# TCTO numerical with time-cost chart (five activities)

Construction Management · Chapter 2: Construction Planning and Scheduling

- Asked in: 2079 Jestha, 8 marks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_8/construction_management/tcto-2079-jestha
- Whole chapter: https://www.bctengineer.com/md/semester_8/construction_management/chapter-2

## Question

Perform time-cost trade-off based on given information regarding a project comprising five different activities. Also, draw the time-cost trade-off chart. Take time dependent cost per week of Rs 1.6 thousand.

| Activity | Predecessors | Time (Week) Normal | Time (Week) Crash | Cost (Thousand Rs.) Normal | Cost (Thousand Rs.) Crash |
|---|---|---|---|---|---|
| A | - | 26 | 18 | 4 | 20 |
| B | - | 28 | 22 | 5 | 20 |
| C | A | 10 | 5 | 6 | 11 |
| D | A | 4 | 2 | 8 | 11 |
| E | B, D | 12 | 6 | 3 | 14 |

## Short answer

Time-cost trade-off crashes the cheapest critical activity per week while saving Rs 1.6 thousand/week indirect. Normal 42 weeks at Rs 93.2k. Optimum: 40 weeks, total cost Rs 93,000. Minimum duration: 28 weeks at Rs 113.8k.

## Answer

#### Given data and method
Indirect cost = 1.6 thousand Rs/week. Time-cost trade-off (TCTO) crashes the activities on the critical path, one time-unit at a time, always choosing the cheapest cost slope, as long as the saving in indirect cost is more than the extra direct cost. To draw the full trade-off chart, crashing is continued to the minimum possible duration.

$$
\text{Cost slope}=\frac{\text{Crash cost}-\text{Normal cost}}{\text{Normal duration}-\text{Crash duration}}
$$

| Activity | Normal dur | Crash dur | Normal cost | Crash cost | Slope |
|---|---|---|---|---|---|
| A | 26 | 18 | 4 | 20 | 2 |
| B | 28 | 22 | 5 | 20 | 2.5 |
| C | 10 | 5 | 6 | 11 | 1 |
| D | 4 | 2 | 8 | 11 | 1.5 |
| E | 12 | 6 | 3 | 14 | 1.83 |

#### Paths at normal duration
- A-C = 36 weeks
- A-D-E = 42 weeks
- B-E = 40 weeks

Critical activities (on the longest path or paths): A, D, E; normal duration = 42 weeks; normal direct cost = 26 thousand Rs.

#### Crashing, step by step (costs in thousand Rs)
| Step | Crash (by 1 unit) | Slope/cost | Duration | Direct | Indirect | Total |
|---|---|---|---|---|---|---|
| 0 | - | - | 42 | 26.00 | 67.2 | 93.20 |
| 1 | D | 1.5 | 41 | 27.50 | 65.6 | 93.10 |
| 2 | D | 1.5 | 40 | 29.00 | 64.0 | 93.00 |
| 3 | E | 1.83 | 39 | 30.83 | 62.4 | 93.23 |
| 4 | E | 1.83 | 38 | 32.67 | 60.8 | 93.47 |
| 5 | E | 1.83 | 37 | 34.50 | 59.2 | 93.70 |
| 6 | E | 1.83 | 36 | 36.33 | 57.6 | 93.93 |
| 7 | C+E | 2.83 | 35 | 39.17 | 56.0 | 95.17 |
| 8 | C+E | 2.83 | 34 | 42.00 | 54.4 | 96.40 |
| 9 | A+B | 4.5 | 33 | 46.50 | 52.8 | 99.30 |
| 10 | A+B | 4.5 | 32 | 51.00 | 51.2 | 102.20 |
| 11 | A+B | 4.5 | 31 | 55.50 | 49.6 | 105.10 |
| 12 | A+B | 4.5 | 30 | 60.00 | 48.0 | 108.00 |
| 13 | A+B | 4.5 | 29 | 64.50 | 46.4 | 110.90 |
| 14 | A+B | 4.5 | 28 | 69.00 | 44.8 | 113.80 |

(At 40 weeks A-D-E and B-E are both critical and D is fully crashed, so E, common to both, is crashed. At 36 weeks A-C also becomes critical, so C+E is the cheapest cut of all three paths. At 34 weeks D and E are at their crash limits, so A and B must be crashed together. At 28 weeks B and E are both fully crashed, so B-E cannot be shortened further.)

#### Result
- **Optimum (minimum-cost) schedule:** duration 40 weeks, direct cost 29 + indirect 64 = **93 thousand Rs**.
- Activities crashed at the optimum: D by 2. Durations: A=26, B=28, C=10, D=2, E=12.
- Crashing beyond 40 weeks costs more than the Rs 1.6 thousand/week saved (E slope 1.83 > 1.6), so the total cost rises.
- **Minimum possible duration:** 28 weeks, with total cost 113.8 thousand Rs (direct 69 + indirect 44.8).

#### Time-cost trade-off chart (total cost against duration)
```text
 Duration   Total cost (Rs '000); bar length = cost above 90
 (weeks)
  42 | ###### 93.20  (normal)
  41 | ###### 93.10
  40 | ###### 93.00  <-- minimum total cost (optimum)
  39 | ###### 93.23
  38 | ####### 93.47
  37 | ####### 93.70
  36 | ######## 93.93
  35 | ########## 95.17
  34 | ############# 96.40
  33 | ################### 99.30
  32 | ######################## 102.20
  31 | ############################## 105.10
  30 | #################################### 108.00
  29 | ########################################## 110.90
  28 | ################################################ 113.80  (crash)
```
On graph paper, plot direct cost (falling with duration), indirect cost (a straight line rising at 1.6 per week) and their sum; the total cost curve is lowest at 40 weeks.

**Answer: optimum duration 40 weeks; minimum total cost Rs 93.0 thousand (direct 29.0 + indirect 64.0). The shortest possible duration is 28 weeks, at a total cost of Rs 113.8 thousand.**

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Which path is critical and how long is it?
   A. A-C, 36 weeks
   B. A-D-E, 42 weeks
   C. B-E, 40 weeks
   D. A-D-E, 40 weeks
   Answer: B. A-D-E = 26+4+12 = 42 weeks. (Key point: Critical path)

2. What is D's cost slope?
   A. 1.5 thousand per week
   B. 2 thousand
   C. 1 thousand
   D. 2.5 thousand
   Answer: A. (11-8)/(4-2) = 1.5. (Key point: Slope of D)

3. Why is crashing stopped after D by 2 weeks?
   A. E's slope 1.83 exceeds the 1.6 saved per week
   B. D is at crash limit and E is cheaper
   C. A has the lowest slope
   D. B-E becomes longer
   Answer: A. Crashing E costs more than the weekly indirect saving; D is also at its limit. (Key point: Stop rule)

4. What is the optimum?
   A. 42 weeks, 93.2
   B. 40 weeks, 93.0 thousand
   C. 38 weeks, 93.47
   D. 28 weeks
   Answer: B. At 40 weeks, direct 29 + indirect 64 = 93 thousand. (Key point: Optimum)

## Related in Construction Management

- [TCTO numerical: least cost schedule, Rs 2000/week](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Atcto-2068-bhadra) — Construction Management, chapter 2
- [TCTO numerical: lowest cost schedule, Rs 400/week](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Atcto-2075-bhadra) — Construction Management, chapter 2
- [TCTO numerical: optimal crashed time, Rs 2500/week](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Atcto-2078-chaitra) — Construction Management, chapter 2, asked 2×
- [TCTO numerical: optimal crashed time, Rs 3000/week](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Atcto-2073-magh) — Construction Management, chapter 2, asked 2×
- [TCTO numerical: seven activities, Rs 225/day](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Atcto-2078-kartik) — Construction Management, chapter 2
- [TCTO numerical: seven activities, Rs 1000/day](https://www.bctengineer.com/question.md?key=semester_8%2Fconstruction_management%3Atcto-2070-magh) — Construction Management, chapter 2

## Related in other subjects

- [Independent events; computer errors per week](https://www.bctengineer.com/question.md?key=semester_5%2Fprobability_and_statistics%3Aindependent-events-computer-errors) — Probability and Statistics, chapter 1, asked 2×
- [Aeroplane angle of attack and take-off power](https://www.bctengineer.com/question.md?key=semester_3%2Ffluid_mechanics%3Aaeroplane-angle-of-attack-power) — Fluid Mechanics, chapter 9