](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Anepal-govt-norms-rates) — Estimating and Costing, chapter 4
- [Departmental norms for rate analysis in Nepal](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Adepartmental-norms-nepal) — Estimating and Costing, chapter 4
- [Importance of rate analysis; how rates taken](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-analysis-importance-rates-taken) — Estimating and Costing, chapter 4
- [Rate analysis: 12 mm plaster 1:3 ceiling](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arate-plaster-12mm-1-3-ceiling) — Estimating and Costing, chapter 4, asked 3×

## Related in other subjects

- [Drainage rate (mm/day), initial 55 mm](https://www.bctengineer.com/question.md?key=semester_6%2Firrigation_and_drainage_engineering%3Adrainage-rate-mmday-bunded-55mm) — Irrigation and Drainage Engineering, chapter 9, asked 3×
- [Bits per sample and information rate (4.5 kHz, 8 levels)](https://www.bctengineer.com/question.md?key=semester_6%2Fcommunication_systems%3Abits-info-rate-4-5khz-8-levels) — Communication Systems, chapter 6
- [Symbol rate, entropy and information rate (6 symbols per 10 μs)](https://www.bctengineer.com/question.md?key=semester_6%2Fcommunication_systems%3Asymbol-rate-six-symbols-10us) — Communication Systems, chapter 6