# Quality; QA vs QC; factors in Nepal

Project Engineering · Chapter 4: Project Implementation and Controlling

- Asked in: 2079 Bhadra, 2+2+2 marks
- Video: [QA & QC | 'Quality Assurance (QA)' Vs 'Quality Control' (QC) in Explained in Detail (In Hindi)](https://www.youtube.com/watch?v=fCCyeaL8ROI) — AYT India Academy
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/project_engineering/quality-qa-qc-nepal-factors
- Whole chapter: https://www.bctengineer.com/md/semester_7/project_engineering/chapter-4

## Question

Define quality. Distinguish between Quality Assurance and Quality Control. List out different factors disturbing the quality of projects in Nepal.

## Answer

#### Quality

**Quality** is the degree to which a set of inherent characteristics of a product or service meets the requirements: the specified standards, the client's needs and fitness for use. In construction, quality means the work follows the drawings, specifications and codes and is safe, durable and functional.

#### Quality assurance and quality control

| Basis | Quality assurance (QA) | Quality control (QC) |
|---|---|---|
| Meaning | Planned system of activities to give confidence that quality requirements will be met | Operational techniques to check that the work meets the requirement |
| Focus | Process; prevents defects | Product; detects defects |
| Nature | Proactive | Reactive |
| When | Before and during the work | During and after the work |
| Responsibility | Whole organisation and management | Site and testing team |
| Tools | Quality plan, audits, procedures, training | Inspection, tests (cube test, slump, compaction), checklists |
| Example | Setting the method statement and approving materials | Testing concrete cubes at 7 and 28 days |

#### Factors disturbing the quality of projects in Nepal

1. Poor and incomplete design, drawings and estimates; weak site investigation.
2. Lowest-bid contractors with low capacity, and unrealistic bid prices.
3. Lack of skilled labour, supervisors and trained engineers.
4. Weak supervision and monitoring by the client or consultant.
5. Poor quality of materials (cement, aggregate, steel) and lack of testing labs near site.
6. Delay in payment and shortage of funds, causing shortcuts.
7. Corruption, commission and political interference.
8. Difficult geography, monsoon and poor access to remote sites.
9. Frequent change of design and variation orders.
10. Low use of quality standards, such as the Nepal Building Code and Nepal Standards, and weak penalties.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. In construction, quality means:
   A. The most expensive materials used
   B. The degree to which characteristics meet requirements: drawings, specifications, codes and fitness for use
   C. Finishing the work as early as possible
   D. Only passing the final cube test
   Answer: B. Quality is meeting the specified requirements and client needs, making the work safe, durable and functional. (Key point: Definition of quality)

2. What best describes quality assurance compared with quality control?
   A. QA is product-focused and detects defects
   B. QA is process-focused, proactive and prevents defects
   C. QA is done only after completion
   D. QA is only the site testing team's task
   Answer: B. QA is a planned process system that prevents defects; QC inspects and tests the product to detect them. (Key point: QA focus)

3. Which is a quality control activity?
   A. Preparing a quality plan
   B. Training staff
   C. Testing concrete cubes at 7 and 28 days
   D. Auditing company procedures
   Answer: C. Cube testing checks the product, so it is QC; plans, training and audits are QA tools. (Key point: QC example)

4. Which is listed as a factor disturbing project quality in Nepal?
   A. Over-supply of testing labs near site
   B. Lowest-bid contractors with low capacity and unrealistic prices
   C. Too much use of quality standards
   D. Very strong penalties
   Answer: B. Lowest-bid, low-capacity contractors, along with weak supervision, poor design and funding delay, harm quality. (Key point: Factors affecting quality in Nepal)

## Related in Project Engineering

- [QA vs QC; types of cost of quality](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aqa-vs-qc-cost-of-quality) — Project Engineering, chapter 4, asked 2×
- [Quality; QA vs QC; site engineer steps](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aquality-qa-qc-site-engineer-steps) — Project Engineering, chapter 4
- [Differentiate quality control and assurance](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aqa-vs-qc-differentiate) — Project Engineering, chapter 4
- [Control cycle; quality control factors](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Acontrol-cycle-quality-control-factors) — Project Engineering, chapter 4, asked 2×
- [Monitoring vs evaluation; quality control tools](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Amonitoring-vs-evaluation-quality-tools) — Project Engineering, chapter 4
- [Risk sources in over-budget, delayed projects of Nepal](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Arisk-sources-nepal-delayed-projects) — Project Engineering, chapter 5

## Related in other subjects

- [QA and QC for a successful project](https://www.bctengineer.com/question.md?key=semester_7%2Fict_project_management%3Aqa-qc-successful-project) — ICT Project Management, chapter 10
- [QC, QA, TQC and TQM compared](https://www.bctengineer.com/question.md?key=semester_3%2Fmetrology%3Aquality-control-vs-assurance-tqm) — Metrology, chapter 15
- [Software quality assurance](https://www.bctengineer.com/question.md?key=semester_5%2Fsoftware_engineering%3Asqa-note) — Software Engineering, chapter 9
- [Quality assurance](https://www.bctengineer.com/question.md?key=semester_7%2Fict_project_management%3Aquality-assurance) — ICT Project Management, chapter 10