title: "CPM network, 12 activities (A=8 to L=3)"
subject: "Project Engineering"
chapter: 3
key: "semester_7/project_engineering:cpm-network-twelve-act-b66"
source: https://www.bctengineer.com/q/semester_7/project_engineering/cpm-network-twelve-act-b66
site: BCT Engineering
---

# CPM network, 12 activities (A=8 to L=3)

Project Engineering · Chapter 3: Project Planning and Scheduling

- Asked in: 2066 Bhadra (old course), 16 marks
- Video: [Use forward and backward pass to determine project duration and critical path](https://www.youtube.com/watch?v=4oDLMs11Exs) — Engineer4Free
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/project_engineering/cpm-network-twelve-act-b66
- Whole chapter: https://www.bctengineer.com/md/semester_7/project_engineering/chapter-3

## Question

A project has the following schedule. Construct the network diagram and compute EST, EFT, LST, LFT, TF, FF, IF and interfering floats for each activity and find the critical path.

| Activity | Time | Predecessor |
|---|---|---|
| A | 8 | None |
| B | 2 | None |
| C | 1 | A |
| D | 9 | B |
| E | 4 | B |
| F | 5 | C, D |
| G | 6 | E |
| H | 3 | E |
| I | 3 | G, H |
| J | 5 | H |
| K | 2 | I, J |
| L | 3 | E, F |

## Short answer

Draw the activity-on-arrow network with dummies, then do forward pass for EST/EFT and backward pass for LST/LFT. Floats: TF=LST-EST, FF=min successor EST minus EFT, IntF=TF-FF, IndF=max(0, min succ EST minus max pred LFT minus D). Project duration is 19 time units; critical path B-D-F-L.

## Answer

IF is taken as independent float.

Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.

#### Network diagram (activity-on-arrow)

Each activity is an arrow with its duration in brackets (time units). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.

```text
(1) --A(8)--> (2)
(1) --B(2)--> (3)
(2) --C(1)--> (4)
(3) --D(9)--> (4)
(3) --E(4)--> (5)
(4) --F(5)--> (7)
(5) --H(3)--> (6)
(5) - - dummy - -> (7)
(5) --G(6)--> (8)
(6) - - dummy - -> (8)
(6) --J(5)--> (9)
(7) --L(3)--> (10)
(8) --I(3)--> (9)
(9) --K(2)--> (10)
```

The network has 10 events and 2 dummy activities. Start event is (1) and the end event is (10).

#### Forward pass (EST and EFT)

Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.

- A: EST = 0; EFT = 0 + 8 = 8
- B: EST = 0; EFT = 0 + 2 = 2
- D: EST = EFT of B = 2; EFT = 2 + 9 = 11
- E: EST = EFT of B = 2; EFT = 2 + 4 = 6
- G: EST = EFT of E = 6; EFT = 6 + 6 = 12
- H: EST = EFT of E = 6; EFT = 6 + 3 = 9
- C: EST = EFT of A = 8; EFT = 8 + 1 = 9
- J: EST = EFT of H = 9; EFT = 9 + 5 = 14
- F: EST = max(C:9, D:11) = 11; EFT = 11 + 5 = 16
- I: EST = max(G:12, H:9) = 12; EFT = 12 + 3 = 15
- K: EST = max(I:15, J:14) = 15; EFT = 15 + 2 = 17
- L: EST = max(E:6, F:16) = 16; EFT = 16 + 3 = 19

Project duration = largest EFT = **19 time units**.

#### Backward pass (LFT and LST)

Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.

- L: LFT = project duration = 19; LST = 19 - 3 = 16
- K: LFT = project duration = 19; LST = 19 - 2 = 17
- I: LFT = LST of K = 17; LST = 17 - 3 = 14
- F: LFT = LST of L = 16; LST = 16 - 5 = 11
- J: LFT = LST of K = 17; LST = 17 - 5 = 12
- C: LFT = LST of F = 11; LST = 11 - 1 = 10
- H: LFT = min(I:14, J:12) = 12; LST = 12 - 3 = 9
- G: LFT = LST of I = 14; LST = 14 - 6 = 8
- E: LFT = min(G:8, H:9, L:16) = 8; LST = 8 - 4 = 4
- D: LFT = LST of F = 11; LST = 11 - 9 = 2
- B: LFT = min(D:2, E:4) = 2; LST = 2 - 2 = 0
- A: LFT = LST of C = 10; LST = 10 - 8 = 2

#### Floats

- **Total float** $TF = LST - EST = LFT - EFT$
- **Free float** $FF = \min(\text{EST of successors}) - EFT$
- **Interfering float** $IntF = TF - FF$
- **Independent float** $IndF = \max\left(0,\ \min(\text{EST of successors}) - \max(\text{LFT of predecessors}) - D\right)$

#### Result table

| Activity | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F |
|---|---|---|---|---|---|---|---|---|---|
| A | 8 | 0 | 8 | 2 | 10 | 2 | 0 | 2 | 0 |
| B | 2 | 0 | 2 | 0 | 2 | 0 | 0 | 0 | 0 |
| C | 1 | 8 | 9 | 10 | 11 | 2 | 2 | 0 | 0 |
| D | 9 | 2 | 11 | 2 | 11 | 0 | 0 | 0 | 0 |
| E | 4 | 2 | 6 | 4 | 8 | 2 | 0 | 2 | 0 |
| F | 5 | 11 | 16 | 11 | 16 | 0 | 0 | 0 | 0 |
| G | 6 | 6 | 12 | 8 | 14 | 2 | 0 | 2 | 0 |
| H | 3 | 6 | 9 | 9 | 12 | 3 | 0 | 3 | 0 |
| I | 3 | 12 | 15 | 14 | 17 | 2 | 0 | 2 | 0 |
| J | 5 | 9 | 14 | 12 | 17 | 3 | 1 | 2 | 0 |
| K | 2 | 15 | 17 | 17 | 19 | 2 | 2 | 0 | 0 |
| L | 3 | 16 | 19 | 16 | 19 | 0 | 0 | 0 | 0 |

Event times (TE from the forward pass, TL from the backward pass):

| Event | TE (earliest) | TL (latest) | Slack |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 8 | 10 | 2 |
| 3 | 2 | 2 | 0 |
| 4 | 11 | 11 | 0 |
| 5 | 6 | 8 | 2 |
| 6 | 9 | 12 | 3 |
| 7 | 16 | 16 | 0 |
| 8 | 12 | 14 | 2 |
| 9 | 15 | 17 | 2 |
| 10 | 19 | 19 | 0 |

#### Critical path and project duration

- Critical activities (TF = 0): B, D, F, L
- Critical path: B - D - F - L (= 2+9+5+3 = 19 time units)

**Answer: project duration = 19 time units; critical path = B - D - F - L**

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. What are the critical path and project duration?
   A. B-D-F-L, 19
   B. A-C-F-L, 17
   C. B-E-H-J-K, 16
   D. B-E-G-I-K, 17
   Answer: A. L ends at 19 and B, D, F, L have TF = 0: 2+9+5+3 = 19. (Key point: Critical path)

2. EST of F is 11. Why?
   A. It is 8 from A
   B. It is the larger of EFT of C (9) and EFT of D (11)
   C. It equals EFT of C
   D. It equals EFT of E
   Answer: B. F follows C and D, so EST = max(9, 11) = 11. (Key point: EST of F)

3. LFT of E is 8. Where does this come from?
   A. Project duration minus 11
   B. Smallest LST of successors G(8), H(9), L(16)
   C. Largest LST of successors
   D. EFT of B
   Answer: B. LFT is the smallest LST of the successors: min(8, 9, 16) = 8. (Key point: LFT of E)

4. J has EFT 14 and its successor K has EST 15. What is FF of J, and what is TF?
   A. FF = 3, TF = 1
   B. FF = 0, TF = 3
   C. FF = 1, TF = 3
   D. FF = 1, TF = 1
   Answer: C. FF = 15 - 14 = 1; TF = LST - EST = 12 - 9 = 3. (Key point: Free float of J)

## Related in Project Engineering

- [CPM network, 12 activities (A=10 to L=8)](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Acpm-network-twelve-act-as67) — Project Engineering, chapter 3
- [CPM network, 10 activities (A=4 to J=9)](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Acpm-network-ten-act-as70) — Project Engineering, chapter 3
- [CPM network, 10 activities (A=10 to J=4)](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Acpm-network-ten-act-k79) — Project Engineering, chapter 3
- [CPM network, 9 activities (A=3 to I=1)](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Acpm-network-nine-act-b82) — Project Engineering, chapter 3, asked 5×
- [CPM network, 9 activities (A=5 to I=2)](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Acpm-network-nine-act-a75) — Project Engineering, chapter 3, asked 5×
- [CPM network, 13 activities (A to M)](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Acpm-network-thirteen-act-k82) — Project Engineering, chapter 3, asked 5×

## Related in other subjects

- [CPM schedule, critical path and float](https://www.bctengineer.com/question.md?key=semester_6%2Findustrial_engineering_and_management%3Acpm-network-critical-path-float) — Industrial Engineering and Management, chapter 3
- [TCTO numerical: crashing critical path, Rs 30/day](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Atcto-2069-bhadra) — Construction Management, chapter 2