title: "Frequency of flushing of settling basin"
subject: "Hydropower Engineering"
chapter: 5
key: "semester_7/hydropower_engineering:sediment-flushing-frequency-10-percent-storage"
source: https://www.bctengineer.com/q/semester_7/hydropower_engineering/sediment-flushing-frequency-10-percent-storage
site: BCT Engineering
---

# Frequency of flushing of settling basin

Hydropower Engineering · Chapter 5: Headworks of Run-of- River (RoR) Plants

- Asked in: 2070 Ashad, 3 marks
- Video: [Sediment in Settling Basins: Estimation of Flushing Planning](https://www.youtube.com/watch?v=5oByylOiALs) — Hydropower
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/hydropower_engineering/sediment-flushing-frequency-10-percent-storage
- Whole chapter: https://www.bctengineer.com/md/semester_7/hydropower_engineering/chapter-5

## Question

If you have allocated about 10% volume for sediment storage and the overall trapping efficiency of the settling basin is 40%, find out the frequency of flushing of the settling basin when the sediment concentration is 2000 ppm.

## Short answer

Deposit volume per unit water: vs = (0.40×2.0)/1325 ≈ 6.04×10⁻⁴ m³ deposit/m³ water. Storage 0.1 Vb, water to fill = 165.6 Vb, so flush every 165.6 detention times (e.g., ~27.6 h for 10‑min detention).

## Answer

**Given**: sediment storage $=10\%$ of the basin volume $V_b$; overall trap efficiency $\eta=40\%$; sediment concentration $C=2000$ ppm $=2.0$ kg/m³. Assumption: the settled sediment has a bulk density of $\rho_b=2650\times0.5=1325$ kg/m³ (particle density 2650 kg/m³, packing factor 0.5).

#### Step 1: Volume of sediment trapped per m³ of water
$$
v_s=\frac{\eta\,C}{\rho_b}=\frac{0.40\times2.0}{1325}=6.038 \times 10^{-4}\ \text{m}^3\ \text{of deposit per m}^3\ \text{of water}
$$

#### Step 2: Storage volume
$$
V_{st}=0.10\,V_b
$$

#### Step 3: Volume of water that can pass before the storage is full
$$
V_w=\frac{V_{st}}{v_s}=\frac{0.10\,V_b}{6.038 \times 10^{-4}}=165.6\,V_b
$$

#### Step 4: Frequency of flushing
The water passes through the basin at the rate $Q$, so the time between flushes is
$$
T=\frac{V_w}{Q}=165.6\,\frac{V_b}{Q}=165.6\,t_d
$$
where $t_d=V_b/Q$ is the detention time of the basin.

So the basin should be flushed once after about **165.6 detention periods** (about every 166 times the time that water takes to pass through it). For example, if the detention time is 10 minutes, then $T=1656$ minutes $\approx27.6$ hours (about 0.9 flushes per day); if $t_d=5$ minutes, $T\approx13.8$ hours.

**Answer**: flush every $\approx165.6\,V_b/Q$ (about 166 detention times; e.g. about 27.6 h for a 10-minute detention time).

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. How is the volume of deposit per m^3 of water found?
   A. eta C / rho_b = 0.4 x 2 / 1325 = 6.04e-4 m^3
   B. C / eta = 5 m^3
   C. eta rho_b / C = 265 m^3
   D. C x rho_b = 2650 m^3
   Answer: A. Trapped mass per m^3 of water is eta C = 0.8 kg; dividing by the bulk density 1325 kg/m^3 gives 6.04e-4 m^3. (Key point: Deposit volume per m^3 of water)

2. What bulk density of settled sediment is assumed and why?
   A. 2650 kg/m^3, the particle density
   B. 1325 kg/m^3, particle density times a packing factor of 0.5
   C. 1000 kg/m^3, same as water
   D. 500 kg/m^3
   Answer: B. Deposited sediment contains voids, so 2650 x 0.5 = 1325 kg/m^3 is used. (Key point: Bulk density assumption)

3. How much water can pass before the 10% storage is full?
   A. V_w = 0.10 V_b / 6.04e-4 = 165.6 V_b
   B. V_w = 0.10 V_b x 6.04e-4
   C. V_w = 6.04e-4 V_b
   D. V_w = 0.4 V_b
   Answer: A. Storage volume divided by deposit per unit water volume gives 165.6 V_b. (Key point: Volume of water before storage fills)

4. What is the flushing interval?
   A. T = 165.6 V_b/Q, about 166 detention times
   B. T = Q/(165.6 V_b)
   C. T = 0.1 V_b/Q
   D. T = 1/(0.4 x 2000)
   Answer: A. Dividing the water volume by flow Q gives T = 165.6 t_d; for t_d = 10 min this is about 27.6 h. (Key point: Flushing interval)

## Related in Hydropower Engineering

- [Sediment flushing in settling basin](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Asediment-flushing-types-nepal) — Hydropower Engineering, chapter 5
- [Continuous flushing settling basin, 95% efficiency](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Asettling-basin-continuous-60cumec-velikanov) — Hydropower Engineering, chapter 5
- [Settling basin with Hazen coefficient and sediment depth](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Asettling-basin-hazen-sediment-depth-5000ppm) — Hydropower Engineering, chapter 5
- [Settling basin 40 m³/s, 0.15 mm](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Asettling-basin-40cumec-015mm-w15) — Hydropower Engineering, chapter 5, asked 4×
- [Settling basin trap efficiency (Camp's diagram)](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Asettling-basin-camp-diagram-80cumec) — Hydropower Engineering, chapter 5
- [Settling basin 60 m³/s, 0.2 mm, w = 1.5 cm/s](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Asettling-basin-60cumec-02mm-w15) — Hydropower Engineering, chapter 5, asked 4×

## Related in other subjects

- [Settling basin design for 0.25 mm sediment](https://www.bctengineer.com/question.md?key=semester_6%2Fhydro_power%3Asettling-basin-design-0-25mm) — Hydro Power, chapter 5
- [Ca and Mg concentration, NCH, alkalinity: TH 400 ppm](https://www.bctengineer.com/question.md?key=semester_5%2Fwater_supply_engineering%3Ahardness-bk79) — Water Supply Engineering, chapter 4
- [Q and center frequency; realize −2000/(s²+500s+10⁶)](https://www.bctengineer.com/question.md?key=semester_5%2Ffilter_design%3Atow-thomas-q-center-frequency-realize) — Filter Design, chapter 6
- [High-volume sampler and concentration calculation](https://www.bctengineer.com/question.md?key=semester_7%2Fenvironment_and_pollution_control%3Ahigh-volume-sampler-concentration) — Environment and Pollution Control, chapter 1