# Appraisal vs formulation; formulation techniques

Project Engineering · Chapter 2: Project Appraisal and Project Formulation

- Asked in: 2076 Asoj, 2+4 marks
- Video: [PROJECT APPRAISAL](https://www.youtube.com/watch?v=LuK0PiD0EsM) — COMMERCE HIGHLIGHTS
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/project_engineering/appraisal-vs-formulation-techniques
- Whole chapter: https://www.bctengineer.com/md/semester_7/project_engineering/chapter-2

## Question

Differentiate between project appraisal and project formulation. Explain in detail the techniques of project formulation.

## Short answer

Project formulation develops an idea into a detailed plan; appraisal independently assesses that plan to approve, modify or reject it. Formulation is done by the promoter before appraisal by banks or authorities. Formulation techniques: feasibility, cost-benefit, input, market, technical, financial, environmental, social, SWOT, sensitivity/risk analysis, and logical framework/ToR preparation.

## Answer

| Basis | Project formulation | Project appraisal |
|---|---|---|
| Meaning | Developing the idea into a detailed project plan | Critical assessment of the formulated project |
| Purpose | Prepare the project | Decide whether to accept it |
| Done by | Project promoter or planner | Independent agency, bank or approving authority |
| Stage | Before appraisal | After formulation, before approval |
| Output | Project report with design, cost, ToR | Recommendation to approve, modify or reject |
| Nature | Creative, constructive | Evaluative, analytical |

#### Techniques of project formulation

| Technique | Description |
|---|---|
| Feasibility analysis | Checks that the project is possible technically, economically, financially, environmentally and socially |
| Cost-benefit analysis (CBA) | Compares all costs and benefits in monetary terms (B/C ratio, NPV, IRR) |
| Input analysis | Studies the resources needed: materials, manpower, equipment, utilities, finance, and their availability and cost |
| Market analysis | Estimates demand, supply and price |
| Technical analysis | Selects technology, capacity, location and layout |
| Financial analysis | Cost, funding, cash flow, profitability |
| Environmental analysis | Impacts and mitigation (IEE/EIA) |
| Social analysis / socio-economic survey | Effects on people, participation |
| SWOT analysis | Strengths, weaknesses, opportunities and threats |
| Sensitivity and risk analysis | Effect of changes in cost, benefit or time on viability |
| Logical framework / ToR preparation | Structures objectives, outputs, indicators and assumptions |

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. What is the purpose of formulation compared with appraisal?
   A. Both only prepare
   B. Formulation prepares the project; appraisal decides whether to accept it
   C. Both only decide
   D. Formulation decides; appraisal prepares
   Answer: B. Formulation develops the plan; appraisal critically assesses it. (Key point: Formulation vs appraisal purpose)

2. Who typically does appraisal?
   A. Supplier
   B. Independent agency, bank or approving authority
   C. Contractor
   D. Promoter or planner
   Answer: B. Promoters formulate; independent bodies appraise. (Key point: Who does each)

3. Where does appraisal come in the sequence?
   A. After formulation, before approval
   B. After approval
   C. After completion
   D. Before formulation
   Answer: A. Appraisal follows formulation and precedes approval. (Key point: Stage)

4. Which technique studies materials, manpower, equipment, utilities and finance and their availability and cost?
   A. SWOT
   B. Feasibility analysis
   C. Market analysis
   D. Input analysis
   Answer: D. That is input analysis. (Key point: Input analysis technique)

## Close variants set in other exams

- [Necessity of appraisal; formulation techniques](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aappraisal-necessity-formulation-techniques) — Project Engineering, chapter 2, asked 2×

## Related in Project Engineering

- [Techniques of project formulation](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Atechniques-project-formulation) — Project Engineering, chapter 2, asked 3×
- [Formulation and appraisal; proposal procedure](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aformulation-appraisal-define-procedure) — Project Engineering, chapter 2
- [Formulation, appraisal, proposal procedure, CBA drawbacks](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aformulation-appraisal-cba-drawbacks) — Project Engineering, chapter 2
- [Need of formulation; techniques for ToR](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aformulation-need-techniques-tor) — Project Engineering, chapter 2
- [Necessity and aspects of project appraisal](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Awhy-appraisal-necessary-aspects) — Project Engineering, chapter 2, asked 4×
- [Appraisal aspects of a hydropower project](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aappraisal-aspects-hydropower) — Project Engineering, chapter 2, asked 4×

## Related in other subjects

- [Project life cycles in detail](https://www.bctengineer.com/question.md?key=semester_7%2Fict_project_management%3Aproject-life-cycles) — ICT Project Management, chapter 4
- [Detail estimate report for sewerage project](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aestimate-report-sewerage) — Estimating and Costing, chapter 5, asked 2×