# Units: flooring, skirting, railing, half brick wall

Estimating and Costing · Chapter 1: Introduction

- Asked in: 2082 Baisakh, 2 marks
- Video: [Tiles work को माप कर कांट्रेक्टर का पेमेंट करना सीखें | how to measure tiles work  |tiles work rate](https://www.youtube.com/watch?v=-hxyoeSBLPk) — Civil Engineer Anjani Kumar
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/estimating_and_costing/units-flooring-skirting-railing-wall
- Whole chapter: https://www.bctengineer.com/md/semester_7/estimating_and_costing/chapter-1

## Question

Write down the unit of measurement and payment of the given items of works: i) Flooring works ii) Skirting iii) Railing works iv) Half brick walls.

## Short answer

Flooring is measured and paid in m² of net floor area; skirting in running metre along the wall with door deductions; railing in running metre along the top rail; half-brick wall in m² with openings deducted.

## Answer

| Item | Unit of measurement | Unit of payment | Remarks |
|---|---|---|---|
| i) Flooring | m² | m² | Length x width of net floor area, thickness and type stated |
| ii) Skirting | m (running metre) | m | Height and thickness specified; measured along the wall, deducting door openings |
| iii) Railing | m (running metre) | m | Measured along the centre line of the top rail, with height and pattern given |
| iv) Half-brick wall | m² | m² | Thickness 115 mm; the area deducts openings larger than the limit in the rules |

In some DUDBC items skirting is also paid per m² by area of the finished strip; the unit stated in the item description governs.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. What is the unit of flooring?
   A. m
   B. m³
   C. kg
   D. m²
   Answer: D. Flooring is area work. (Key point: Flooring)

2. What is the usual unit for skirting and railing?
   A. Running metre
   B. Square metre
   C. Cubic metre
   D. Number
   Answer: A. They are measured along their length. (Key point: Skirting and railing)

3. How is a half-brick wall (115 mm) measured?
   A. In m³
   B. In m², as thickness is fixed
   C. In running metre
   D. In kg
   Answer: B. A fixed-thickness wall is measured by area. (Key point: Half-brick wall)

## Related in Estimating and Costing

- [Units: iron grills, skirting, formwork, shutters](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aunits-grills-skirting-formwork-shutters) — Estimating and Costing, chapter 1
- [Units of measurement and payment, civil and sanitary](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aunits-civil-sanitary-works) — Estimating and Costing, chapter 1
- [Measurement and units: pointing, steel](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Ameasure-pointing-steel-units) — Estimating and Costing, chapter 1
- [Units: sunshade, shutters, grills, AC sheet](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aunits-sunshade-shutter-grill-acsheet) — Estimating and Costing, chapter 1
- [Units: excavation, well steining, conductor, cornice](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aunits-excavation-well-steining-conductor) — Estimating and Costing, chapter 1
- [RCC frame building: excavation, brick, plaster](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Arcc-frame-two-room-e) — Estimating and Costing, chapter 6

## Related in other subjects

- [Brick and mortar for wall with timber flooring](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Awall-eccentric-230mm-135kn-timber) — Concrete Technology and Masonry Structure, chapter 8
- [Brick masonry infill walls in RC frames](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Amasonry-infill-walls) — Concrete Technology and Masonry Structure, chapter 7, asked 3×
- [Brick and mortar for 230 mm wall (100 kN/m)](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Awall-eccentric-230mm-100kn-5m) — Concrete Technology and Masonry Structure, chapter 8, asked 7×
- [Brick and mortar: 20 cm wall, 3.4 m](https://www.bctengineer.com/question.md?key=semester_5%2Fconcrete_technology_and_masonry_structure%3Awall-eccentric-20cm-100kn-3-4m) — Concrete Technology and Masonry Structure, chapter 8, asked 7×