title: "Phreatic line and discharge (k = 5.1×10⁻⁴ cm/s)"
subject: "Hydropower Engineering"
chapter: 4
key: "semester_7/hydropower_engineering:earthen-dam-phreatic-line-2082"
source: https://www.bctengineer.com/q/semester_7/hydropower_engineering/earthen-dam-phreatic-line-2082
site: BCT Engineering
---

# Phreatic line and discharge (k = 5.1×10⁻⁴ cm/s)

Hydropower Engineering · Chapter 4: Headworks of Storage Plants

- Asked in: 2082 Bhadra, 8 marks
- Video: [Problem on Design of Phreatic line in earthen dam without filter](https://www.youtube.com/watch?v=gPWo52zz3OI) — MSR Geo Spatial Solutions
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/hydropower_engineering/earthen-dam-phreatic-line-2082
- Whole chapter: https://www.bctengineer.com/md/semester_7/hydropower_engineering/chapter-4

## Question

An earthen dam made of homogeneous material has the following data: coefficient of permeability of dam material = $5.1 \times 10^{-4}$ cm/sec; top level of dam = 290 masl; bed level of river = 235 masl; reservoir water level = 285 masl; top width of dam = 5 m; U/S slope of dam = 3:1; D/S slope of dam = 2:1. Determine the phreatic line for the dam section and the discharge passing through the dam.

## Short answer

Using Casagrande’s method: base width 280 m, wetted projection b = 150 m, d = 175 m, y₀ = √(50²+175²) – 175 = 7.00 m. The phreatic parabola is y = √(49+14x) (m) with exit about 35 m up the face. Seepage q = k y₀ = 5.1×10⁻⁶ × 7.00 = 3.57×10⁻⁵ m³/s per metre.

## Answer

**Given data and assumptions**: homogeneous dam without any drain; foundation impervious; tail water ignored. Casagrande's method (basic parabola with focus at the d/s toe) is used.

- Dam height $= 290-235 = 55$ m; water head $h = 285-235 = 50$ m; free board $= 5$ m.
- $k = 5.1\times10^{-4}$ cm/s $= 5.1\times10^{-6}$ m/s.

```text
 290 ______5 m______
     /|              \
  3:1/ |   homogeneous \ 2:1
    /  |    dam        \
 285 ~~|                 \
    /  |                  \
 235 ///////////////////////////
     |<--------- 280 m ------->|
```

#### Step 1: Geometry
$$
\begin{aligned}
\text{Base width } B &= 3(55)+5+2(55) = 280\ \text{m} \\
\text{Wetted horizontal projection } b &= 3\times 50 = 150\ \text{m} \\
\text{Entry correction } 0.3b &= 45.0\ \text{m} \\
d &= B-0.7b = 280-105.0 = 175.0\ \text{m}
\end{aligned}
$$
Here $d$ is the horizontal distance from the corrected entry point to the d/s toe (the focus $F$).

#### Step 2: Basic parabola
$$
y_0=\sqrt{h^2+d^2}-d=\sqrt{50^2+175.0^2}-175.0=7.00\ \text{m}
$$
$$
y=\sqrt{y_0^2+2y_0x}
$$
with $x$ measured from the focus (d/s toe) towards the u/s side:

| x from focus (m) | y (m) |
|---|---|
| 0.0 | 7.00 |
| 5.0 | 10.91 |
| 10.0 | 13.75 |
| 20.0 | 18.14 |
| 40.0 | 24.68 |
| 60.0 | 29.82 |
| 80.0 | 34.20 |
| 100.0 | 38.07 |
| 125.0 | 42.42 |
| 150.0 | 46.37 |
| 175.0 | 50.00 |

At $x=d=175.0$ m the parabola reaches $y=h=50$ m, which is the corrected entry point. The u/s end of the actual line is drawn to meet the u/s face at right angles.

#### Step 3: Exit correction (d/s face)
The d/s slope angle is $\alpha=\tan^{-1}(1/2)=26.57^\circ$. The parabola meets the d/s face at a distance
$$
a+\Delta a=\frac{y_0}{1-\cos\alpha}=\frac{7.00}{1-\cos 26.57^\circ}=66.3\ \text{m}
$$
(measured along the slope from the toe). Casagrande's chart covers $30^\circ\le\alpha\le180^\circ$, so for $\alpha<30^\circ$ the exit point is found from Schaffernak's formula:
$$
a=\frac{d}{\cos\alpha}-\sqrt{\frac{d^2}{\cos^2\alpha}-\frac{h^2}{\sin^2\alpha}}=195.66-\sqrt{38,281-12,500}=35.1\ \text{m}
$$
So the line leaves the d/s face about 35.1 m along the slope from the toe (about 15.7 m above the base). (Extrapolating Casagrande's factor 0.36 would give about 42.5 m.) The last part of the line is drawn tangent to the parabola and blended into this exit point.

#### Step 4: Discharge
$$
q=k\,y_0=5.1\times10^{-6}\times 7.00=3.571 \times 10^{-5}\ \text{m}^3/\text{s per m}
$$
(Schaffernak's $q=k\,a\sin\alpha\tan\alpha=5.1\times10^{-6}\times35.1\times0.447\times0.5=4.0\times10^{-5}$ m³/s per m gives a similar order of value.)

**Answer**: the phreatic line is the parabola $y=\sqrt{49.04+14.01\,x}$ (x from the d/s toe, with entry and exit corrections), $y_0=7.00$ m, exit point about 35 m up the d/s face; seepage $q=3.571 \times 10^{-5}\ \text{m}^3/\text{s}$ per metre length of dam ($\approx 3.09$ m³/day per m).

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. How is d computed in Casagrande's method for this dam?
   A. d = B - 0.7b, from base width and wetted horizontal projection b
   B. d = B - b
   C. d = h + b
   D. d = 0.3b
   Answer: A. B = 280, b = 150, d = 280 - 105 = 175 m. (Key point: Geometry)

2. y0 for h = 50 m and d = 175 m is
   A. 50 m
   B. 25 m
   C. 175 m
   D. about 7.0 m
   Answer: D. y0 = sqrt(50^2 + 175^2) - 175 = 7.00 m. (Key point: Basic parabola)

3. Discharge per metre is found from
   A. q = k y0 with k in m/s
   B. q = k h^2
   C. q = k d
   D. q = y0/k
   Answer: A. q = 5.1e-6 x 7.00 = 3.571e-5 m^3/s per m. (Key point: Discharge)

4. The exit correction uses a + delta a = y0/(1 - cos alpha). What is alpha?
   A. The u/s slope angle
   B. The d/s slope angle, tan^-1(1/2) = 26.57 degrees
   C. 90 degrees
   D. The angle of the crest
   Answer: B. alpha is the d/s face angle; C is read from Casagrande's chart (about 0.36 near 30 degrees). (Key point: Exit correction)

## Close variants set in other exams

- [Phreatic line and discharge (crest 300 masl)](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Aearthen-dam-phreatic-line-2079-baishakh) — Hydropower Engineering, chapter 4, asked 2×

## Related in Hydropower Engineering

- [Toe-drain earthen dam: discharge and phreatic line](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Aearthen-dam-toe-drain-2069) — Hydropower Engineering, chapter 4
- [Seepage line for 22 m high earthen dam](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Aearthen-dam-seepage-line-22m-45deg) — Hydropower Engineering, chapter 4
- [Earth dam with drain pipe: phreatic coordinates](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Aearthen-dam-drain-pipe-phreatic) — Hydropower Engineering, chapter 4
- [Seepage discharge through dam body (k = 1×10⁻⁶ m/s)](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Aearthen-dam-seepage-gradient-figure-2072k) — Hydropower Engineering, chapter 4
- [Gravity dam equilibrium and overtopping discharge coefficient](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Agravity-dam-reservoir-capacity-curve-hrwl) — Hydropower Engineering, chapter 4
- [Filter material in earthen dam](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Aearthen-dam-filter-purpose-design) — Hydropower Engineering, chapter 4

## Related in other subjects

- [Top flow line, dam with horizontal filter](https://www.bctengineer.com/question.md?key=semester_4%2Fsoil_mechanics%3Atop-flow-line-horizontal-filter) — Soil Mechanics, chapter 7
- [Reservoir level change, water balance, 15.5 km2](https://www.bctengineer.com/question.md?key=semester_5%2Fengineering_hydrology%3Areservoir-level-change-15-5km2) — Engineering Hydrology, chapter 1, asked 2×