# WBM: material, equipment, procedure, quality control

Transportation Engineering II · Chapter 3: Road Construction Technology

- Asked in: 2082 Baisakh, 8 marks
- Video: [Quality Control during Road Construction - Part 2 Granular subbase and base layers, MoRTH and MoRD](https://www.youtube.com/watch?v=SKmL_XXqCEc) — Transportation Engg Talks | Satish IITR
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_7/transportation_engineering_ii/wbm-materials-equipment-quality-control
- Whole chapter: https://www.bctengineer.com/md/semester_7/transportation_engineering_ii/chapter-3

## Question

Write down the material, equipment, construction procedure and quality control for water bound macadam pavement.

## Short answer

WBM uses graded crushed coarse aggregate (Grading 1–3), screenings (13.2/11.2 mm), binding material, water. An 8–10 t roller and grader are used. Spread coarse aggregate, dry roll, add screenings in stages with wet rolling till slurry waves, set 1–2 days. Quality control: LAA<40%, AIV<30%, flakiness<15%, thickness, camber, evenness ≤12 mm under straight edge.

## Answer

**Water Bound Macadam (WBM)** is a base or surfacing course of clean crushed stone aggregate of graded sizes, bound by screenings, binding material and water, and compacted by rolling (IRC:19 and MoRTH Section 404; used in Nepal DoR specifications for base courses).

**Materials**
- **Coarse aggregate**: hard, tough crushed stone (Los Angeles abrasion value below 40 percent and aggregate impact value below 30 percent for base; up to 50 and 40 percent for sub-base), flakiness index below 15 percent, in three gradings: Grading 1 (90-45 mm), Grading 2 (63-45 mm) and Grading 3 (53-22.4 mm).
- **Screenings**: crushed stone of 13.2 mm (Type A) or 11.2 mm (Type B) nominal size to fill the voids in the coarse aggregate; non-plastic moorum or gravel (liquid limit below 20, plasticity index below 6) may be used where economical.
- **Binding material**: a small quantity of fine material such as crusher dust or moorum (PI below 6 percent), used only if needed to bind the screenings.
- **Water**: clean and free from salts.

**Equipment**: three-wheel power roller (8-10 t) or vibratory roller (8-10 t), motor grader or spreader, water tanker, brooms, screening spreaders.

**Construction procedure**
1. Prepare the base: clean it, trim it to profile and fill depressions; provide lateral confinement by building the shoulders (or kerbs) along both edges to the thickness of the layer.
2. Spread the coarse aggregate to a uniform thickness and the correct camber by stone spreader or manually. The compacted thickness of one layer is 100 mm for Grading 1 and 75 mm for Gradings 2 and 3; the loose depth is about 1.25-1.30 times this.
3. Dry rolling: roll from the edges to the centre with an 8-10 t roller until the aggregate is firmly keyed (no creep ahead of the roller).
4. Apply the screenings gradually in 3 or 4 stages, with dry rolling and sweeping, so that the voids are filled.
5. Sprinkle water on the surface and roll; the slurry formed by the screenings and water fills the voids and binds the stone. Continue wet rolling until a wave of slurry forms ahead of the roller wheels.
6. Apply binding material (if required), sprinkle water, roll, and let the surface dry overnight.
7. Allow the layer to dry and set (1 to 2 days, with no traffic) before laying the next layer or the surface treatment/premix carpet.

**Quality control**: aggregate tests (LAA, AIV, flakiness, water absorption, soundness), grading of aggregate and screenings, thickness and camber checks with a template, density by sand replacement, surface regularity by straight edge (max 12 mm undulation), and tests every 100-200 m.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. What requirement applies to the screenings in WBM?
   A. PI above 20 percent for better binding
   B. Non-plastic with plasticity index below 6 percent
   C. Any clay is acceptable
   D. Must be 90 mm size
   Answer: B. Screenings of 13.2 mm stone dust must be non-plastic so the layer does not soften when wet. (Key point: Screenings quality)

2. What layer thickness is spread in one WBM layer?
   A. 75 mm compacted, with loose depth 1.25-1.30 times that
   B. 25 mm compacted, loose depth equal
   C. 300 mm compacted in one layer
   D. 150 mm with no allowance for compaction
   Answer: A. The loose depth is larger to allow for reduction by rolling. (Key point: Layer thickness)

3. When is binding material (clay or fine crusher dust) used in WBM?
   A. Always in large quantity
   B. Never, even if the screenings lack fines
   C. Only if the screenings lack fines
   D. Only for the first coat of bitumen
   Answer: C. Binding material is small and only supplementary. (Key point: Binding material)

4. Which checks are part of WBM quality control?
   A. Marshall stability and flow
   B. Slump and cube strength
   C. Bitumen extraction and penetration
   D. Aggregate tests, grading, template check for thickness and camber, sand replacement density, straight-edge regularity
   Answer: D. WBM has no bitumen or cement, so Marshall, slump and extraction tests do not apply. (Key point: Quality control)

## Related in Transportation Engineering II

- [Water bound macadam materials and construction](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Awbm-construction-procedure) — Transportation Engineering II, chapter 3, asked 4×
- [Road construction equipment and DBSD procedure](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Aequipment-plants-activities-dbsd) — Transportation Engineering II, chapter 3
- [Asphalt concrete construction and quality control](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Aasphalt-concrete-construction) — Transportation Engineering II, chapter 3, asked 5×
- [Mass haul diagram and WBM construction](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Amass-haul-wbm-construction) — Transportation Engineering II, chapter 3
- [Bituminous pavement types and quality control](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Atypes-bituminous-pavement-quality-control) — Transportation Engineering II, chapter 3
- [Rolled vs normal concrete; CC pavement construction](https://www.bctengineer.com/question.md?key=semester_7%2Ftransportation_engineering_ii%3Arolled-concrete-cc-pavement-construction) — Transportation Engineering II, chapter 3

## Related in other subjects

- [Equipment for highway and pavement construction](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Ahighway-pavement-equipment) — Construction Management, chapter 4, asked 3×
- [Quality control in urban road construction](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aquality-control-urban-roads) — Project Engineering, chapter 4
- [Macadam versus Telford construction](https://www.bctengineer.com/question.md?key=semester_6%2Ftransportation_engineering_i%3Amacadam-vs-telford) — Transportation Engineering I, chapter 1, asked 2×
- [Macadam road construction method](https://www.bctengineer.com/question.md?key=semester_6%2Ftransportation_engineering_i%3Amacadam-construction) — Transportation Engineering I, chapter 1