title: "Development phases; pre-feasibility factors"
subject: "Hydropower Engineering"
chapter: 2
key: "semester_7/hydropower_engineering:dev-phases-prefeasibility-factors"
source: https://www.bctengineer.com/q/semester_7/hydropower_engineering/dev-phases-prefeasibility-factors
site: BCT Engineering
---

# Development phases; pre-feasibility factors

Hydropower Engineering · Chapter 2: Planning of Hydropower Projects

- Asked in: 2080 Bhadra, 2+2+2 marks
- Video: [What are the Stage of Hydropower Development #water #energy #generated #powerhouse #dam #electricity](https://www.youtube.com/watch?v=QAR-x4D_0Gk) — Hydropower
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/hydropower_engineering/dev-phases-prefeasibility-factors
- Whole chapter: https://www.bctengineer.com/md/semester_7/hydropower_engineering/chapter-2

## Question

Mention different phases of the hydropower development cycle. What factors do you consider in the pre-feasibility and feasibility study of hydropower projects?

## Short answer

Phases: reconnaissance, pre-feasibility, feasibility, detailed design, construction, operation. Pre-feasibility studies examine topography, hydrology, geology, layout alternatives, access, transmission, cost, environment, and social factors. Feasibility adds detailed investigations, design optimisation, financial analysis, and environmental assessment.

## Answer

#### Phases of the hydropower development cycle
Reconnaissance, pre-feasibility, feasibility, detailed design and tender, construction and commissioning, operation and maintenance.

#### Factors in the pre-feasibility study
- **Topography:** map and survey of headworks, waterway and powerhouse; choose the layout alternatives.
- **Hydrology:** mean flow, flow duration curve, floods and sediment from available data and short-term gauging.
- **Geology:** surface mapping and geophysics for dam, tunnel and powerhouse sites; landslide and fault risk.
- **Alternatives:** capacity, head, and type of scheme (RoR, PRoR, storage); choose the best one.
- **Access and transmission:** road and line routes, distance to the grid and market.
- **Cost and economics:** rough cost (±20-25%), energy and B/C, IRR.
- **Environment and society:** screening of protected areas, land, settlement, and fish.

#### Additional factors in the feasibility study
- Accurate and detailed survey, drilling, tests, and material surveys.
- Long-term hydrology, 100- and 1000-year floods, sediment and GLOF.
- Optimisation of the installed capacity, final layout and equipment selection.
- Detailed quantity and cost estimate (±10-15%) and construction schedule.
- Financial analysis (NPV, IRR, B/C, sensitivity), financing plan, and the power market (PPA).
- IEE/EIA, resettlement, risk and legal clearances.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. What cost accuracy is expected from pre-feasibility and feasibility studies respectively?
   A. ±5% and ±1%
   B. ±10-15% and ±20-25%
   C. ±20-25% and ±10-15%
   D. ±50% and ±30%
   Answer: C. Accuracy improves from about ±20-25% in pre-feasibility to ±10-15% in feasibility. (Key point: Cost accuracy)

2. Which hydrological work is typical at pre-feasibility level?
   A. Mean flow, flow duration curve, floods and sediment from available data and short-term gauging
   B. 1000-year flood and GLOF analysis with long records only
   C. Hydraulic model tests
   D. No hydrology is done
   Answer: A. Pre-feasibility uses available data and short gauging; long-term series and extreme floods are added at feasibility. (Key point: Pre-feasibility hydrology)

3. What is a key aim regarding alternatives in pre-feasibility?
   A. Fix the final turbine rating
   B. Compare capacity, head and scheme type (RoR, PRoR, storage) and choose the best
   C. Sign the PPA
   D. Prepare tender drawings
   Answer: B. Several alternatives are compared and the best one selected for feasibility study. (Key point: Pre-feasibility alternatives)

4. Which is an additional factor of the feasibility study, not of pre-feasibility?
   A. Screening of protected areas
   B. Rough B/C estimate
   C. Financial analysis (NPV, IRR, sensitivity), financing plan and PPA
   D. Choosing layout alternatives
   Answer: C. Feasibility adds detailed financial analysis, financing and market arrangements. (Key point: Feasibility additions)

## Related in Hydropower Engineering

- [Stages of hydropower development cycle](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Adev-cycle-stages) — Hydropower Engineering, chapter 2
- [Pre-feasibility site-specific investigations](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Aprefeasibility-site-investigations) — Hydropower Engineering, chapter 2
- [Studies in reconnaissance, pre-feasibility, feasibility](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Arecon-prefeas-feas-studies) — Hydropower Engineering, chapter 2, asked 3×
- [Pre-feasibility vs feasibility; site investigations](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Aprefeasibility-vs-feasibility-investigations) — Hydropower Engineering, chapter 2
- [Steps of a feasibility study (team leader)](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Afeasibility-study-steps-consultant) — Hydropower Engineering, chapter 2
- [Development cycle; RoR layout with headrace canal](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Adev-cycle-ror-layout-headrace-canal) — Hydropower Engineering, chapter 2

## Related in other subjects

- [Project development life cycle phases](https://www.bctengineer.com/question.md?key=semester_7%2Fict_project_management%3Aproject-development-life-cycle) — ICT Project Management, chapter 1
- [Pre-feasibility versus feasibility studies](https://www.bctengineer.com/question.md?key=semester_6%2Fhydro_power%3Aprefeasibility-vs-feasibility) — Hydro Power, chapter 3
- [PDLC and feasibility study](https://www.bctengineer.com/question.md?key=semester_7%2Fict_project_management%3Apdlc-feasibility-study) — ICT Project Management, chapter 1
- [Stages of hydropower project study](https://www.bctengineer.com/question.md?key=semester_6%2Fhydro_power%3Ahydropower-study-stages) — Hydro Power, chapter 3, asked 3×