# Development cycle; RoR layout with headrace canal

Hydropower Engineering · Chapter 2: Planning of Hydropower Projects

- Asked in: 2080 Baishakh, 4+4 marks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/hydropower_engineering/dev-cycle-ror-layout-headrace-canal
- Whole chapter: https://www.bctengineer.com/md/semester_7/hydropower_engineering/chapter-2

## Question

Explain the different phases of the hydropower development cycle. Draw the layout plan and section of a RoR type hydropower project with headrace canal.

## Short answer

A RoR plant with headrace canal uses a diversion weir, intake with trash rack, gravel trap, settling basin, contour canal, forebay with spillway and trash rack, penstock, powerhouse, tailrace and switchyard. The canal preserves gross head by a small slope.

## Answer

#### Phases of the hydropower development cycle
1. **Reconnaissance:** Desk study and site visit to identify and rank the sites; rough cost and energy.
2. **Pre-feasibility:** Survey, hydrology and geology at a moderate level; compare alternative layouts; select the best.
3. **Feasibility:** Detailed investigation, design optimisation, cost (±10-15%), economic and financial analysis, IEE/EIA.
4. **Detailed design and tendering:** Final drawings, specification, tender documents, contract.
5. **Construction and commissioning:** Build and test the plant.
6. **Operation and maintenance:** Run, maintain and monitor.

#### Layout of RoR plant with headrace canal
```text
Plan
 River~~~~~  Weir             Canal
 ~~~~~~~~~~~|Intake=Desander===========\
 ~~~~~~~~~~~                            \ Forebay
                                          \ Penstock
                                            PH -> Tailrace
                                               -> River
Section along waterway
 weir  intake desander    canal (slope 1:1000)  forebay
 __|~~~|__ __ ___________________________________|
                                               \ penstock
                                                  \__PH
```
Main components: diversion weir with undersluice, intake with trash rack, gravel trap, settling basin (desander), headrace canal with cross-drainage works, forebay with spillway and trash rack, penstock, powerhouse, tailrace and switchyard. The canal is laid along the contour at a small slope so that most of the gross head is kept for the penstock.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Which is a feature of the feasibility stage?
   A. Desk study only
   B. Detailed investigation, design optimisation, cost within ±10-15% and IEE/EIA
   C. Tender and contract signing
   D. Rough cost and energy estimate
   Answer: B. Feasibility gives detailed investigation, optimisation, economic and financial analysis and environmental study. (Key point: Feasibility stage content)

2. What is done in the reconnaissance phase?
   A. Final drawings
   B. Commissioning of turbines
   C. Desk study and site visit to identify and rank sites with rough cost and energy
   D. Detailed drilling at every structure
   Answer: C. Reconnaissance is a low-cost screening of sites. (Key point: Reconnaissance)

3. Why is the headrace canal laid along the contour at a small slope (about 1:1000)?
   A. To increase sediment deposition
   B. So that most of the gross head is kept for the penstock
   C. To reduce the canal length to zero
   D. To raise the flow velocity to a maximum
   Answer: B. A small slope loses little head in the canal, so the head is retained for power. (Key point: Canal slope)

4. What is the correct sequence of the waterway in a RoR plant with headrace canal?
   A. Weir, intake, desander, canal, forebay, penstock, powerhouse, tailrace
   B. Weir, penstock, canal, desander, powerhouse
   C. Intake, forebay, canal, desander, penstock
   D. Powerhouse, penstock, forebay, canal, weir
   Answer: A. Water flows from headworks through settling basin and canal to the forebay, then the penstock and powerhouse. (Key point: Components order)

## Related in Hydropower Engineering

- [Development cycle; storage plant layout](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Adev-cycle-storage-layout) — Hydropower Engineering, chapter 2
- [RoR layout: pressure tunnel and free surface](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Aror-layout-pressure-tunnel-free-flow) — Hydropower Engineering, chapter 2
- [Stages of hydropower development cycle](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Adev-cycle-stages) — Hydropower Engineering, chapter 2
- [Development phases; pre-feasibility factors](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Adev-phases-prefeasibility-factors) — Hydropower Engineering, chapter 2
- [Development cycle and detailed design studies](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Adev-cycle-detailed-design-studies) — Hydropower Engineering, chapter 2
- [Optimizing plant capacity of a RoR project](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Aror-optimum-capacity-discussion) — Hydropower Engineering, chapter 3

## Related in other subjects

- [Project development life cycle phases](https://www.bctengineer.com/question.md?key=semester_7%2Fict_project_management%3Aproject-development-life-cycle) — ICT Project Management, chapter 1
- [Project life cycle phases and activities](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Alife-cycle-phases-activities) — Project Engineering, chapter 1, asked 5×
- [Scope of CM and project life cycle phases](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Ascope-lifecycle-phases) — Construction Management, chapter 1, asked 4×
- [Stages of hydropower project study](https://www.bctengineer.com/question.md?key=semester_6%2Fhydro_power%3Ahydropower-study-stages) — Hydro Power, chapter 3, asked 3×