# Combined plant layouts, performance and economics

Power Plant Equipment · Chapter 8: Combined Power Plant

- Asked in: 2078 Bhadra, 2+4+2 marks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/power_plant_equipment/combined-layout-economics
- Whole chapter: https://www.bctengineer.com/md/semester_7/power_plant_equipment/chapter-8

## Question

What is combined Power plant? Sketch the layout with necessary labels, for various types of combined power plant. Discuss the performance and economics of combined power plants.

## Short answer

A combined plant runs a topping and bottoming cycle in series, typically gas turbine (Brayton) exhausting at 450-600 C into a steam Rankine cycle, giving 50-60% efficiency. Layouts are HRSG, exhaust as combustion air in a fired boiler, and exhaust feed water heating. Economics: low capital cost per kW, short construction, quick start, good load following, less cooling water and space.

## Answer

#### What is a combined power plant

A **combined power plant** (combined cycle plant) uses two thermodynamic cycles in series, so that the heat rejected by the first (**topping**) cycle becomes the heat input of the second (**bottoming**) cycle. The most common is the **gas turbine - steam turbine combined cycle**: a gas turbine (Brayton cycle, heat added at 1100-1500 C) exhausts at 450-600 C, and this exhaust raises steam for a steam turbine (Rankine cycle, heat rejected at 30-45 C). Overall efficiency of 50-60% is achieved, compared with 30-40% for each plant alone.

#### Layouts of various types

#### Design 1: Unfired (or supplementary fired) heat recovery boiler (HRSG)

```text
      air 1                fuel
      |                     |
      v                     v
   +------+     2     +-----------+   3   +------+
   | Comp |---------->| Combustion|------>|  GT  |===> G1
   +------+           |  chamber  |       +------+
      ||              +-----------+        ||  |
      ++=============== shaft =============++  | 4 hot exhaust
                                               v   (~500-600 C)
   stack <-- 5 --+-------------------------------+
                 |  HRSG (economiser,            |
                 |  evaporator, superheater)     |
                 +-------------------------------+
                     ^ d                  | a steam
                     |                    v
                 +------+             +------+
                 | Pump |             |  ST  |===> G2
                 +------+             +------+
                     ^ c                  | b
                     |   +-----------+    |
                     +---| Condenser |<---+
                         +-----------+
```

The GT exhaust raises all the steam in a heat recovery boiler. A duct burner may add supplementary fuel. This is the most common modern design (efficiency 50-60%).

#### Design 2: Exhaust used as combustion air in a fired boiler

```text
  air      fuel
   |1        |
   v         v
  [C]--2-->[CC]--3-->[GT]==> G1
                      | 4 hot exhaust (~15% O2)
                      v   used as combustion air
         fuel --> +-----------------+  a  +----+
                  | Fired steam     |---->| ST |==> G2
       stack <----| boiler          |     +----+
                  +-----------------+       | b
                     ^ d                    v
                     |  +------+  c  +-----------+
                     +--| Pump |<----| Condenser |
                        +------+     +-----------+
```

The hot, oxygen-rich exhaust replaces the air preheater and forced draft air of a conventional fired boiler. Steam turbine output is large compared to gas turbine output.

#### Design 3: Exhaust heats the feed water

```text
  air       fuel
   | 1        |
   v          v
  [C]--2-->[ CC ]--3-->[GT]==> G1
   ||                   |  4  exhaust gas
   ++=====shaft=========+  v
          +--------------------------+
 stack <-5| Feed water heater (gas   |
          | to water heat exchanger) |
          +--------------------------+
             ^ d             | e  hot feed water
             |               v
          +------+     +----------+  a  +----+
          | Pump |     |  Steam   |---->| ST |==> G2
          +------+     |  boiler  |     +----+
             ^ c       +----------+       | b
             |              ^ fuel        v
             |           +-----------------+
             +-----------|    Condenser    |
                         +-----------------+
```

The exhaust heats the condensate/feed water of a conventional steam plant, replacing bled-steam feed heaters; the boiler supplies the rest of the heat.

#### Performance and economics

Performance of a combined plant is judged by its **overall thermal efficiency** (or heat rate):

$$
\eta_{cc} = \frac{W_{GT} + W_{ST}}{Q_{GT} + Q_{sf}}
$$

where $W_{GT}$, $W_{ST}$ are net outputs of gas and steam units, $Q_{GT}$ is fuel heat to the gas turbine and $Q_{sf}$ is any supplementary fuel heat.

For an unfired HRSG with no losses, all heat rejected by the gas turbine, $Q_{GT}(1-\eta_{GT})$, goes to the steam cycle, so

$$
\eta_{cc} = \eta_{GT} + \eta_{ST} - \eta_{GT}\,\eta_{ST}
$$

Example: $\eta_{GT} = 0.35$, $\eta_{ST} = 0.32$ gives $\eta_{cc} = 0.35 + 0.32 - 0.112 = 0.558$ (55.8%).

If the HRSG (heat recovery) effectiveness is $\eta_{HR}$ (part of exhaust heat lost to stack), $\eta_{cc} = \eta_{GT} + \eta_{HR}\,\eta_{ST}(1 - \eta_{GT})$.

Other performance figures: **heat rate** = 3600 / $\eta_{cc}$ kJ/kWh (about 6000-7000 kJ/kWh), **power ratio** $W_{ST}/W_{GT}$ (about 0.5), part-load efficiency and stack temperature.

Economics:

- **Capital cost** per kW is lower than for coal or nuclear plants (the gas turbine is factory made, the HRSG is simple, and there is no coal or ash handling); it is often about half that of a coal plant, or less.
- **Construction time** 2-3 years; phased construction earns revenue early.
- **Fuel cost** is the largest cost item; high efficiency reduces it, but gas/oil price decides the cost of energy.
- **Operating and maintenance cost** is moderate; fewer staff, but GT hot parts need regular overhaul.
- **Cost of electricity** is lowest for base and intermediate load where cheap natural gas is available; supplementary firing gives cheap peaking capacity.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. How is overall thermal efficiency of a combined plant defined?
   A. (W_GT + W_ST) / (Q_GT + Q_sf)
   B. W_ST / W_GT
   C. Q_GT / W_GT
   D. W_GT / W_ST
   Answer: A. Total net output divided by the total fuel heat, including any supplementary firing. (Key point: Performance measure)

2. How is heat rate related to efficiency?
   A. Heat rate = 3600 / eta_cc kJ/kWh
   B. Heat rate = eta_cc x 3600
   C. Heat rate = 1 / 3600 eta
   D. Heat rate = eta_cc
   Answer: A. One kWh is 3600 kJ, so fuel energy per kWh is 3600/eta. (Key point: Heat rate)

3. How does the capital cost per kW of a combined plant compare with a coal plant?
   A. About 60-70 % of coal plant, since no coal or ash handling is needed
   B. Double the coal plant
   C. Same as nuclear
   D. Ten times greater
   Answer: A. Gas turbines are factory made, HRSG is simple and there is no coal/ash handling. (Key point: Capital cost)

4. What is the largest cost item of a combined plant and what decides cost of energy?
   A. Fuel; gas/oil price
   B. Labour; wage rate
   C. Cooling water; river flow
   D. Land; plot price
   Answer: A. Fuel is the largest cost; high efficiency reduces it, but fuel price determines electricity cost. (Key point: Largest cost item)

## Related in Power Plant Equipment

- [Working and performance of combined plant](https://www.bctengineer.com/question.md?key=semester_7%2Fpower_plant_equipment%3Acombined-working-performance) — Power Plant Equipment, chapter 8
- [Combined plant introduction and popular designs](https://www.bctengineer.com/question.md?key=semester_7%2Fpower_plant_equipment%3Acombined-intro-designs) — Power Plant Equipment, chapter 8
- [Advantages of combined power plant](https://www.bctengineer.com/question.md?key=semester_7%2Fpower_plant_equipment%3Acombined-advantages) — Power Plant Equipment, chapter 8
- [Methods to utilize waste heat in combined plants](https://www.bctengineer.com/question.md?key=semester_7%2Fpower_plant_equipment%3Acombined-waste-heat-methods) — Power Plant Equipment, chapter 8, asked 2×
- [Combined plant heating feed water with exhaust](https://www.bctengineer.com/question.md?key=semester_7%2Fpower_plant_equipment%3Acombined-feedwater-layout) — Power Plant Equipment, chapter 8, asked 2×
- [Layout of diesel power plant](https://www.bctengineer.com/question.md?key=semester_7%2Fpower_plant_equipment%3Adiesel-plant-layout) — Power Plant Equipment, chapter 5, asked 3×

## Related in other subjects

- [RoR plant layouts; storage over RoR](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Aror-layouts-storage-importance) — Hydropower Engineering, chapter 2
- [Importance of storage plants; pumped storage layout](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Astorage-importance-pump-storage-layout) — Hydropower Engineering, chapter 2
- [Operational characteristics of combined cycle plant](https://www.bctengineer.com/question.md?key=semester_8%2Fpower_plant_design%3Accgt-operational-characteristics) — Power Plant Design, chapter 1
- [Development cycle; storage plant layout](https://www.bctengineer.com/question.md?key=semester_7%2Fhydropower_engineering%3Adev-cycle-storage-layout) — Hydropower Engineering, chapter 2