# Project portfolio management

ICT Project Management · Chapter 3: Portfolio and Project Management Institutes’ (PMI) Framework

- Asked in: year not given
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/ict_project_management/portfolio-management
- Whole chapter: https://www.bctengineer.com/md/semester_7/ict_project_management/chapter-3

## Question

What do you mean by project portfolio management?

## Short answer

Project portfolio management is centralised management of a collection of projects and programs to achieve strategic objectives. It involves selecting, prioritising, allocating resources, monitoring and terminating projects based on value, risk and strategic fit.

## Answer

**Project portfolio management** is the centralised management of one or more portfolios of projects, programs and related work, so that the organisation's strategic objectives are achieved. A **portfolio** is a collection of projects or programs grouped together to meet strategic business goals; projects need not be related to each other.

#### Purpose
- Select the right projects (do the right things) rather than only manage them well.
- Allocate limited money, people and time to projects with the highest value.
- Balance risk, return and strategic fit.

#### Hierarchy
```text
Organisation strategy
        |
    Portfolio
    /       \
 Program   Program / Projects
   |
Projects
```

#### Key activities
1. **Identify** candidate projects and categorise them.
2. **Evaluate and select** using criteria such as ROI, NPV, payback, strategic alignment, risk and resource availability (scoring models).
3. **Prioritise** and balance the portfolio (short vs long term, high vs low risk).
4. **Allocate resources** across selected projects.
5. **Monitor and review** performance; continue, change or terminate projects.
6. **Report** to senior management.

#### Portfolio, program and project
| Level | Focus |
|---|---|
| Portfolio | Strategic alignment, value |
| Program | Related projects coordinated for benefits |
| Project | Deliver a specific output |

#### Benefits
Better use of resources, links projects to strategy, improved decision making, early termination of poor projects and transparency.

**Example:** A bank's IT portfolio contains a mobile banking app, core system upgrade and cybersecurity project. The management ranks them by strategic value and budget, and delays a low-value project when funds are short.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. A portfolio is:
   A. A single large project
   B. A collection of projects or programs grouped to meet strategic business goals, not necessarily related
   C. Only related projects with one manager
   D. A team of developers
   Answer: B. Projects in a portfolio need not be related; they share strategic goals. (Key point: Portfolio definition)

2. The main purpose of portfolio management is to:
   A. Do projects faster
   B. Reduce the team size
   C. Select the right projects and allocate resources to those with highest value
   D. Write the WBS
   Answer: C. It is about doing the right projects, not only managing them well. (Key point: Purpose)

3. Which criteria are used to evaluate and select projects in a portfolio?
   A. ROI, NPV, payback, strategic alignment, risk and resource availability
   B. Team size only
   C. Colour of logo
   D. Length of the schedule only
   Answer: A. Scoring models use financial, strategic and risk criteria. (Key point: Selection criteria)

4. A program differs from a portfolio in that a program:
   A. Focuses on strategic value of unrelated work
   B. Contains no projects
   C. Coordinates related projects for benefits
   D. Is a single output
   Answer: C. Program: related projects coordinated for benefits; portfolio: strategic alignment and value. (Key point: Portfolio vs program)

## Related in ICT Project Management

- [Project management body of knowledge](https://www.bctengineer.com/question.md?key=semester_7%2Fict_project_management%3Adefine-pmbok) — ICT Project Management, chapter 2
- [General management skills and project management](https://www.bctengineer.com/question.md?key=semester_7%2Fict_project_management%3Ageneral-management-skill) — ICT Project Management, chapter 2
- [Define project management](https://www.bctengineer.com/question.md?key=semester_7%2Fict_project_management%3Adefine-project-management) — ICT Project Management, chapter 4
- [System view of project management](https://www.bctengineer.com/question.md?key=semester_7%2Fict_project_management%3Asystem-view-three-parts) — ICT Project Management, chapter 5
- [Project management methodology](https://www.bctengineer.com/question.md?key=semester_7%2Fict_project_management%3Apm-methodology) — ICT Project Management, chapter 7
- [Project management information system](https://www.bctengineer.com/question.md?key=semester_7%2Fict_project_management%3Apmis) — ICT Project Management, chapter 7

## Related in other subjects

- [Function of project management in Nepal](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Acpm-function-nepal) — Construction Management, chapter 1
- [Types of projects; effect of project management](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aproject-types-effect-of-management) — Project Engineering, chapter 1
- [Project vs traditional management; external environment](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aproject-vs-traditional-mgmt-external-env) — Project Engineering, chapter 1
- [Project management and its functions](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aproject-management-and-functions) — Project Engineering, chapter 1