# Scope of CM and project life cycle phases

Construction Management · Chapter 1: Construction Management Framework

- Asked in: 2075 Bhadra, 2 marks; 2073 Magh, 6 marks; 2070 Bhadra, 5 marks; 2072 Asoj (asked 4 times)
- Video: [How To Manage A Construction Project Step By Step](https://www.youtube.com/watch?v=PDAmTebSIv8) — Jason Schroeder
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_8/construction_management/scope-lifecycle-phases
- Whole chapter: https://www.bctengineer.com/md/semester_8/construction_management/chapter-1

## Question

Discuss the scope of construction management and the phases of the construction project life cycle.

## Short answer

Construction management covers planning, scheduling, resource, cost, quality and contract management. The project life cycle consists of conception, planning/design, procurement, construction, commissioning and handover, and operation/maintenance.

## Answer

**Construction management** is the planning, organising, coordinating and controlling of resources (men, materials, machines, money and methods) to complete a project in time, within budget and to the required quality and safety.

#### Scope of construction management
- Project feasibility and cost estimating
- Planning and scheduling (bar chart, CPM, PERT)
- Resource management: material, equipment, labour and finance
- Contract and procurement management
- Site management, quality, safety and environment
- Cost control, progress monitoring and cash flow
- Risk and claims management
- Handover, operation and maintenance

#### Phases of the construction project life cycle
```text
 Conception -> Planning/Design -> Procurement
      -> Construction -> Commissioning/Handover
                 -> Operation & Maintenance
```
1. **Conception / initiation:** need identification, pre-feasibility, feasibility, site selection and budget.
2. **Planning and design:** preliminary then detailed design, drawings, specifications, cost estimates, work programme and approvals.
3. **Procurement:** preparing tender documents, tendering, evaluation, award and contract signing.
4. **Construction (execution):** mobilisation, execution of work, monitoring of time, cost and quality, payments.
5. **Commissioning and handover:** testing, completion certificate, defects liability period, as-built drawings.
6. **Operation and maintenance (closing):** use of the facility, routine and periodic maintenance, and final evaluation.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Construction management is best described as:
   A. Only designing the structure
   B. Planning, organising, coordinating and controlling resources to finish in time, budget and quality
   C. Only supervising labour on site
   D. Only preparing tender documents
   Answer: B. It is the planning, organising, coordinating and controlling of resources to meet time, cost, quality and safety targets. (Key point: Definition)

2. Which is the correct order of life cycle phases?
   A. Procurement, conception, design, construction
   B. Conception, procurement, planning/design, construction
   C. Conception, planning/design, procurement, construction, handover, O&M
   D. Planning/design, construction, procurement, handover
   Answer: C. The order is conception, planning/design, procurement, construction, commissioning/handover, then operation and maintenance. (Key point: Life cycle order)

3. Which activity belongs to the procurement phase?
   A. Feasibility study
   B. Tendering, evaluation, award and contract signing
   C. Testing and as-built drawings
   D. Routine maintenance
   Answer: B. Procurement covers tender documents, tendering, evaluation, award and signing of contract. (Key point: Procurement phase)

4. Which belongs to commissioning and handover?
   A. Site selection
   B. Mobilisation
   C. Completion certificate, defects liability period and as-built drawings
   D. Detailed design
   Answer: C. Testing, completion certificate, defects liability and as-built drawings mark handover. (Key point: Handover phase)

## Related in Construction Management

- [Function of project management in Nepal](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Acpm-function-nepal) — Construction Management, chapter 1
- [Characteristics of a construction project](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Aconstruction-project-characteristics) — Construction Management, chapter 1
- [Define construction management and its need](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Adefine-cm-need-knowledge) — Construction Management, chapter 1
- [Work scope control](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Awork-scope-control) — Construction Management, chapter 7, asked 3×
- [Cash flow management: importance and preparation](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Acash-flow-importance-preparation) — Construction Management, chapter 6, asked 8×
- [How CM helps with delay, quality and cost](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Acm-course-delay-cost) — Construction Management, chapter 1

## Related in other subjects

- [Project life cycle phases and activities](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Alife-cycle-phases-activities) — Project Engineering, chapter 1, asked 5×
- [Project development life cycle phases](https://www.bctengineer.com/question.md?key=semester_7%2Fict_project_management%3Aproject-development-life-cycle) — ICT Project Management, chapter 1
- [Life cycle phases and goal setting example](https://www.bctengineer.com/question.md?key=semester_7%2Fproject_engineering%3Alife-cycle-phase-goal-example) — Project Engineering, chapter 1
- [Product versus project life cycle](https://www.bctengineer.com/question.md?key=semester_7%2Fict_project_management%3Aproduct-vs-project-life-cycle) — ICT Project Management, chapter 4