title: "Gantt chart; resource allocation and smoothing"
subject: "Project Engineering"
chapter: 3
key: "semester_7/project_engineering:gantt-chart-resource-allocation-smoothing"
source: https://www.bctengineer.com/q/semester_7/project_engineering/gantt-chart-resource-allocation-smoothing
site: BCT Engineering
---

# Gantt chart; resource allocation and smoothing

Project Engineering · Chapter 3: Project Planning and Scheduling

- Asked in: 2068 Baisakh (old course), 8 marks
- Video: [Resource Leveling versus Resource Smoothing - Key Project Management Concepts from the PMBOK](https://www.youtube.com/watch?v=NnYhXHcn2zs) — David McLachlan
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/project_engineering/gantt-chart-resource-allocation-smoothing
- Whole chapter: https://www.bctengineer.com/md/semester_7/project_engineering/chapter-3

## Question

What is a Gantt chart? Discuss resource allocation and smoothing.

## Short answer

A Gantt chart is a bar chart with each activity as a horizontal bar filled in as work progresses, so planned and actual progress are compared. Resource allocation assigns manpower, machines and materials to activities. Smoothing shifts non-critical activities within float to level demand without changing project duration or critical path; limited resource allocation may delay activities and extend duration.

## Answer

#### Gantt chart

A **Gantt chart** is a bar chart in which each activity is a horizontal bar on a time scale; the bar is filled in as work progresses, so that planned and actual progress are seen together. It is used for scheduling and monitoring.

Example (days): A excavation (3 days, 4 men), C foundation (3 days, 2 men, after A) and B fencing and store (2 days, 2 men, independent). `=` shows work done up to the status at the end of day 3.

```text
                  0 2 4 6 (day)
                 +------
A Excavation     |===|  
C Foundation     |   ###
B Fencing, store |== |  
                 +------
                     ^ status (day 3)
```

#### Resource allocation

**Resource allocation** is the assignment of the available manpower, machines and materials to the activities of the schedule. The daily requirement of every activity (early start schedule) is added to get a **resource aggregation chart**, drawn as a **resource histogram**. If the demand is uneven or higher than the supply, the schedule is adjusted. Two cases occur:

1. **Resource levelling or smoothing (time-limited)** - the project duration is fixed; activities are shifted within their float to get a smooth demand.
2. **Limited resource allocation (resource-limited)** - the amount of resource available is fixed; activities are delayed, even beyond their float, so the duration may increase.

#### Resource smoothing

**Smoothing** is the adjustment of non-critical activities within their total float to remove peaks and valleys of the histogram without changing the project duration or the critical path.

In the example the critical chain is A-C (6 days); B has a float of 4 days. Early start histogram (B on days 1-2):

```text
  6 |# #         
  5 |# #         
  4 |# # #       
  3 |# # #       
  2 |# # # # # # 
  1 |# # # # # # 
    +------------
     1 2 3 4 5 6  day
     6 6 4 2 2 2  men
```

Peak = 6 men. Starting B on day 4 (inside its float) gives:

```text
  4 |# # # # #   
  3 |# # # # #   
  2 |# # # # # # 
  1 |# # # # # # 
    +------------
     1 2 3 4 5 6  day
     4 4 4 4 4 2  men
```

The peak falls from 6 to 4 men; total man-days (22) and the completion time (6 days) are unchanged. Benefits: steady employment, less hiring and firing, better use of equipment.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. What is a resource histogram?
   A. A chart of activity dependence
   B. A chart of milestone dates
   C. A chart of the daily resource requirement added up from all activities
   D. A chart of cost per unit
   Answer: C. Adding each activity's daily need gives the aggregation drawn as a histogram. (Key point: Resource histogram)

2. What is fixed in resource levelling?
   A. The project duration
   B. The resource available
   C. The cost
   D. The number of activities
   Answer: A. Levelling is time-limited: activities shift within float; limited resource allocation fixes the resource instead. (Key point: Levelling vs limited)

3. How does smoothing change the schedule?
   A. Critical activities are delayed
   B. Non-critical activities move within total float without changing duration or critical path
   C. Project duration is increased
   D. Resources are added to peaks
   Answer: B. Smoothing uses float only, so the completion time remains the same. (Key point: Smoothing)

4. In the example, what happens when B is started on day 4?
   A. Peak rises to 8 men
   B. Completion becomes 8 days
   C. Total man-days change from 22 to 20
   D. Peak falls from 6 to 4 men with the 6-day completion unchanged
   Answer: D. B has 4 days float; shifting it levels demand while total man-days (22) and duration are unchanged. (Key point: Example)

## Related in Project Engineering

- [Short note: Resource allocation and smoothing](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aresource-allocation-smoothing-note) — Project Engineering, chapter 3, asked 4×
- [Limited resource allocation and smoothing](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Alimited-resource-allocation-smoothing-application) — Project Engineering, chapter 3
- [Resource schedule; leveling vs smoothing](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aresource-schedule-leveling-smoothing) — Project Engineering, chapter 3, asked 2×
- [Resource leveling and smoothing](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aresource-leveling-smoothing-wbs-4level) — Project Engineering, chapter 3
- [Resource histogram, leveling, limited allocation, WBS](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aresource-terms-histogram-wbs) — Project Engineering, chapter 3
- [Gantt chart with advantages](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Agantt-chart-draw-advantages) — Project Engineering, chapter 3

## Related in other subjects

- [Gantt chart for loading and scheduling](https://www.bctengineer.com/question.md?key=semester_6%2Findustrial_engineering_and_management%3Agantt-chart-loading-and-progress) — Industrial Engineering and Management, chapter 3
- [CPU criteria; RR Gantt and times](https://www.bctengineer.com/question.md?key=semester_6%2Foperating_system%3Acpu-criteria-rr-gantt) — Operating System, chapter 2
- [FCFS, SJF, Priority, RR Gantt; max AWT](https://www.bctengineer.com/question.md?key=semester_6%2Foperating_system%3Ascheduling-gantt-fcfs-sjf-priority-rr-q2) — Operating System, chapter 2
- [Preemptive priority and SRTF Gantt](https://www.bctengineer.com/question.md?key=semester_6%2Foperating_system%3Apreemptive-priority-srtf-gantt) — Operating System, chapter 2