# Muster roll for user's committee project

Construction Management · Chapter 8: Site Management

- Asked in: 2077 Chaitra, 2 marks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_8/construction_management/muster-roll-user-committee
- Whole chapter: https://www.bctengineer.com/md/semester_8/construction_management/chapter-8

## Question

Prepare a typical muster roll used in a construction project executed through user's committee.

## Short answer

A muster roll records daily-wage labour attendance for a pay period, with columns for worker name, father's name/citizenship no., category, daily attendance (P/A), days worked, rate, and amount. It includes project details, total, signatures of preparer, checker, verifier, and approver, and a certificate of work and payment.

## Answer

A **muster roll** for a user's committee project is prepared for each pay period for the daily-wage labour employed directly by the committee (community participation).

**Muster roll**

Name of project: ................................  User's Committee: ................................  Ward/Municipality: ................
Period: from ......... to .........   Roll no.: ......   Date: ......

| S.N. | Name of worker | Father's name / Citizenship no. | Category (skilled / unskilled) | Sun | Mon | Tue | Wed | Thu | Fri | Days worked | Rate/day (Rs) | Amount (Rs) | Signature / thumb |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | | | | | | | | | | | | | |
| 2 | | | | | | | | | | | | | |
| 3 | | | | | | | | | | | | | |
| | **Total** | | | | | | | | | | | | |

Notes: mark attendance as P/A; show deductions (if any) and the net payment; the preparing technician signs.

Prepared by (Technician): ............  Checked by (Engineer): ............  Verified by (Secretary/Treasurer): ..........  Approved by (Chairperson): ...........

Certificate: Certified that the workers named above worked on the days shown and were paid the amounts mentioned.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. For whom is a user's committee muster roll prepared?
   A. Daily-wage labour employed directly by the committee
   B. Consultant staff
   C. Material suppliers
   D. The contractor's permanent staff
   Answer: A. It records daily-wage labour engaged directly by the committee for each pay period. (Key point: Purpose)

2. Which column set belongs in the muster roll?
   A. Drawing number and revision
   B. Days worked, rate per day, amount and signature/thumb
   C. Test result and grade
   D. Bid price and bond
   Answer: B. The roll shows attendance, days worked, rate, amount and the worker's signature or thumb impression. (Key point: Contents)

3. What does the certification on the roll state?
   A. That the materials were tested
   B. That the design is approved
   C. That the tender is valid
   D. That the named workers worked the days shown and were paid the amounts
   Answer: D. The roll certifies the workers worked on the days shown and were paid the stated amounts. (Key point: Certification)

## Related in Construction Management

- [Muster roll and its importance](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Amuster-roll-importance) — Construction Management, chapter 8, asked 3×
- [Short note: Measurement book and muster roll](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Ameasurement-book-muster-roll-note) — Construction Management, chapter 8
- [Typical job layout of a building project](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Atypical-job-layout-building) — Construction Management, chapter 6, asked 4×
- [Equipment used in hydropower construction](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Ahydropower-equipment) — Construction Management, chapter 4
- [Characteristics of a construction project](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Aconstruction-project-characteristics) — Construction Management, chapter 1
- [Prepare tender notice for commercial complex](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Aprepare-tender-notice-100mln) — Construction Management, chapter 5

## Related in other subjects

- [Agenda and minutes of construction committee](https://www.bctengineer.com/question.md?key=semester_5%2Fcommunication_english%3Aminutes-construction-committee-meeting) — Communication English, chapter 5
- [Prepare AOC, BOQ and summary of cost](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aaoc-boq-summary-numerical) — Estimating and Costing, chapter 2
- [Terminology used in stair construction](https://www.bctengineer.com/question.md?key=semester_6%2Fbuilding_technology%3Astair-terminology) — Building Technology, chapter 5
- [Internal risk of Nepalese construction project](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Arisk-internal-construction-nepalese-company) — Project Engineering, chapter 5