title: "Bar chart of irrigation project with milestones"
subject: "Project Engineering"
chapter: 3
key: "semester_7/project_engineering:bar-chart-irrigation-milestones"
source: https://www.bctengineer.com/q/semester_7/project_engineering/bar-chart-irrigation-milestones
site: BCT Engineering
---

# Bar chart of irrigation project with milestones

Project Engineering · Chapter 3: Project Planning and Scheduling

- Asked in: 2075 Chaitra, 7 marks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/project_engineering/bar-chart-irrigation-milestones
- Whole chapter: https://www.bctengineer.com/md/semester_7/project_engineering/chapter-3

## Question

Prepare a bar chart of an irrigation project mentioning at least 6 activities. Also show the milestones in a chart.

## Short answer

An irrigation project bar chart includes activities: survey and design (2 months), land acquisition (3), headworks (6), main canal earthwork (5), canal lining (4), canal structures (6), field channels (4), testing and handover (1). Key milestones: design approved (month 2), land ready (4), headworks complete (9), main canal complete (12), field channels complete (15), handover (16). Total project 16 months.

## Answer

**Assumption:** a small irrigation scheme (weir, main canal and field channels) of 16 months.

#### Activities and durations

| Code | Activity | Start (month) | Duration (months) |
|---|---|---|---|
| A | Survey and design | 0 | 2 |
| B | Land acquisition and site clearing | 1 | 3 |
| C | Headworks (weir and intake) | 3 | 6 |
| D | Main canal earthwork | 4 | 5 |
| E | Canal lining | 8 | 4 |
| F | Canal structures (culverts, outlets) | 6 | 6 |
| G | Field channels and distribution | 11 | 4 |
| H | Testing and handover | 15 | 1 |

#### Bar chart (months)

```text
                       0   4   8   12  16  (month)
                      +----------------
A Survey & design     |##              
B Land acquisition    | ###            
C Headworks (weir)    |   ######       
D Main canal earthwork|    #####       
E Canal lining        |        ####    
F Canal structures    |      ######    
G Field channels      |           #### 
H Testing, handover   |               #
                      +----------------
```

#### Milestone chart

Milestones are key events that mark completion of a major stage; `*` shows the planned date.

```text
                       0   4   8   12  16 (month)
                      +----------------
M1 Design approved    | *
M2 Land ready         |   *
M3 Headworks done     |        *
M4 Main canal done    |           *
M5 Distribution done  |              *
M6 Handover           |               *
                      +----------------
```

| Milestone | Event | Month |
|---|---|---|
| M1 | Design approved | 2 |
| M2 | Land ready | 4 |
| M3 | Headworks complete | 9 |
| M4 | Main canal complete | 12 |
| M5 | Field channels complete | 15 |
| M6 | Handover | 16 |

The project is finished in **16 months**. Land acquisition must end by month 4 and design approval by month 2; these early milestones are the main control points.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. In the irrigation example, what is the total duration?
   A. 16 months
   B. 15 months
   C. 12 months
   D. 9 months
   Answer: A. Testing and handover starts at month 15 and lasts 1 month, so it ends at month 16. (Key point: Project duration)

2. When does headworks (weir and intake) start and finish?
   A. Start month 0, finish month 6
   B. Start month 4, finish month 9
   C. Start month 3, finish month 9
   D. Start month 8, finish month 12
   Answer: C. Start 3 plus duration 6 gives month 9, matching milestone M3. (Key point: Headworks)

3. What is a milestone in this chart?
   A. A task lasting several months
   B. A key event marking completion of a major stage
   C. A resource bar
   D. A dummy activity
   Answer: B. Milestones such as design approved or headworks done are zero-duration control points. (Key point: Milestones)

4. Which are called the main early control points?
   A. Handover at month 16 and canal lining
   B. Field channels and testing
   C. Weir and lining
   D. Design approval by month 2 and land ready by month 4
   Answer: D. Early milestones M1 and M2 control the start of later works. (Key point: Control points)

## Related in Project Engineering

- [Planning, scheduling; linked bar chart](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aplanning-scheduling-linked-bar-chart) — Project Engineering, chapter 3
- [Bar chart advantages and limitations](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Abar-chart-advantages-limitations) — Project Engineering, chapter 3, asked 2×
- [Planning in dynamic environment; linked bar chart](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aplanning-necessary-dynamic-linked-bar) — Project Engineering, chapter 3
- [Planning need, tools, bar chart limitations](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aplanning-necessary-tools-bar-chart-limits) — Project Engineering, chapter 3
- [When to use bar chart, CPM, PERT](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Abar-chart-cpm-pert-situations) — Project Engineering, chapter 3
- [Gantt, link bar chart, milestone chart](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Agantt-linked-bar-milestone-chart) — Project Engineering, chapter 3

## Related in other subjects

- [TCTO numerical with time-cost chart (five activities)](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Atcto-2079-jestha) — Construction Management, chapter 2
- [Bar chart vs CPM/PERT as planning tool](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Aplanning-tool-choice) — Construction Management, chapter 2, asked 3×
- [Chart vs table; bar vs pie graph](https://www.bctengineer.com/question.md?key=semester_5%2Fcommunication_english%3Adifferences-chart-table-bar-pie) — Communication English, chapter 4
- [Define project; irrigation project estimate](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aproject-irrigation-estimate) — Estimating and Costing, chapter 5, asked 4×