# EVA numerical with bar schedule (A to F)

Construction Management · Chapter 7: Controlling Project Integration and Work

- Asked in: 2078 Kartik, 7 marks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_8/construction_management/eva-numerical-2078-kartik
- Whole chapter: https://www.bctengineer.com/md/semester_8/construction_management/chapter-7

## Question

Perform EVA and comment on the performance for the given project.

| Activity | Cost (Rs.) | Planned days (of 1 to 7) |
|---|---|---|
| A | 5000 | 1-2 |
| B | 10000 | 2-5 |
| C | 15000 | 5-6 |
| D | 7000 | 6-7 |
| E | 6000 | 5-6 |
| F | 2000 | 6-7 |

[Figure: bar chart with shaded cells showing the planned days of each activity, as in the table; read from the scan, may be off by a day.]

The progress was monitored and recorded at the end of 5th day.

| Activity | % Completed | Expenditure (Rs) |
|---|---|---|
| A | 100 | 5000 |
| B | 80 | 9000 |
| C | 60 | 8000 |
| D | 0 | X |
| E | 30 | 3500 |
| F | 0 | X |

## Short answer

PV = Rs 25,500; EV = Rs 23,800; AC = Rs 25,500. CV = SV = −Rs 1,700, CPI = SPI = 0.93, EAC ≈ Rs 48,214. The project is over budget and behind schedule by work worth Rs 1,700; if trend continues, final cost will be about Rs 48,214, requiring corrective action.

## Answer

**Assumptions:** the cost of each activity is spread uniformly over its planned (shaded) days, from day 1 to day 7. The review is at the end of day 5. Activities D and F have not started, so their actual cost ("X") is taken as zero.

#### Planned value (PV) at end of day 5
| Activity | Cost (Rs) | Planned days | Days done by day 5 | PV (Rs) |
|---|---|---|---|---|
| A | 5,000 | 1-2 (2 days) | 2 of 2 | 5,000 |
| B | 10,000 | 2-5 (4 days) | 4 of 4 | 10,000 |
| C | 15,000 | 5-6 (2 days) | 1 of 2 | 7,500 |
| D | 7,000 | 6-7 | 0 | 0 |
| E | 6,000 | 5-6 (2 days) | 1 of 2 | 3,000 |
| F | 2,000 | 6-7 | 0 | 0 |
| **Total** | **45,000** | | | **25,500** |

#### Earned value (EV) = % complete × budget
| Activity | % done | Budget | EV (Rs) | AC (Rs) |
|---|---|---|---|---|
| A | 100 | 5,000 | 5,000 | 5,000 |
| B | 80 | 10,000 | 8,000 | 9,000 |
| C | 60 | 15,000 | 9,000 | 8,000 |
| E | 30 | 6,000 | 1,800 | 3,500 |
| **Total** | | | **23,800** | **25,500** |

BAC = 5,000 + 10,000 + 15,000 + 7,000 + 6,000 + 2,000 = Rs 45,000.

#### Variances and indices
$$
\begin{aligned}
CV &= EV - AC = 23{,}800 - 25{,}500 = -1{,}700 \\
SV &= EV - PV = 23{,}800 - 25{,}500 = -1{,}700 \\
CPI &= EV/AC = 23{,}800/25{,}500 = 0.933 \\
SPI &= EV/PV = 23{,}800/25{,}500 = 0.933 \\
EAC &= BAC/CPI = 45{,}000/0.9333 = 48{,}214 \\
VAC &= BAC - EAC = -3{,}214
\end{aligned}
$$

**Answer:** PV = Rs 25,500; EV = Rs 23,800; AC = Rs 25,500; CV = −Rs 1,700; SV = −Rs 1,700; CPI = SPI = 0.93.

**Comment:** The project is over budget by Rs 1,700 and behind schedule by work worth Rs 1,700 (about 7%). Activity E is the main problem (30% done but 58% of its budget spent); B is also overspent. If the same trend continues, the final cost will be about Rs 48,214, i.e. Rs 3,214 above the budget. Corrective action is needed: speed up activities B, C and E, control the cost of E, and re-plan D and F.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. How is the planned value of activity C (Rs 15,000, days 5-6) at end of day 5 found?
   A. Full cost 15,000
   B. Cost spread uniformly over 2 days, 1 day done: 7,500
   C. Zero
   D. 60% of 15,000
   Answer: B. Cost is spread uniformly over planned days; one of two days is done by day 5, so 7,500. (Key point: PV method)

2. Earned value of activity B (budget 10,000, 80% complete) is:
   A. 9,000
   B. 10,000
   C. 8,000
   D. 7,500
   Answer: C. EV = % complete x budget = 0.8 x 10,000 = 8,000 (9,000 is the actual cost). (Key point: EV method)

3. With EV = 23,800, AC = 25,500 and PV = 25,500, CV and SV are:
   A. +1,700 each
   B. -1,700 each
   C. 0 and -1,700
   D. -1,700 and +1,700
   Answer: B. CV = EV - AC = -1,700 and SV = EV - PV = -1,700, so over budget and behind schedule. (Key point: Results)

4. Which activity is the main problem, and what is EAC?
   A. A; Rs 45,000
   B. E (30% done but 58% of budget spent); about Rs 48,214
   C. C; Rs 40,000
   D. F; Rs 50,000
   Answer: B. E spent 3,500 of 6,000 for 30% progress. EAC = 45,000/0.933, about 48,214. (Key point: Forecast and problem activity)

## Related in Construction Management

- [TCTO numerical: least cost schedule, Rs 2000/week](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Atcto-2068-bhadra) — Construction Management, chapter 2
- [TCTO numerical: seven activities, Rs 2000/day](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Atcto-2079-shrawan) — Construction Management, chapter 2
- [EVA numerical with five activities at day 5](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Aeva-numerical-2070-magh) — Construction Management, chapter 7
- [TCTO numerical: lowest cost schedule, Rs 400/week](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Atcto-2075-bhadra) — Construction Management, chapter 2
- [TCTO numerical: seven activities, Rs 1000/day](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Atcto-2070-magh) — Construction Management, chapter 2
- [TCTO numerical with time-cost chart (five activities)](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Atcto-2079-jestha) — Construction Management, chapter 2

## Related in other subjects

- [EVA application; 35 days, Rs 8,00,000 spent](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeva-applicable-monitoring-numerical-b82) — Project Engineering, chapter 4
- [EVA; 10 days, 50 labour days at Rs 1000](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeva-numerical-labour-days-1000) — Project Engineering, chapter 4, asked 2×
- [EVA; 10 days, 100,000, day 6, Rs 65,000](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeva-numerical-day6-65000-k80) — Project Engineering, chapter 4
- [EVA; 60 days, 25% work, Rs 12,00,000](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Aeva-numerical-60-days-25-percent) — Project Engineering, chapter 4