title: "Double surface treatment materials and procedure"
subject: "Transportation Engineering II"
chapter: 3
key: "semester_7/transportation_engineering_ii:double-surface-treatment-material-procedure"
source: https://www.bctengineer.com/q/semester_7/transportation_engineering_ii/double-surface-treatment-material-procedure
site: BCT Engineering
---

# Double surface treatment materials and procedure

Transportation Engineering II · Chapter 3: Road Construction Technology

- Asked in: 2076 Asoj, 8 marks
- Video: [Single and Multiple Surface Treatments](https://www.youtube.com/watch?v=ci7y36KkWFI) — PublicResourceOrg
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/transportation_engineering_ii/double-surface-treatment-material-procedure
- Whole chapter: https://www.bctengineer.com/md/semester_7/transportation_engineering_ii/chapter-3

## Question

Write down material selection and construction procedure of double surface treatment pavement.

## Short answer

Double surface treatment uses two coats: first about 1.2 kg/m2 bitumen with 13.2 mm chips, second about 1.0 kg/m2 with 11.2 mm chips; aggregate must be clean, AIV below 30%. Procedure: clean and prime base, spray first binder, spread chips, roll, repeat second coat, final roll, open after 24 hours.

## Answer

**Double bituminous surface dressing (DBSD)** is a surface treatment of two successive applications of bitumen and stone chips on a prepared WBM or granular base, forming a 20-25 mm waterproof wearing surface (IRC:17 and IRC:23; Nepal DoR "Standard Specifications for Road and Bridge Works"). It is used for low-cost roads.

**Materials**
- **Binder**: bitumen 80/100 or 60/70, cutback or emulsion; typical rates are about 1.2 kg/m2 for the first coat (with 13.2 mm chips) and about 1.0 kg/m2 for the second coat (with 11.2 mm chips), as fixed by the specification.
- **Aggregate**: crushed stone or gravel, AIV below 30 percent, flakiness below 25 percent, water absorption below 1 percent, stripping value below 5 percent; first coat 13.2 mm (about 0.15 m3 per 10 m2); second coat 11.2 mm or 6.7 mm (about 0.09 m3 per 10 m2).
- **Prime coat** over a WBM base if required: 0.6-1.0 kg/m2 of cutback or emulsion.

**Construction procedure**
1. Prepare the base: sweep and clean it, fill all depressions, patch potholes and ensure the correct camber. Apply a prime (or tack) coat and let it cure.
2. Spray the first coat of binder with a pressure distributor at the specified rate and spraying temperature (about 150-170 C for paving bitumen; lower for cutback, and emulsion is sprayed cold or warm), as a uniform film, one lane width at a time.
3. Immediately spread the first-coat chippings (13.2 mm) by chip spreader or manually, covering 100 percent of the binder without piling.
4. Roll with an 8-10 t roller, moving from the edge to the centre; brush off surplus chips.
5. Apply the second coat of binder and the smaller chips (11.2 mm) in the same way, then roll.
6. Do the final rolling with a pneumatic roller and sweep off loose chips; open to traffic after 24 hours at low speed (20 km/h) for a few days.
7. Quality control: bitumen temperature and rate of spread (tray test), chip spread rate, grading, cleanness and surface regularity.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. What is DBSD?
   A. Two successive applications of bitumen and chips on a prepared base forming a 20-25 mm wearing surface
   B. A 100 mm hot mix layer
   C. A single coat of cement slurry
   D. Penetration macadam with grouting
   Answer: A. Double surface treatment applies binder and chips twice to give a thin waterproof surface. (Key point: Definition of DBSD)

2. Which aggregate requirements apply to DBSD?
   A. AIV below 30 percent, flakiness below 25 percent, stripping value below 5 percent
   B. AIV above 50 percent, flakiness above 40 percent
   C. Any gravel with clay coating
   D. Only sand below 2 mm
   Answer: A. Chips must be hard, cubical and resistant to stripping: AIV below 30, flakiness below 25, absorption below 1, stripping below 5 percent. (Key point: Aggregate quality limits)

3. What are the typical binder rates for the two coats?
   A. About 1.0 kg/m2 first, 1.2 kg/m2 second
   B. About 1.2 kg/m2 first and 1.0 kg/m2 second
   C. About 5 kg/m2 each
   D. About 0.2 kg/m2 each
   Answer: B. The first coat takes about 1.2 kg/m2 with 13.2 mm chips, the second about 1.0 kg/m2 with 11.2 mm chips. (Key point: Binder rates)

4. At what temperature is the binder sprayed by pressure distributor?
   A. 50-70 C
   B. 90-100 C
   C. 150-170 C
   D. 220-250 C
   Answer: C. The binder is sprayed at 150-170 C in a uniform sheet within one lane width at a time. (Key point: Binder spraying)

## Related in Transportation Engineering II

- [WBM: material, equipment, procedure, quality control](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Awbm-materials-equipment-quality-control) — Transportation Engineering II, chapter 3
- [Road construction equipment and DBSD procedure](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Aequipment-plants-activities-dbsd) — Transportation Engineering II, chapter 3
- [Bituminous pavement types; asphalt concrete construction](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Atypes-bituminous-pavement-ac-construction) — Transportation Engineering II, chapter 3
- [Surface dressing and DBSD construction](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Asurface-dressing-dbsd-procedure) — Transportation Engineering II, chapter 3
- [Rolled vs normal concrete; CC pavement construction](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Arolled-concrete-cc-pavement-construction) — Transportation Engineering II, chapter 3
- [Rigid pavement thickness by IRC procedure](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Arigid-thickness-irc-procedure) — Transportation Engineering II, chapter 2

## Related in other subjects

- [Anti-termite treatment procedure](https://www.bctengineer.com/question.md?key=semester_3%2Fcivil_engineering_materials%3Aantitermite-procedure) — Civil Engineering Materials, chapter 9, asked 3×
- [Post construction anti-termite treatment](https://www.bctengineer.com/question.md?key=semester_3%2Fcivil_engineering_materials%3Apost-construction-antitermite) — Civil Engineering Materials, chapter 9
- [Materials in pavement layers](https://www.bctengineer.com/question.md?key=semester_6%2Ftransportation_engineering_i%3Apavement-layer-materials) — Transportation Engineering I, chapter 6
- [Equipment for highway and pavement construction](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Ahighway-pavement-equipment) — Construction Management, chapter 4, asked 3×